A free course by Xerox Builders · Instructor: Mandeep Singh, Licensed Residential Builder · All 20 chapters
Opening
Welcome to Chapter Nine of Running a Residential Build in BC, Start to Finish. This chapter is about Construction Financing and Cash Flow. I am Mandeep Singh, a licensed residential builder in British Columbia. More construction businesses fail because they run out of cash than because they build badly. In this chapter, we look at how construction lenders work, how draws and inspections work, and how a builder keeps cash flowing through every stage of a project. This is general information. For your own situation, talk to your lender, your accountant, and where needed, a lawyer.
Quick recap of Chapter 8
Let’s quickly recap Chapter Eight.
Check every trade — licences, WorkSafeBC, insurance
We check every trade properly: licences or certification, Work Safe BC clearance before and after, insurance and references.
Clear scopes and written agreements
We use clear scopes, a responsibility matrix, and a written agreement for every trade.
Pay on time — and keep good trades
And we pay on time, every time, to keep good trades working for us. Today, we look at where that money comes from.
By the end of this chapter you will be able to:
Here are the learning outcomes for this chapter.
Explain how construction loans work
One. Explain how construction loans work, and how they differ from a regular mortgage.
Prepare what a lender needs — and support the client’s financing
Two. Prepare what a lender needs, and support your client’s financing application.
Manage draws, lender inspections and holdbacks
Three. Manage draws, lender inspections, and lender holdbacks.
Build and use a cash flow forecast
Four. Build and use a cash flow forecast for each project and for your business.
Understand the extra risks of spec and multi-unit projects
Five. Understand the extra financing risks of building for sale, and of multi unit projects.
Protect your business — taxes, trust money and reserves
And six. Protect your business: taxes, trust money, and cash reserves.
Part 1 — How construction loans work
Construction loan vs. regular mortgage
A construction loan is different from the regular mortgage most people know.
A regular mortgage — the full amount at once, on a finished home
With a regular mortgage, the lender advances the full amount at once, secured by a finished home that already has a clear value.
A construction loan — money released in stages as the home is built
With a construction loan, the lender releases money in stages, called draws, as the home is built. The security, the house, does not exist yet, so the lender protects itself by paying only for work already in place.
Interest on what’s been drawn — often interest-only
Interest is usually charged only on the amount drawn so far, and often only interest is paid during construction.
Converted or replaced at completion
At completion, the construction loan is usually converted to, or replaced by, a regular mortgage, or paid off from the sale of the home.
Because of the risk, lenders ask for more
Because construction loans carry more risk, lenders ask for more information, and control the money more closely. As the builder, you need to understand exactly how that works.
Key financing terms
Let’s make sure we understand some common financing terms.
Equity — the owner’s own money and land value
Equity is the owner’s own stake in the project: their cash, and the value of their land.
Loan-to-cost and loan-to-value
Loan to cost compares the loan to the total project cost. Loan to value compares the loan to the appraised value. Lenders limit both.
Draw — a release of loan money
A draw is a release of loan money, usually tied to a stage of construction.
Cost to complete — what it will take to finish
Cost to complete is the amount still needed to finish the project. Lenders want the remaining loan to cover it.
Holdback — money retained until conditions are met
And a holdback is money retained until certain conditions are met, like the end of the lien period. Knowing these terms helps you talk confidently with lenders and clients.
Where the money comes from
On most projects, the money comes from a combination of sources.
The owner’s equity — land and cash
The owner’s equity: the value of the land they own, and their own cash. Lenders usually require the owner to have a meaningful stake in the project.
The construction loan
The construction loan, released in draws.
Sometimes private or secondary lenders — at higher cost
Sometimes private lenders or a second loan, usually at a higher cost, to fill a gap.
Equity usually goes in first
In many cases, the lender expects the owner’s equity to be used first, before the loan pays for construction. That means the first months of the project may be paid from the client’s own cash.
Understand the client’s full funding plan — before you start
So, before you start, understand the client’s full funding plan: how much cash, how much loan, and when each becomes available.
Types of lenders
Construction financing comes from different kinds of lenders, each with its own approach.
Banks — lower rates, stricter rules
Major banks usually offer lower interest rates, but they have stricter rules about borrowers, builders, budgets and draw procedures.
Credit unions — often flexible, local knowledge
Credit unions are often more flexible, and may understand local markets and smaller builders well.
Private lenders — faster, but more expensive
Private lenders can move faster and accept more risk, but they charge higher rates and fees. They are often used for short periods, or to fill a gap.
Mortgage brokers — help find the right lender
Mortgage brokers help borrowers find the right lender, and can be very useful for construction and multi unit projects, which many lenders do not handle often.
The right lender depends on the project and the borrower
The right lender depends on the project, the borrower, and the timeline. As the builder, it helps to know a few good mortgage professionals you can recommend to clients.
Financing before construction — land and soft costs
Money is needed long before construction starts.
Buying the land — a land loan or the owner’s cash
Buying the land is usually financed by the owner’s cash, or a land loan, which often has higher rates and shorter terms than a home mortgage.
Design, consultants and permits — usually from equity
Design, consultants, permit fees and levies usually come from the owner’s equity, because many construction loans do not fund until the permit is issued.
Carrying costs while waiting for the permit
Interest, property taxes and insurance continue while waiting for the permit, which, as we saw in Chapter Five, can take months.
Plan this phase’s cash — it’s often underestimated
Help your clients plan the cash for this phase. It is often underestimated, and it can drain the money they were counting on for construction.
Financing your own business
Besides project financing, your business needs its own financing.
Working capital — cash to carry projects between payments
Working capital: the cash, or credit, needed to carry projects between payments. Your cash flow forecast tells you how much.
Vehicles and equipment — finance or lease carefully
Vehicles and equipment, which can be financed or leased. Be careful not to take on more monthly payments than your steady income can support.
A business line of credit — arranged in good times
A business line of credit, arranged when your business is doing well. Banks lend most easily to businesses that do not urgently need money.
Keep business and personal finances separate
And keep your business and personal finances separate. It makes your records clear, protects your family, and makes lenders and warranty providers more comfortable.
What lenders usually want to see
Lenders usually want a package of information before approving a construction loan. Much of it comes from the builder.
A detailed budget — the cost to build
A detailed budget, showing the full cost to build, including soft costs and contingency.
The construction contract and the schedule
The signed construction contract, and the construction schedule.
Drawings, the building permit, and the warranty enrolment
The drawings, the building permit or its expected timing, and proof of home warranty enrolment.
