Running a Residential Build in BC · Chapter 14 of 20

A free course by Xerox Builders · Instructor: Mandeep Singh, Licensed Residential Builder · All 20 chapters

Watch the video above, or read the full lesson below. It follows the video slide by slide: each bold line is the slide, and the text under it is what is said.

Opening

Welcome to Chapter Fourteen of Running a Residential Build in BC, Start to Finish. This chapter is about Framing. I am Mandeep Singh, a licensed residential builder in British Columbia. Framing is the stage when the house finally appears. It moves fast, it involves big money, and it sets the quality for every trade that follows. This chapter gives practical, general information. The BC Building Code, your structural engineer’s drawings, and the manufacturers’ instructions always govern your specific project.

Quick recap of Chapter 13

Let’s quickly recap Chapter Thirteen.

Prepare before digging — and work with the geotechnical engineer

We learned to prepare carefully before digging, and to work closely with the geotechnical engineer.

Accurate, inspected footings and walls — with hold-downs in place

We built accurate, inspected footings and walls, with hold downs and anchor bolts exactly where the drawings show.

Drainage, damp-proofing, soil gas and grading

And we installed drainage, damp-proofing, and soil gas control, and graded water away from the house. Now, the house goes up.

By the end of this chapter you will be able to:

Here are the learning outcomes for this chapter.

Prepare for framing — drawings, materials and the framer

One. Prepare for framing: drawings, materials, and the framing contractor.

Understand the structural system — loads, beams, shear walls

Two. Understand the structural system: load paths, beams, and shear walls.

Manage engineered products — joists, trusses and beams

Three. Manage engineered products, like I-joists, trusses, and engineered beams.

Control moisture and protect the frame

Four. Control moisture, and protect the frame from our wet climate.

Check framing quality — and pass the framing inspection

Five. Check the framing quality, and pass the framing inspection.

Prepare the house for the trades that follow

And six. Prepare the house for the trades that follow.

Part 1 — Preparing for framing

Why framing matters so much

Let’s start with why framing deserves so much attention.

It carries the house — for its whole life

The frame carries the house for its whole life: its weight, the people and furniture, snow on the roof, wind, and earthquakes.

It sets the quality — for every trade after

It sets the quality for every trade that follows. Crooked walls mean bad drywall, bad cabinets, and bad tile.

It’s a big part of the budget — and the schedule

It is a big part of the budget, and of the schedule. A good framing stage keeps the whole project on track.

Mistakes get covered quickly

And mistakes get covered quickly, by sheathing, insulation, and drywall. They must be caught while the frame is open.

The framing sequence

Let’s look at the typical sequence of framing a house, from the foundation up.

Sill plates and the first floor system

First, the sill plates are installed on the foundation, with the sill gasket and anchor bolts, followed by the beams and the first floor system.

Walls — laid out, framed, sheathed and stood

Next, the walls are laid out on the floor, framed, often sheathed while flat, and then stood up, plumbed, and braced.

Upper floors — repeat

Upper floors repeat the process: floor system, then walls.

Roof — trusses or rafters, then sheathing

Then the roof: trusses or rafters, bracing, and roof sheathing, followed by the underlayment.

Windows, doors, stairs and details

Finally, windows and exterior doors, stairs, blocking, backframing, and details. On a typical house, this takes several weeks to a few months, depending on size and complexity.

Layout — the first day matters most

The framing layout on the first floor sets the accuracy of the whole house.

Check the foundation — before the sill plates

Check the foundation dimensions, square, and level before the sill plates go down. Deal with any errors now.

Snap lines — from the drawings, not the foundation edge

Snap wall lines from the drawings, measured from established reference lines, not just from the edge of the foundation.

Check diagonals — every floor

Check diagonals for square on every floor.

Mark plumbing and mechanical locations

Mark the locations of toilets, tubs, drains, and major ducts, so the framing leaves room for them.

A walk-through — before walls go up

Walk through the layout with the framer before the walls go up. Moving a wall line in chalk is free. Moving a standing wall is not.

Plate heights and floor elevations

Heights are as important as dimensions. Small errors add up over several floors.

Wall plate heights — as on the drawings

Build walls to the plate heights shown on the drawings. Pre-cut studs come in standard lengths, but your design may need something different.

Floor system depths — confirmed with the supplier

Confirm the actual depth of the floor system with the supplier. Engineered joists come in specific depths, and a change in depth changes everything above.

Building height — check it during framing

Check the building height during framing against the zoning limit, especially on houses that were designed close to the maximum.

Ceiling heights — for suites and finishes

Check finished ceiling heights, especially in basement suites, where minimum heights apply, and under ducts and beams.

Measure at every floor — not just the top

Measure at every floor, not just at the top. It is much easier to correct a small error on the first floor than to discover a large one at the roof.

Drawings the framer needs

Before framing starts, the framer needs a complete, current set of drawings.

Architectural drawings — layout, heights and openings

Architectural drawings, showing the layout, wall heights, window and door openings, and stairs.

Structural drawings — beams, posts, shear walls and connections

Structural drawings, showing beams, posts, shear walls, hold downs, and connections.

Engineered product layouts — joists and trusses

Layouts for engineered products from the suppliers, like floor joist layouts and roof truss drawings.

Window and door schedules — with rough opening sizes

Window and door schedules, with rough opening sizes confirmed with the supplier.

The latest revisions — and old ones removed

And the latest revisions, with old drawings removed from site. Framing from an old drawing is one of the most common and costly mistakes.

Questions to answer before framing

Before framing starts, resolve the questions that commonly cause delays.

Window and door sizes — confirmed and ordered

Are the windows and exterior doors confirmed, and ordered, with rough opening sizes?

Stairs — type, finish and dimensions

Are the stairs designed: the type, the finished floor heights, and the finish materials, which affect the rise?

Finished floor heights — for each room

Do you know the finished floor materials in each room? Tile and hardwood heights affect door clearances and stair rises.

Tubs, showers and special fixtures

Are the tubs, shower bases, and special fixtures selected? Some need specific framing or support.

Mechanical routes — ducts and drains

And are the mechanical routes planned? Each unanswered question becomes a delay, or a change, during framing.

A framing pre-start meeting

Hold a short pre-start meeting with the framer before work begins. It prevents many problems.

Walk through the drawings — page by page

Walk through the drawings together, page by page, especially the structural details, shear walls, and hold downs.

Confirm the schedule and crew

Confirm the schedule, the crew size, and the key dates, like truss delivery and crane day.

Safety — the fall protection plan for each stage

Review safety, especially the fall protection plan for each stage, guardrails, and floor openings.

Site rules — deliveries, waste, parking and neighbours

Review your site rules: deliveries, waste, parking, working hours, and how to treat the neighbours.

How changes and questions will be handled

And agree how questions and changes will be handled. Nobody changes anything without asking you first, and changes are in writing.

Choosing and contracting the framer

As we discussed in Chapter Eight, choose and contract your trades carefully. Framing is one of the most important.

Experience with your type of house

Choose a framer with experience in your type of house: size, complexity, and engineered systems.

Clear scope — what’s included and what isn’t

Agree on a clear scope: walls, floors, roof, sheathing, stairs, blocking, backframing, windows, and clean up. Who installs windows and exterior doors? Who does fire blocking?

Price — per square foot, lump sum, or labour only

Agree on the price, whether per square foot, lump sum, or labour only, and what is extra.

Schedule and crew size

Agree on the schedule, and the crew size needed to meet it.

Safety — fall protection plan and documentation

And confirm safety: their fall protection plan, training, WorkSafe BC registration, and clearance letter, as we discussed in Chapter Twelve.

Paying the framer

Framing payments are large. Structure them clearly.

Progress payments — tied to stages

Tie progress payments to clear stages, like floor systems complete, walls complete, roof complete, and lockup.

Check the work — before each payment

Check the work before each payment, including quality and safety.