Information about the builder — licence, experience, references
Information about the builder: your licence, your experience, past projects, and sometimes references.
Insurance — builder’s risk with the lender named
And insurance: builder’s risk insurance, often with the lender named on the policy.
The appraisal — ‘as complete’ value
Lenders also look at the value of the finished home.
An appraiser estimates the ‘as complete’ value
An appraiser estimates what the home will be worth when it is complete, based on the plans, the specifications, and similar homes nearby.
The loan is limited by value — and by cost
The loan amount is usually limited by both the value and the cost. If the value comes in lower than expected, the loan may be smaller than the client hoped.
A detailed spec helps the appraisal
A detailed specification, with finishes, systems and features clearly listed, helps the appraiser see the real quality of the home.
A gap between cost and loan must be filled with equity
Any gap between the total cost and the loan must be filled with the client’s own money. Discover that gap early, not halfway through construction.
Interest during construction — why it matters
Interest during construction is a real project cost, and it grows over time.
Interest is charged on the amount drawn so far
Interest is charged on the amount drawn so far. Early in the project, the balance is small. Near the end, it is close to the full loan.
It adds up — especially near the end
That means most of the interest is paid in the second half of the project, when the balance is largest.
Delays increase interest — every month
Every month of delay adds another month of interest on a large balance. That is why schedule matters so much to the client.
Include interest in the client’s budget
Make sure interest during construction is included in the client’s overall budget, usually as a soft cost.
Show the client the cost of delay
And help the client understand the cost of delay. It helps them make decisions on time, and understand why you push for a realistic schedule.
Knowledge check
How does a construction loan usually release money?
- All at once at the start
- In stages (draws) as work is completed
- Only at completion
- Weekly, regardless of progress
Show the answer
The answer is: in stages, called draws, as work is completed and confirmed by the lender. The lender pays only for work already in place.
Part 2 — Supporting your client’s financing
The builder’s role in the client’s loan
When a client finances their project, the builder plays an important role, even though the loan is between the client and the lender.
Provide clear, professional documents — fast
Provide clear, professional documents quickly: the budget, the contract, the schedule, and your company information.
Make the budget match what the lender expects
Make sure your budget is organized in a way the lender can understand, often matching their own cost categories or draw stages.
Know the draw schedule before signing
Know the lender’s draw schedule before you sign your contract, so your payment schedule matches, as we discussed in Chapter Seven.
Be available to the lender’s inspector
Be available to the lender’s inspector or cost consultant, and answer their questions honestly.
Never inflate numbers to help a client borrow more
And never inflate the budget or the contract price to help a client borrow more. Misleading a lender is a serious matter, and it can follow you for years.
Questions to ask the client early
Ask your client these questions early, ideally before you sign the contract.
Is the financing approved — or only discussed?
Is the construction financing approved, or only discussed? There is a big difference.
How much equity — and when is it available?
How much of their own money is going into the project, and when is it available?
What’s the draw schedule — and the lender’s holdback?
What is the lender’s draw schedule, and how much will the lender hold back from each draw?
What does the lender need from you — and by when?
What does the lender need from you, the builder, and by when?
Is there a cushion for overruns and changes?
And is there a cushion for changes and overruns? If every dollar is already committed, any change becomes a crisis.
When the client pays without a loan
Some clients pay for their project without a construction loan. It is simpler, but still needs care.
Confirm the money is really available — and when
Confirm that the money is really available, and when. Funds tied up in investments or another property sale may not be available when you need them.
Use the same payment schedule discipline
Use the same payment schedule discipline as with a lender: clear stages, clear invoices, and on-time payment.
Holdbacks still apply
Holdbacks under the Builders Lien Act still apply, even without a lender.
Watch for ‘I’ll pay at the end’
Be careful if a client suggests paying most of the price at the end. You would be financing their project, and carrying all the risk.
Same records, same professionalism
Keep the same records, and the same professionalism. Cash clients deserve the same clarity as financed ones.
Explaining financing to first-time clients
Many clients have never built a home before. A short explanation of how construction financing works helps them a lot.
The loan comes in stages — not all at once
Explain that the loan comes in stages, not all at once, and only for work already completed.
Their own money usually goes in first
Explain that their own money usually goes in first, for land, design, permits, and often the early construction.
Interest grows as the loan grows
Explain that interest grows as the loan grows, so delays near the end are expensive.
Changes may need their own cash
Explain that changes may need to be paid from their own cash, not the loan.
Keep a cushion — for the unexpected
And encourage them to keep a cushion for the unexpected. Clients who understand this at the start make calmer, better decisions throughout the project.
Documents the lender usually needs from you
To keep the client’s financing moving, have these documents ready in a standard format.
Company profile — licence, warranty provider, experience
A short company profile: your builder licence, your warranty provider, years of experience, and a list of completed projects.
Detailed budget — by stage or category
A detailed budget, organized by the lender’s stages or categories.
Signed contract and schedule
The signed contract and the construction schedule.
Insurance certificates
Your insurance certificates, and the builder’s risk policy information.
Permit and warranty enrolment confirmation
Confirmation of the building permit, and the home warranty enrolment. Having these ready makes you look professional, and saves the client weeks.
Working with the client’s mortgage professional
Building a good relationship with your clients’ mortgage professionals helps everyone.
Talk early — before the contract is signed
Talk early, before the contract is signed, to understand the lender’s requirements and the draw schedule.
Agree who sends what — and when
Agree who sends what, and when: the budget, the contract, the draw requests, and updates.
Keep them informed of schedule changes
Keep them informed of schedule changes, so draws can be planned.
Answer questions quickly and accurately
Answer their questions quickly and accurately.
Good relationships bring referrals
And remember that mortgage professionals often refer clients to builders they trust. Being easy to work with is good business.
Scenario: the lender wants contract changes
The situation: The client’s lender reviews your contract and asks for changes: a different payment schedule, and a clause allowing the lender to take over the contract if the client defaults. The client asks you to just sign whatever the lender wants.
Here is a situation that comes up with construction lenders. The client’s lender reviews your contract and asks for changes: a different payment schedule, and a clause allowing the lender to take over the contract if the client defaults. The client asks you to just sign whatever the lender wants. What do you do?
Read the requested changes carefully
First, read the requested changes carefully. Do not sign anything you have not read and understood.
Payment schedule — make sure your cash flow still works
Second, for the payment schedule, check that your cash flow still works. If the new schedule leaves you carrying large costs for long periods, negotiate.
Assignment or takeover clauses — get legal advice
Third, clauses that let a lender take over or assign the contract are common, but they have legal effects. Get legal advice before agreeing.
Agree in writing — and update your forecast
And when it is agreed, put the changes in writing, and update your cash flow forecast to match.
Scenario: the loan comes in short
The situation: The client’s appraisal comes in lower than expected. The approved loan is $150,000 less than the budget requires. Construction is supposed to start in three weeks.
Here is a situation that happens more often than people think. The client’s appraisal comes in lower than expected, and the approved loan is one hundred and fifty thousand dollars less than the budget needs. Construction is supposed to start in three weeks. What do you do?
Don’t start until the full funding is clear
First, do not start until the full funding is clear. Starting a project that is not fully funded puts you, your trades, and the client at serious risk.
Help the client review options: more equity, design or finish changes, phasing
Second, help the client review options: adding more of their own money, changing the design or finishes to reduce cost, or phasing parts of the work, like landscaping or a laneway home.
Update the budget and contract to match any changes
Third, update the budget and the contract to match any changes, in writing.
Get confirmation in writing before mobilizing
And fourth, get written confirmation of the funding before you mobilize trades and order materials. A three week delay is far better than a half-built house with no money.
Part 3 — Draws, inspections and holdbacks
How a draw usually works
Let’s walk through how a typical construction draw works. Each lender has its own process, but the steps are similar.
1 · The work reaches a stage — or the month ends
Step one. The work reaches a draw stage, or the end of a billing period, depending on the lender’s system.
2 · A draw request is submitted — with backup
Step two. A draw request is submitted, usually by the client, with the builder’s invoice and any backup the lender requires.
3 · The lender’s inspector or cost consultant visits
Step three. The lender’s inspector or cost consultant visits the site, and reports on the work completed and the cost to complete.
4 · The lender checks title — and releases funds
Step four. The lender typically checks the title for liens or other problems, and then releases the funds, less any holdback.
5 · The client pays the builder
Step five. The money is paid to the client or their lawyer, and then to the builder, or sometimes directly to the builder, depending on the arrangement. Each step takes days, so plan for the total time.
Planning the draw calendar
Draws take time. Plan a draw calendar for each project.
Map each stage to an expected date
Map each draw stage to its expected completion date, from your construction schedule.
Add the time for request, inspection and funding
Add the time for the request, the inspection, the title check, and the funding. Often a week or two, sometimes more.
Plan your trade payments around it
Plan your trade payments around the expected funding dates, with your line of credit covering short gaps.
Book the inspector early — near the end of each stage
Book the lender’s inspector early, as each stage nears completion, so the inspection happens as soon as the work is done.
Update the calendar when the schedule moves
And update the draw calendar whenever the construction schedule moves.
Knowledge check
What usually happens before a lender releases a draw?
- Nothing — it’s automatic
- An inspection and a title check
- A new building permit
- A client party
Show the answer
The answer is: an inspection by the lender’s inspector or cost consultant, and a title check for liens or other problems.
Stage draws vs. cost-to-complete
Lenders use different methods to decide how much to release.
Stage draws — fixed percentages at milestones
Some lenders use stage draws: fixed percentages of the loan released at milestones, like foundation, framing, lock-up, drywall and completion.
Cost-to-complete — based on actual costs and remaining budget
Others, especially on larger projects, use a cost to complete method. A cost consultant checks the actual costs to date and the cost to finish, and the lender releases money only if the remaining loan is enough to finish the project.
Cost overruns can stop draws
With cost to complete, if the consultant thinks the project will cost more than the budget, the lender may hold back money until the owner adds more equity.
Know which method your client’s lender uses
Know which method your client’s lender uses, and organize your invoices and reports to match it.
A clean draw package
A clean draw package gets paid faster. Here is what it usually includes.
Your invoice — matching the stage or period
Your invoice, matching the draw stage or billing period, with the contract price, changes, previous payments, and holdback shown clearly.
Change orders approved since the last draw
Copies of change orders approved since the last draw.
Photos of the completed work
Photos of the completed work, especially items that will be covered soon.
Inspection results — city and engineers
City inspection results and engineer field review reports for the stage.
Anything the lender’s checklist asks for
And anything else on the lender’s checklist, such as updated insurance or a statutory declaration about payments to trades. Ask for the lender’s checklist at the start, and use it every time.
Working with the lender’s inspector
The lender’s inspector or cost consultant has a big influence on your cash flow. Work with them professionally.
Know when they’re coming — and be there
Know when they are coming, and be there, or have someone there who knows the project.
Have the work truly complete for the stage
Have the work truly complete for the stage being claimed. Partial completion usually means partial payment.
Show them the hidden work — photos and reports
Show them photos and reports of work that is already covered, so they can confirm it.
Explain any changes and their cost
Explain any approved changes, and how they affect the budget.
Respect their role — they protect the lender
And respect their role. They protect the lender, not you, but a builder who is organized and honest makes their job easy, and their reports reflect that.
Lender holdbacks
Lenders often hold back part of each draw. Understand how this affects your cash.
Builders lien holdback — often held by the lender
Many lenders hold back an amount related to the builders lien holdback, often ten percent, until the holdback period has passed with no liens.
Other holdbacks — for incomplete work or deficiencies
Some lenders also hold back money for incomplete work or deficiencies at the end.
Released after conditions are met
These amounts are released after the conditions are met, such as the end of the lien period, or completion of listed items.
Plan your cash for the delay
Plan your cash for the delay. If ten percent of every payment is held back for months, that is a large amount of your money waiting. Your own holdbacks to trades help balance this, but only if you track them properly.
Changes and the lender
When the client makes changes, the lender may need to know.
Changes affect the budget — and the lender’s numbers
Changes affect the budget, and the lender’s numbers. Large changes can affect the cost to complete, and even the appraised value.
Some lenders must approve significant changes
Some lenders require approval of significant changes, especially if they increase the cost.
Who pays for the change — the loan or the client’s cash?
Agree who pays for each change: is it covered by the loan, or must the client pay from their own cash?
Include approved changes in each draw package
Include approved change orders in each draw package, so the lender’s records match yours.
Surprises for the lender slow down the money
Surprises for the lender slow down the money. Keep them informed, through the client, and draws stay on schedule.
The final draw — and completion
The final draw is often the slowest. Plan for it.
Occupancy — and sometimes a final appraisal
The lender usually requires the occupancy permit, and sometimes a final inspection or appraisal.
Completion of deficiencies
They may hold back an amount for deficiencies, until listed items are complete.
Title checks — and the lien period
They check title again, and the builders lien holdback is usually held until the holdback period ends.