Holdback — as required by law

Keep the holdback required by the Builders Lien Act.

Deficiencies — fixed before final payment

Keep enough back to cover deficiencies, as your contract allows.

Clearance letter — before final payment

And get a current WorkSafe BC clearance letter before final payment, as we discussed in Chapter Eight.

Pricing framing in your estimate

As we discussed in Chapter Six, a good estimate starts with understanding what drives the cost. For framing, these are the main drivers.

Floor area — the starting point, not the whole story

Floor area is the usual starting point, and many framers quote per square foot. But the square footage alone does not tell the whole story, so read the quote carefully.

Complexity — corners, roof lines, vaults and heights

Complexity drives cost: the number of corners, complicated roof lines, vaulted ceilings, tall walls, and cantilevers all take more labour and more material.

Engineered products and steel

Engineered beams, engineered joists, and any steel add material cost, and sometimes crane time and special installation.

Shear walls and seismic hardware

Shear walls, hold downs, and straps add material and labour, especially on houses with many windows and few solid walls.

Site access and season

And site access and season matter. A tight lot with no room for material, or a winter build with rain delays, will cost more than a wide open lot in summer.

Labour-only or supply-and-install?

Framers can be hired in two main ways. Each has advantages and risks for the builder.

Labour-only — you supply the materials

With a labour only contract, the builder buys the lumber package and the framer supplies the labour. You control the material quality and price, but you also carry the risk of shortages, wrong deliveries, and waste.

Supply-and-install — the framer supplies everything

With a supply and install contract, the framer supplies both the materials and the labour. Your price is more certain, but you have less control over material choices, and you must check substitutions carefully.

Either way — engineered products must match the drawings

Either way, engineered products, beams, and connectors must match the drawings exactly, and substitutions need the engineer’s approval.

Define responsibility for waste, theft and shortages

Define in writing who is responsible for waste, theft, damage, and shortages.

Choose what fits your business

Choose the method that fits your business, your cash flow, and your ability to manage materials on site. Many builders use both, depending on the project.

Materials — ordering the package

The framing materials are usually ordered as a package from a lumber supplier.

A takeoff — from the drawings

The supplier or framer does a takeoff from the drawings, listing every piece needed.

Check the takeoff — against the drawings

Check the takeoff yourself, especially beams, posts, engineered products, and sheathing for shear walls.

Lead times — for trusses and engineered products

Know the lead times, especially for trusses, engineered joists, and large beams, which can take weeks.

Delivery — staged, not all at once

Plan deliveries in stages if the site is tight, so materials are not damaged or in the way.

Storage — off the ground and covered

Store materials off the ground, on supports, and covered from rain. Wet lumber causes problems later.

Scenario: the wrong beam was delivered

The situation: The lumber delivery includes an LVL beam one size smaller than the structural drawings show. The framer says: ‘It’s close enough — we’ll double it up with a 2×10.’

Here is a situation that happens on many sites. The lumber delivery includes an L.V.L. beam one size smaller than the structural drawings show. The framer says: it is close enough, we will double it up with a two by ten. What do you do?

Don’t install a substitute — without approval

First, do not install a substitute without approval. Close enough is not a structural calculation.

Call the supplier — get the correct beam

Second, call the supplier, and get the correct beam delivered.

If time is critical — ask the engineer about alternatives

Third, if time is critical, ask the structural engineer whether an alternative is acceptable. If they approve one, get it in writing.

Check every engineered product on delivery

And fourth, check every engineered product on delivery against the drawings, so mistakes are caught before they are installed.

Treated lumber and fasteners

Some framing materials need special care.

Treated lumber — where wood touches concrete or soil

Treated lumber is used where wood is in contact with concrete or near the ground, as the code requires.

Corrosion-resistant fasteners — with treated lumber

Treated lumber can corrode ordinary fasteners. Use hot dip galvanized or stainless fasteners and connectors, as the manufacturer requires.

Cut ends — treated as required

Cut ends of treated lumber may need field treatment.