Conversion to a regular mortgage — or sale
The construction loan is converted to a regular mortgage, or paid out from a sale, which takes time and paperwork.
Plan your cash for the final months
So plan your cash for the final months, when costs are still being paid, but money arrives slowly. Many builders feel the cash squeeze most at the very end.
Proof of payment to trades
Some lenders want proof that trades and suppliers have been paid before they release more money.
Lenders want to avoid liens
Lenders want to avoid liens on the property they are financing, so they may ask for proof that earlier payments reached the trades.
A declaration or list of payments
This may be a signed declaration, or a list of trades and suppliers with amounts paid. Ask your client’s lender what they require.
Your payment records make this easy
If you follow the payment routine from Chapter Seven, with records for every trade payment and holdback, this is easy to provide.
Never sign a declaration that isn’t true
Never sign a declaration that is not true. Declaring that trades are paid when they are not is a serious matter.
Scenario: the cost consultant says you’re over budget
The situation: The lender’s cost consultant reports that the project’s cost to complete is $60,000 more than the remaining loan. The lender won’t release the next draw until the client adds equity.
Here is a situation on projects with cost monitoring. The lender’s cost consultant reports that the cost to complete is sixty thousand dollars more than the remaining loan. The lender will not release the next draw until the client adds more of their own money. What do you do?
Review the consultant’s numbers — line by line
First, review the consultant’s numbers, line by line, against your own cost report.
Explain anything they’ve misunderstood — with evidence
Second, if they have misunderstood something, like counting a change order twice, or missing costs already paid, explain it with evidence.
If it’s real: client adds funds, or scope is reduced
Third, if the overrun is real, the client may need to add funds, or reduce the remaining scope, through proper change orders.
Keep trades informed — and protect your cash meanwhile
And meanwhile, keep your trades informed, and protect your own cash. Do not keep spending heavily while the draw is stopped.
Scenario: the draw is delayed by a lien
The situation: The lender refuses to release the framing draw. A title search shows a lien filed by a window supplier. Your window installer bought the windows and hasn’t paid the supplier.
Here is a cash flow emergency. The lender refuses to release the framing draw, because a title search shows a lien filed by a window supplier. Your window installer bought the windows, and has not paid the supplier. What do you do?
Act the same day — the whole project’s cash depends on it
First, act the same day. Until the lien is cleared, the lender may not release any more money, and your whole project’s cash flow is stuck.
Get the facts — invoices, payments, holdbacks
Second, get the facts: the supplier’s invoice, what you have paid the installer, and the holdback you have retained.
Resolve with the installer and supplier — properly
Third, resolve it with the installer and the supplier properly, using the holdback where appropriate, and making sure the supplier is paid.
Get legal advice to clear the lien — then review your payment routine
And fourth, get legal advice on clearing the lien from title correctly. Then review your payment routine, so you know your trades are paying their suppliers.
Knowledge check
Under a cost-to-complete method, what can stop a draw?
- Good weather
- A forecast that the project will cost more than the remaining loan
- Too many photos
- A clean site
Show the answer
The answer is: a forecast that the project will cost more than the remaining loan. The lender may hold back money until the owner adds more equity.
Part 4 — Cash flow for the builder
Why profitable builders still run out of cash
Many builders are profitable on paper, but still struggle to pay their bills. Here is why.
Money goes out before it comes in
Money often goes out before it comes in. You pay for excavation, concrete and framing before the first draw arrives.
Holdbacks tie up money for months
Holdbacks tie up a share of every payment for months.
Late client payments and slow draws
Late client payments and slow draws stretch your cash even further.
Overhead continues every month
Your overhead continues every month, whether money arrives or not.
Growth makes it worse — more projects, more cash needed
And growth makes it worse. Taking on more projects at once means more money going out at the same time. Many builders fail in their busiest year.
Profit vs. cash — a simple example
Let’s make the difference between profit and cash very clear with a simple example.
A project shows a healthy profit on paper
Imagine a project that shows a healthy profit on paper when it is finished.
But 10% of every payment is held back
But ten percent of every payment has been held back, and will not arrive until the holdback period ends.
The final draw is delayed by deficiencies
The final draw is delayed, because a few deficiencies are not finished.
And the trades want their final payments now
Meanwhile, the trades want their final payments now.
Profitable — but short of cash for months
The project is profitable, but you are short of cash for months. That is why cash flow planning matters as much as pricing.
Your monthly money meeting
Once a month, hold a short money meeting, with yourself, a partner, or your bookkeeper.
Review each project’s cost report
Review each project’s cost report: budget, committed, actual and forecast.
Update the cash flow forecast
Update the cash flow forecast for every project and the business.
Check taxes, holdbacks and receivables
Check the tax account, the holdbacks owed to you and by you, and any late payments.
Decide on actions — and who does them
Decide on actions: invoices to send, payments to chase, costs to control, and who will do each one.
One hour a month — the best investment you’ll make
One hour a month is one of the best investments a builder can make. It turns money from a worry into a plan.
Building a cash flow forecast
A cash flow forecast shows when money comes in and goes out, month by month. Here is how to build a simple one.
Months across the top — for the whole project
Put the months across the top, for the whole length of the project.
Money in — client payments and draws, with realistic timing
Below that, list money coming in: client payments and draws, in the month you realistically expect to receive them, not the month you invoice.
Money out — trades, suppliers, fees, overhead
Then list money going out: trades, suppliers, fees, and your overhead, in the month you will pay them.
Net cash each month — and the running balance
Calculate the net cash each month, and the running balance. The lowest point of that running balance is how much cash, or credit, you need to get through the project.
Combine all projects — for the business view
Then combine all your projects, plus overhead, to see the whole business. Update it every month.
Example: cash flow on a new house
Let’s walk through a simplified example of cash flow on a new house, without specific numbers.
Months 1–2: deposit in; demolition, excavation, foundation out
In months one and two, the deposit comes in, but demolition, excavation, and foundation costs go out. The running balance often drops.
Month 3: foundation draw arrives — framing costs go out
In month three, the foundation draw arrives, but framing costs are going out at the same time.
Months 4–6: framing, lock-up and rough-in draws — big trade payments
In months four to six, framing, lock-up and rough-in draws arrive, while big trade payments go out. Timing is everything here.
Months 7–8: finishes — many smaller payments, slower draws
In months seven and eight, finishes bring many smaller payments, and draws may slow down as the lender waits for completion.
After completion: holdbacks released — weeks or months later
After completion, the holdbacks are released, often weeks or months later. Seeing this pattern on paper helps you plan your credit and avoid surprises.