The right nails — size and type as specified

Use the right nails: the size and type specified for shear walls, connectors, and sheathing. Not every nail in the gun is the right nail.

Connectors — the right model, every hole

Use the exact connector model specified, with every required hole filled with the right fastener.

Framing waste and site cleanliness

Framing creates a lot of waste. Managing it keeps the site safe and saves money.

Bins — sized and placed for framing

Order bins sized for the framing stage, placed where they can be filled and swapped easily.

Sort where you can — wood, metal and cardboard

Sort waste where you can. Clean wood, metal, and cardboard can often be recycled, which may reduce disposal costs and help meet city requirements.

Daily clean-up — in the contract

Make daily clean up part of the framer’s contract, especially cut-offs on floors and around edges, which cause trips and falls.

Re-use off-cuts — for blocking

Re-use off-cuts for blocking and backing, where suitable. It reduces waste and cost.

A clean house — for the next trades

And hand over a clean house to the next trades. A clean start makes the rough-in stage faster.

Knowledge check

What is one of the most common and costly framing mistakes?

  • Using too many nails
  • Framing from an old or superseded drawing
  • Starting on a Monday
  • Using a nail gun
Show the answer

The answer is: framing from an old or superseded drawing. Make sure the framer has the latest revisions, and remove old drawings from site.

Part 2 — The structural system

Load paths — how weight reaches the ground

Every house has load paths: the routes that weight follows down to the foundation.

Roof to walls to floors to foundation

Loads travel from the roof, through the walls and floors, down to the foundation and footings.

Point loads — must be carried all the way down

Point loads, like the end of a beam or a girder truss, must be carried all the way down, with posts and solid blocking, to the foundation.

Missing a load path — is a serious defect

A missing load path, like a post that lands on nothing, is a serious structural defect.

Follow the structural drawings — exactly

Follow the structural drawings exactly. Do not move posts, beams, or bearing walls without the engineer’s approval.

Check for squash blocks and blocking

Check for squash blocks and solid blocking under posts, where loads pass through floor systems.

Bearing walls — know which ones they are

Not every wall is the same. Some carry loads, and some do not.

Bearing walls — carry loads from above

Bearing walls carry loads from floors or the roof above.

Mark them — on the drawings and on site

Mark them on the drawings and on site, so every trade knows which walls are structural.

Don’t move or cut them — without the engineer

Do not move, cut, or remove them, or make large openings in them, without the engineer’s approval.

Openings — need headers sized for the load

Openings in bearing walls need headers sized for the load above.

Client changes — check before agreeing

When a client asks to move a wall, check whether it is bearing before agreeing, and price the engineering as a change order.

Reading the structural drawings

Builders and site supervisors should be comfortable reading the structural drawings.

The general notes — read them first

Read the general notes first. They contain important requirements for materials, nailing, connections, and field reviews.

Framing plans — beams, posts and bearing walls

The framing plans show beams, headers, posts, and bearing walls on each floor.

Shear wall schedule — types and nailing

The shear wall schedule shows the type of each shear wall, its sheathing, and its nailing.

Details — connections and special conditions

The details show special connections and conditions, like beam pockets, cantilevers, and step downs.

Questions — ask the engineer early

If something is unclear, ask the engineer early, in writing. Do not let the framer guess.

When the drawings don’t work on site

Sometimes what is on the drawings cannot be built exactly as shown. Here is how to handle it properly.

Stop and confirm the conflict

First, stop, and confirm that the conflict is real. Measure, check the latest revisions, and compare the architectural and structural drawings.

Ask the right professional — in writing

Ask the right professional in writing: the designer for layout issues, and the engineer for anything structural. Send photos and a sketch.

Get the answer in writing — with a sketch or revision

Get the answer in writing, with a sketch, a revised detail, or a revised drawing.

Share it with the framer and the inspector

Share it with the framer, keep it on site, and make sure the inspector can see it if asked.

Track any cost or time — as a change if needed

And track any cost or time impact. If it was caused by a design error or a client change, handle it through your change order process.