Supplier accounts — set them up and keep them
Good supplier accounts are a powerful cash flow tool.
Open accounts with key suppliers — lumber, electrical, plumbing
Open accounts with your key suppliers: lumber yards, and electrical, plumbing and building supply wholesalers.
Credit terms give you time to collect from clients
Credit terms, such as paying thirty days after the end of the month, give you time to collect from your clients first.
Pay on time — every time — to keep the terms
Pay on time, every time, to keep those terms and your credit limit.
Check every invoice against delivery tickets
Check every invoice against the delivery tickets and your purchase orders.
Suppliers can lien too — keep them paid
And remember that suppliers can file liens too. Keeping them paid protects your clients and your reputation.
Tools to manage cash flow
Here are practical tools builders use to manage cash flow.
A payment schedule that front-loads where fair
A payment schedule that collects money before or as costs are incurred, within what is fair and what the lender allows.
Supplier credit terms — and paying on time to keep them
Credit terms with suppliers, for example paying thirty days after delivery, and paying on time to keep those terms.
A business line of credit — for timing gaps, not losses
A business line of credit, arranged before you need it, to cover timing gaps. Use it for timing, not to cover losses.
Invoice promptly — chase payments politely and quickly
Invoice promptly, and follow up on late payments politely but quickly.
Don’t take on more projects than your cash can carry
And do not take on more projects than your cash can carry. Saying no to a project can protect the projects you already have.
Deposits and early costs
The beginning of a project is often the hardest part for cash flow.
Early costs are large — demolition, excavation, foundation
Early costs are large: demolition, excavation, shoring, foundations, and often early orders like windows.
The first draw often comes after the foundation
The first lender draw often comes only after the foundation is complete.
A fair deposit helps — within the rules
A fair deposit, within the consumer protection rules we discussed in Chapter Seven, helps cover the start.
Some early costs can be paid by the client directly — in writing
In some cases, the client may pay certain early costs directly, like a demolition contractor or a hazardous materials removal company, if it is clearly agreed in writing, including responsibility and warranty.
Plan the start — it sets the tone for the whole project
Plan the start carefully. A project that starts with a cash shortage rarely recovers easily.
Warning signs of a cash crunch
Watch for these warning signs. They usually appear weeks before a real crisis.
You’re paying trades late — for the first time
You start paying trades late, for the first time.
You’re using one project’s money for another
You find yourself using one project’s money to pay another project’s bills.
Your line of credit is always near its limit
Your line of credit is always near its limit.
Tax remittances are delayed
G.S.T. or payroll remittances are delayed.
You’re taking new projects just for the deposits
And you are taking on new projects mainly for the deposits. If you see these signs, stop, review your forecast with your accountant, and act early. Problems caught early can usually be fixed.
A simple weekly cash routine
A short weekly cash routine keeps you in control.
Check the bank balances — every project and the business
Check the bank balances for the business, and the tracking for each project.
List what’s due to be paid this week and next
List what is due to be paid this week and next: trades, suppliers, and overhead.
List what’s expected in — and chase anything late
List what money is expected in, and follow up on anything late.
Update the forecast if anything changed
Update the forecast if anything changed: a delayed draw, a new change order, an unexpected cost.
Twenty minutes a week — no surprises
Twenty minutes a week, every week, and cash surprises become rare.
Knowledge check
When is most of the interest on a construction loan paid?
- In the first month
- In the second half — when the balance is largest
- Evenly every month
- After occupancy only
Show the answer
The answer is: in the second half of the project, when the drawn balance is largest. That is why delays near the end are so expensive.
Scenario: three projects start at once
The situation: You win three projects in one month. All three want to start in spring. Your forecast shows that in month two, you’d need far more cash than you have.
Here is a problem many growing builders would like to have. You win three projects in one month, and all three want to start in spring. Your cash flow forecast shows that in month two, you would need far more cash than you have. What do you do?
Celebrate — then plan carefully
First, celebrate, and then plan carefully. This is exactly the moment when growing builders get into trouble.
Stagger the starts — even a few weeks helps
Second, try to stagger the starts. Even a few weeks between projects spreads out the heavy early costs.
Adjust payment schedules and arrange credit in advance
Third, adjust payment schedules where fair, and arrange a line of credit before you need it.
If needed, decline or defer one project
And if the numbers still do not work, decline or defer one project. It is much better to build two projects well than three projects badly, with unpaid trades.
Knowledge check
The lowest point of your running cash balance in the forecast tells you:
- Your profit
- How much cash or credit you need to get through
- Your tax bill
- Nothing useful
Show the answer
The answer is: how much cash, or credit, you need to get through the project. Plan for that number before you start.
Part 5 — Building for sale — spec projects
Spec building — higher reward, higher risk
Some builders build homes to sell, sometimes called spec homes. The financing is very different.
You are the owner — you carry all the risk
On a spec project, you are the owner as well as the builder. You carry the cost risk, the schedule risk, and the market risk.
You need your own equity — usually a lot
Lenders usually require significant equity from you, often the land plus cash.
Interest and carrying costs until it sells
You pay interest and carrying costs, like property taxes and insurance, until the home sells.
Market risk — prices can fall while you build
And there is market risk. Prices and buyer demand can change during the year or two it takes to build and sell.
Start small — and plan for a slow sale
If you build on spec, start small, and plan your finances for a slow sale, not just a fast one.
The numbers for a spec project
Before starting a spec project, work through the numbers carefully.
Expected sale price — realistic, from current sales
The expected sale price, based on current, comparable sales, not hopes.
Minus selling costs — commissions, legal, GST treatment
Minus selling costs: commissions, legal fees, and the effect of G.S.T. on the sale.
Minus land, construction, soft costs and contingency
Minus the land cost, construction cost, soft costs, and contingency.
Minus interest and carrying costs — for a realistic sale time
Minus interest and carrying costs, for a realistic time to sell, not the fastest possible time.
What’s left is the profit — is it worth the risk?
What is left is your profit. Then ask honestly: is this profit worth the risk, and what happens if the price falls by ten or fifteen percent? If the answer is a loss you cannot survive, the project is too risky.
Spec risks you can control
You cannot control the market, but you can control many other risks on a spec project.
Buy the right land at the right price
Buy the right land, at the right price, after proper feasibility, as we covered in Chapter Three.
Design for the buyers in that area
Design for the buyers who actually live in that area, not for your own taste.
Control costs and schedule tightly
Control costs and the schedule tightly. Every month saved is interest saved.
Keep enough reserve to wait for the right buyer
Keep enough reserve to wait for the right buyer, so you are not forced to sell at a bad price.
Don’t put all your money in one project
And do not put all your money in one project. A builder with everything in one spec home has no room for a slow market.
Your first spec project — a careful approach
If you are thinking about your first spec project, here is a careful approach many experienced builders recommend.
Build several projects for clients first
Build several projects for clients first, so you know your real costs, schedule, and trades.
Start with a product you know — in an area you know
Start with a type of home you know well, in an area you know well, where you understand what buyers want and what homes sell for.
Use conservative numbers
Use conservative numbers: a lower sale price, higher costs, and a longer selling time than you hope for.
Keep your client work going
Keep your client work going at the same time, so your business still has income while the spec home is being built and sold.
Get your accountant and lawyer involved before you buy
And involve your accountant and lawyer before you buy the land. A careful first spec project can grow your business. A careless one can end it.
Knowledge check
When testing a spec project’s numbers, you should use:
- The best possible sale price
- Conservative numbers — lower price, higher costs, longer sale time
- Last year’s prices
- The neighbour’s asking price
Show the answer
The answer is: conservative numbers. A lower sale price, higher costs, and a longer selling time. If the project still works with those numbers, the risk is more manageable.
Taxes and rules for selling new homes
Building to sell also brings tax and legal rules. These are complex, so get professional advice.
GST on the sale of a new home
G.S.T. generally applies to the sale of a new home, and how it is handled in the price matters. Rebates may be available to some buyers.
Income tax — business income vs. capital gains
Profits from building and selling homes are usually treated as business income. Get advice on how your situation is taxed.
Home warranty and disclosure
The home must be covered by home warranty, as we covered in Chapter Two, and buyers must receive the required information.
Selling before completion — presales have rules
Selling homes before they are built, often called presales, especially strata units, is regulated, with rules about disclosure and deposits. Get legal advice before marketing a project this way.
Plan these with an accountant and lawyer — before you buy the land
Plan all of this with an accountant and a lawyer before you buy the land, not after.
Selling spec homes — timing and marketing
How and when you sell a spec home affects your cash flow.
Choose an experienced realtor early
Choose an experienced realtor early, ideally during design, to advise on what buyers in that area want.
Plan the listing date — not too early, not too late
Plan the listing date. Listing too early, when the home is still a construction site, can hurt the price. Listing too late adds months of carrying cost.
Good photos, staging and a clear information package
Invest in good photos, staging if appropriate, and a clear package for buyers: the warranty, the specifications, the energy rating, and the features.
Know your lowest acceptable price — before offers arrive
Know your lowest acceptable price before offers arrive, based on your numbers, not emotions.
Plan for the closing timeline
And plan for the closing timeline, because your loan, interest and carrying costs continue until the sale completes.
Partners and investors
Many builders partner with investors to fund projects. This can work well, if it is set up properly.
Agree everything in writing — with a lawyer
Agree everything in writing, with a lawyer: who contributes what, who decides what, and how profits and losses are shared.
Define the builder’s fee — separate from profit share
Define the builder’s fee for construction, separately from any share of profit, so you are paid for your work even if the market turns.
Plan for cost overruns — who pays?
Plan for cost overruns. If more money is needed, who provides it, and what happens if they cannot?
Plan the exit — sale, refinance, or one partner buying out
Plan the exit: how the property is sold or refinanced, and what happens if one partner wants out early.
Friendships and family make agreements MORE important
And remember, as we said about contracts, friendships and family make written agreements more important, not less.
Scenario: the spec home isn’t selling
The situation: Your spec home was finished three months ago. The market has slowed, and there are no offers. Your interest and carrying costs continue every month.
Here is a stressful situation for spec builders. Your spec home was finished three months ago. The market has slowed, and there are no offers. Your interest and carrying costs continue every month. What do you do?
Review the price honestly — against the current market
First, review the price honestly, against the current market, not the market when you started. Talk to experienced realtors.
Improve marketing — and listen to buyer feedback
Second, improve the marketing, and listen to feedback from buyers who viewed the home.
Consider options: rent it, refinance, adjust the price
Third, consider your options: renting the home for a period, refinancing, or adjusting the price. Each has tax and financing implications, so get advice.
Next time: plan for a slow sale before you start
And next time, plan your finances for a slow sale before you start. The builders who survive slow markets are the ones who expected them.
Part 6 — Multi-unit projects and rental housing
Financing multiplexes
With the new zoning rules, many builders and clients are financing multiplexes. Here is what changes.
Bigger budgets — and lenders want more experience
Budgets are bigger, and lenders often want to see more experience from the builder, or a stronger team.
Sell or rent? The financing follows the plan
Whether the units will be sold or rented changes the financing completely, as we discussed in Chapter Three.
Strata sales — presales, deposits and timing
For strata sales, presales and deposits may be part of the plan, with legal rules about how deposits are held.
Rental — long-term lenders look at rents and operating costs
For rental, long term lenders look at expected rents and operating costs, not just construction cost.
Government-backed programs may exist for rental housing
There are federal and provincial programs that support rental housing in various ways. Their rules change, so check the current programs with a mortgage professional who specializes in multi unit projects.
Strata presales and deposits — the basics
If strata units will be sold before or during construction, there are special legal rules.
Marketing strata units before completion is regulated
In BC, marketing strata units before they are completed is regulated. For many developments, the Real Estate Development Marketing Act requires a disclosure statement before units are marketed.
Deposits must be handled properly — usually held in trust
Purchasers’ deposits must be handled properly, usually held in trust, and generally cannot be used freely for construction.
Lenders may require a minimum number of presales
Lenders on larger strata projects may require a minimum number of presales before they will fund construction.
Get a real estate lawyer before you market anything
So before you market anything, get a real estate lawyer who works with developers. Mistakes here can allow buyers to cancel, and can create serious legal problems.
Practical tips for multi-unit financing
Here are practical tips if you or your clients are financing a multi unit project.
Start financing conversations during feasibility
Start financing conversations during feasibility, before the design is finished. The lender’s requirements may affect the design.
Use a mortgage professional with multi-unit experience
Use a mortgage professional with experience in multi unit and construction lending.
Expect cost-to-complete monitoring
Expect more detailed monitoring, often by a cost consultant using the cost to complete method.
Build bigger contingencies — and longer schedules
Build bigger contingencies and longer schedules into the financing plan. Multi unit projects have more unknowns.
Keep impeccable records — from day one
And keep impeccable records from day one. Lenders on larger projects will check everything.