Shear walls and seismic resistance

As we discussed in Chapter Thirteen, our coast is an earthquake zone. Shear walls keep the house standing.

Shear walls — sheathed walls with special nailing

Shear walls are walls sheathed with plywood or O.S.B., with special nailing patterns, that resist sideways forces.

Nailing — size, spacing and edge distance

The nailing must match the drawings: nail size, spacing at edges and in the field, and distance from the panel edges.

Blocking — at panel edges where required

Blocking at panel edges, where required, so every edge is nailed.

Hold-downs and straps — connected as designed

Hold downs and straps must be connected as designed, to the foundation and between floors.

Over-driven nails — reduce strength

Watch for over-driven nails, where the nail head breaks through the sheathing surface. They reduce the strength of the wall. Adjust the nail gun pressure.

Connections between floors

A house only resists earthquakes and wind if its parts are connected together.

Straps and hold-downs — between floors

Straps and hold downs connect the walls of one floor to the walls or foundation below.

Floor diaphragms — sheathing and nailing

Floors and roofs act as diaphragms, carrying sideways forces to the shear walls. Their sheathing and nailing matter too.

Blocking — to transfer forces

Blocking between joists transfers forces at shear walls and diaphragm edges, where required.

Shrinkage — affects connections

Wood shrinks as it dries, which can loosen connections. Some hold down systems include shrinkage compensation.

The engineer’s field review — catches problems

The structural engineer’s field review checks these connections. Book it before the framing is covered.

Knowledge check

A client asks to remove a wall to open up the kitchen. What should you check first?

  • The paint colour
  • Whether it is a bearing or shear wall — and get the engineer involved if it is
  • Nothing — just remove it
  • Only the electrical
Show the answer

The answer is: whether it is a bearing wall or a shear wall. If it is, the engineer must design the change, and it should be priced as a change order.

Beams, headers and posts

Beams and headers carry loads over openings and open spaces.

Sized by the code or the engineer

Beams and headers are sized according to the building code tables, or by the engineer.

Bearing — enough length at each end

Each end needs enough bearing length, as designed, on posts or walls.

Posts — built up or solid, as specified

Posts must be built up or solid, as specified, with the right number of plies and fastening.

No notching or drilling — without approval

Do not notch or drill beams without the engineer’s or manufacturer’s approval.

Hangers and connectors — correctly installed

Install hangers and connectors correctly: the right model, every nail hole filled with the right nail, as the manufacturer requires.

Tall walls, vaulted ceilings and open spaces

Modern house designs often have tall walls, vaulted ceilings, and large open spaces. They need special care.

Tall walls — may need engineered studs

Tall walls may need engineered studs or special design, to resist wind and to stay straight.

Vaulted ceilings — ridge beams and thrust

Vaulted ceilings may need structural ridge beams, and the design must deal with the outward thrust on the walls.

Large openings — big headers and posts

Large window walls and wide openings need big headers and posts, and sometimes steel.

Fewer walls — less bracing

Open spaces have fewer walls, so the remaining shear walls must work harder.

Follow the engineer’s details — exactly

Follow the engineer’s details exactly. These areas are where structural problems most often appear.

Cantilevers and overhangs

Cantilevers, where floors or walls extend past the support below, are common in modern designs.

Designed by the engineer

Cantilevers must be designed by the engineer or follow the code and manufacturer’s limits.

Back-span and connections

The joists must extend back far enough into the house, with the right connections, to hold the cantilever.

Insulation and air sealing — at the underside

The underside of a cantilever is exposed to the outside, so it must be insulated and air sealed carefully. It is a common cold spot.

Water — at the wall connection

Flash the connection between the cantilever and the wall below, so water does not get in.

Check for bounce and deflection

Check the finished cantilever for bounce and deflection, especially under heavy loads like bathtubs or kitchen islands.

Shrinkage in multi-storey wood houses

Wood shrinks across its grain as it dries. In a house with several floors, that shrinkage adds up.