Laneway homes and suites — financing tips
Many clients add a laneway home or a suite to create rental income. Financing has its own questions.
Can the existing mortgage be increased?
Can the client’s existing mortgage be increased, or do they need a separate construction loan?
Lenders may count future rental income — or not
Some lenders may count part of the future rental income when deciding how much to lend. Others may not. A mortgage professional can explain the options.
A laneway home can’t usually be sold separately
Remember that in many areas, like Vancouver’s R one dash one zone, a laneway home cannot be sold separately, which affects how lenders value it.
Check for government programs — they change
From time to time, governments offer programs or incentives for adding rental units. Check what is currently available, because these programs change.
Scenario: rents lower than planned
The situation: A client is building a rental fourplex. Halfway through, local rents have flattened. The long-term lender says the expected rents may not support the planned mortgage.
Here is a multi unit financing problem. A client is building a rental fourplex. Halfway through construction, local rents have flattened. The long term lender says the expected rents may not support the planned mortgage. What can you do as the builder?
Review the numbers with the client and their mortgage professional
First, review the numbers with the client and their mortgage professional. Understand exactly what the lender needs.
Look at the unit mix, finishes and operating costs
Second, look at what you can influence: the unit mix, the finishes, and operating costs like heating and maintenance, which affect the building’s income.
Consider more equity, a different lender, or a different program
Third, the client may need to consider more equity, a different lender, or a different financing program.
Next time: test the plan with lower rents before starting
And next time, test the plan with lower rents and higher interest rates before starting. Projects that work only in the best case are fragile.
Part 7 — Protecting your business
Trust money and separate tracking
We covered this in Chapter Seven, but it is so important for cash flow that we repeat it here.
Project money is generally held in trust for that project’s trades
Under the Builders Lien Act, money received for a project is generally held in trust for the trades and suppliers who worked on that project.
Don’t use project A’s money for project B
Do not use one project’s money to pay another project’s bills, or your personal expenses, while that project’s trades are unpaid.
Track each project separately
Track each project’s money separately, so you can always show where it went.
Pay trades first — profit comes last
Pay the trades and suppliers on each project first. Your profit comes from what is left, at the end.
Set aside taxes — every time money comes in
Taxes cause many builders serious cash problems, because the money is spent before the tax is due.
GST collected is not your money
G.S.T. you collect from clients is not your money. It belongs to the government, and must be remitted.
Set it aside in a separate account — immediately
Set G.S.T. aside in a separate account as soon as each payment arrives, along with an amount for income tax.
Payroll deductions and WorkSafeBC premiums — on time
If you have employees, remit payroll deductions and Work Safe BC premiums on time. Penalties and interest add up quickly.
Monthly bookkeeping — quarterly review with your accountant
Do your bookkeeping every month, and review it with your accountant regularly, at least every quarter.
Tax surprises sink builders
Tax surprises sink more small builders than almost anything else. A separate tax account is one of the simplest and most powerful habits you can build.
Building a cash reserve
Every construction business needs a cash reserve.
Aim for several months of overhead
Aim to build a reserve that covers several months of your overhead.
Add to it from every project
Add to it from every project, before taking money out for yourself.
It carries you through slow months, slow draws and warranty work
It carries you through slow months, delayed draws, and warranty repairs years later.
It lets you say no to bad projects
And it gives you the freedom to say no to bad projects. Builders without reserves often take on risky work because they need the cash, and that is how problems multiply.
A warranty reserve for every project
Warranty work comes after the money has stopped. Plan for it.
Set aside a small amount from every project
Set aside a small amount from every project for future warranty work.
Warranty work continues for years
Remember that warranty work can continue for years, as we covered in Chapter Two.
Track warranty costs by project
Track warranty costs by project, so you know whether your reserve is enough.
Good warranty service protects your future income
Good warranty service protects your reputation and your future income. A builder who cannot afford to fix problems quickly loses referrals, and may face higher costs from the warranty provider.
Protecting against non-payment
Sometimes clients do not pay. Here is how to protect yourself.
Check the funding before you start
Check that the client’s funding is real and sufficient before you start, as we discussed.
Don’t get too far ahead of payments
Do not get too far ahead of payments. The less you are owed at any time, the less you can lose.
Use your contract rights early
Use your contract rights early: notice, interest, and suspension of work, as the contract allows.
Know your lien rights — and the deadlines
Know your lien rights and the strict deadlines, and get legal advice before they pass.
Keep records that prove what you’re owed
And keep records that prove what you are owed: the contract, change orders, invoices, and correspondence. Good records turn a dispute into a collection.
Insurance as cash protection
Insurance protects your cash from big, unexpected losses.
Builder’s risk — fire, theft and damage during construction
Builder’s risk insurance protects the building during construction from things like fire, theft and some weather damage.
Liability — injuries and property damage
Liability insurance protects you if someone is injured, or neighbouring property is damaged.
Tools and equipment
Tools and equipment insurance protects the assets your business depends on.
Understand deductibles — they’re your cash
Understand your deductibles. A large deductible is cash you must find when something goes wrong.
Review with your broker every year
Review your insurance with your broker every year, especially as your projects grow. One uninsured loss can wipe out years of profit.
Knowledge check
Which is a warning sign of a coming cash crunch?
- Paying trades early
- Using one project’s money to pay another’s bills
- A growing cash reserve
- Remitting GST on time
Show the answer
The answer is: using one project’s money to pay another project’s bills. It is a warning sign, and it can also break trust obligations under the Builders Lien Act.
Your own financial statements
Your own financial records matter for more than taxes.
Warranty providers review them
Warranty providers often review your financial statements when accepting or renewing your company, as we saw in Chapter Two.
Lenders and partners ask for them
Lenders and investment partners ask for them.
They show you the truth about your business
And most importantly, they show you the truth about your business: whether you are really making money, and where.
Prepared properly — by an accountant who knows construction
Have them prepared properly, by an accountant who understands construction. Clean financial statements open doors. Messy ones close them.
Your relationship with your bank
A good relationship with your bank is a business asset.
Meet your banker before you need money
Meet your banker before you need money, and explain your business and your plans.
Share your financial statements every year
Share your financial statements every year, even when you are not borrowing.
Tell them early about problems — and your plan
If problems appear, tell them early, with your plan to fix them. Banks dislike surprises more than bad news.
Keep your promises — payments and reporting
Keep your promises on payments and reporting.
A banker who knows you can help in hard times
A banker who knows and trusts you can help when times are hard. A banker who has never heard of you will not.
Knowledge check
When should you take profit from a project?
- When the first draw arrives
- When it’s really finished — holdbacks released, deficiencies done, warranty reserve set aside
- Whenever cash is available
- Before starting
Show the answer
The answer is: when the project is really finished. Holdbacks released, deficiencies done, and a warranty reserve set aside. Taking profit early is how builders end up short when the last bills arrive.
Paying yourself properly
Many small builders do not pay themselves properly. That creates problems for the business and the family.
Pay yourself a regular, sustainable amount
Pay yourself a regular, sustainable amount, rather than taking money whenever a draw arrives.
Your salary is overhead — profit is extra
Your salary is part of your overhead. Profit is what is left after everyone, including you, has been paid.
Take profit only when the project is really finished
Take profit only when a project is really finished: holdbacks released, deficiencies done, and warranty reserves set aside.
Get advice on salary vs. dividends
Get advice from your accountant on how to pay yourself, salary or dividends, in a tax efficient way.
Planning for slow years
Construction is cyclical. Busy years are followed by slower ones. Plan for them.
Save in busy years
Save in busy years. Build your reserve when work is plentiful.
Keep overhead flexible
Keep your overhead flexible, so it can be reduced if work slows down.
Diversify — new homes, renovations, multiplexes, service work
Consider diversifying: new homes, renovations, multiplexes, and warranty or service work, so one slow market does not stop your whole business.
Keep your best trades busy — and loyal
Keep your best trades as busy as you can in slow times, so they are still with you when the market returns.
Stay disciplined on pricing
And stay disciplined on pricing. In slow years, many builders take work at a loss just to stay busy. That rarely ends well.
Scenario: the surprise GST bill
The situation: Your accountant tells you that you owe a large GST amount for the year. You collected it from clients — but spent it on project costs.
Here is a painful situation for many small builders. Your accountant tells you that you owe a large G.S.T. amount for the year. You collected it from clients, but spent it on project costs. What now?
Don’t ignore it — call the accountant and plan
First, do not ignore it. Penalties and interest grow over time. Sit down with your accountant and make a plan.
Ask about payment arrangements
Second, ask about payment arrangements with the tax authority, if you cannot pay the full amount immediately.
Review cash flow and cut what you can
Third, review your cash flow, and reduce spending where you can until it is paid.
Next time: a separate tax account, funded every time money arrives
And next time, open a separate tax account, and transfer the G.S.T. and an amount for income tax into it every single time a payment arrives. It is one of the simplest habits that protects a building business.
Scenario: using personal credit to carry a client’s project
The situation: A client’s draw is late again. To keep the trades working, you’ve been paying them from your personal credit cards. The balance is growing, and the client says the money is ‘coming soon’.
Here is a dangerous pattern. A client’s draw is late again. To keep the trades working, you have been paying them from your personal credit cards. The balance is growing, and the client says the money is coming soon. What should you do?
Stop — this is a dangerous pattern
First, stop. Funding a client’s project with your personal credit is a very dangerous pattern, and it can damage your business and your family’s finances.
Find out the real reason for the delays
Second, find out the real reason for the delays. Talk to the client, and if possible, understand the lender’s position.
Use your contract rights — notice, interest, suspension
Third, use your contract rights: written notice, interest on late payments, and if necessary, suspension of work as the contract allows.
Protect yourself — and get advice early
And protect yourself. Get legal advice early, especially about lien deadlines, before the amount owed becomes too large to recover.
Chapter 9 — key takeaways
Let’s review the key takeaways from this chapter.
Construction loans release money in draws — for work in place
One. Construction loans release money in draws, for work already in place, and lenders need a lot of information from the builder.
Confirm the client’s full funding before you start
Two. Confirm the client’s full funding plan, including equity, before you start.
Clean draw packages and clean title get paid faster
Three. Clean draw packages, and a title free of liens, get paid faster.
Forecast cash monthly — and don’t take on more than you can carry
Four. Forecast your cash monthly, and do not take on more than your cash can carry.
Protect trust money, set aside taxes, and build a reserve
And five. Protect trust money, set aside taxes, and build a cash reserve.
Coming up in Chapter 10
In Chapter Ten, we look at one of the biggest causes of disputes and lost profit.
Change orders — the process
We will look at change orders, step by step,
Pricing changes fairly
how to price changes fairly,
Keeping clients happy through changes
and how to keep clients happy through changes. But first, the quiz.
Chapter 9 Quiz
1. A construction loan usually:
- Pays everything at the start
- Releases money in draws as work is completed
- Pays only at completion
- Has no interest
Show the answer
Answer: B — It releases money in draws for work in place.
2. Lenders often expect the owner’s equity to be used:
- Never
- First, before the loan funds construction
- Only at the end
- Only for furniture
Show the answer
Answer: B — Often the owner’s equity goes in first.
3. If the appraisal is lower than expected, the loan may be:
- Larger
- Smaller — leaving a gap to fill with equity
- Cancelled automatically
- Unchanged always
Show the answer
Answer: B — Smaller, and any gap must be filled with the client’s own money.
4. Inflating a budget to help a client borrow more is:
- Smart
- Misleading the lender — a serious matter
- Required
- Normal
Show the answer
Answer: B — It misleads the lender and can follow you for years.
5. Before releasing a draw, lenders typically check:
- The weather
- Title for liens or problems
- The client’s car
- Trade scorecards
Show the answer
Answer: B — They typically check title for liens.
6. Why do profitable builders run out of cash?
- They charge too much
- Money goes out before it comes in, plus holdbacks and late payments
- Too few projects
- Banks refuse all builders
Show the answer
Answer: B — Timing gaps, holdbacks, late payments, overhead and growth.
7. A business line of credit should be used for:
- Covering losses
- Timing gaps
- Personal holidays
- Paying taxes late
Show the answer
Answer: B — Timing gaps, arranged before you need it.
8. GST collected from clients:
- Is the builder’s profit
- Belongs to the government — set it aside
- Can be ignored
- Is optional
Show the answer
Answer: B — It must be remitted. Set it aside immediately.
9. On a spec home, who carries the market risk?
- The city
- The builder-owner
- The warranty provider
- The trades
Show the answer
Answer: B — The builder, who is also the owner.
10. Funding a client’s project with your personal credit cards is:
- A good long-term strategy
- A dangerous pattern — stop and get advice
- Required by law
- Tax-free
Show the answer
Answer: B — A dangerous pattern. Use your contract rights and get advice early.
Rules and figures change. Confirm current BC Housing, municipal, WorkSafeBC and warranty provider requirements before publishing.