Most shrinkage — in plates, rims and joists

Most shrinkage happens across the width of horizontal members, like plates, rim boards, and sawn joists, not along the length of studs.

It adds up — floor by floor

It adds up floor by floor. A three storey house can shrink noticeably between the foundation and the roof.

Effects — cracks, gaps and stressed pipes

It can cause drywall cracks, gaps at stairs and trim, stressed plumbing stacks, and problems where wood framing meets materials that do not shrink, like concrete, steel, or brick.

Reduce it — dry lumber and engineered products

Reduce it by using dry lumber, and engineered products for rims and joists, which shrink less.

Detail for it — where materials meet

And detail for it where different materials meet, as the designer and engineer specify.

Scenario: the plumber cut the joist

The situation: The plumber has cut a large notch through the bottom of a floor joist to run a drain line. The joist supports a bathroom with a heavy tub.

Here is a very common problem. The plumber has cut a large notch through the bottom of a floor joist to run a drain line. The joist supports a bathroom with a heavy tub. What do you do?

Stop — don’t let it be covered

First, stop, and do not let it be covered. Notches in the bottom of a joist can seriously weaken it.

Check the code or the manufacturer’s rules

Second, check the building code limits for sawn joists, or the manufacturer’s rules for engineered joists. Most do not allow cutting the flanges at all.

Get an engineered repair if needed

Third, if it is outside the rules, get an engineered repair from the engineer or manufacturer, and install it exactly.

Plan service routes before rough-in next time

And fourth, prevent it next time. Plan the drain routes with the plumber and designer before framing, and frame in drops or chases where needed.

Steel in residential framing

Some house designs include structural steel beams or posts.

Shop drawings and fabrication — lead time

Steel needs shop drawings and fabrication, which take time. Order early.

Lifting and placement — plan the crane

Plan how the steel will be lifted and placed, often with a crane, on the same day as other heavy lifts.

Connections — bolted or welded as designed

Connections must be bolted or welded exactly as designed, and sometimes inspected.

Wood-to-steel connections — nailer plates

Wood framing connects to steel with nailer plates or special connectors.

Fire protection and thermal bridging

Consider fire protection, and thermal bridging where steel passes through the building envelope.

Part 3 — Engineered products

I-joists and engineered floor systems

Most new homes in British Columbia use engineered floor joists, like I-joists or open-web joists.

Longer spans, straighter floors

They allow longer spans, and make straighter, quieter floors than sawn lumber.

A layout from the supplier — follow it

The supplier provides a layout. Follow it exactly: joist sizes, spacing, and blocking.

Holes — only where the manufacturer allows

Holes for services are only allowed in certain locations and sizes, as the manufacturer’s charts show. Never cut the flanges.

Rim board, web stiffeners and blocking

Install the rim board, web stiffeners, and blocking where required.

Floor sheathing — glued and fastened

Glue and fasten the floor sheathing as specified. It reduces squeaks, which are one of the most common homeowner complaints.

Floors that don’t squeak or bounce

Squeaky and bouncy floors are among the most common homeowner complaints. Most can be prevented during framing.

Dry, straight joists — installed level

Use dry, straight joists, installed level and at the correct spacing.

Glue and fasten the subfloor

Glue and fasten the subfloor as specified, with the right adhesive, applied before it skins over.

Blocking and bridging — as required

Install blocking and bridging as the layout requires.

Stiffer floors — for tile and long spans

Consider stiffer floors for tile, stone, and long spans, by closer spacing or deeper joists.

Keep the subfloor dry

Keep the subfloor dry, and sweep water off quickly. Wet subfloors swell at the edges, causing humps under flooring.

Knowledge check

What helps prevent squeaky floors during framing?

  • Using wet joists
  • Gluing and fastening the subfloor as specified, with dry, straight joists
  • Leaving the subfloor wet
  • Fewer nails
Show the answer

The answer is: dry, straight joists, installed level, and a subfloor glued and fastened as specified, with blocking where required.

Roof trusses

Roof trusses are engineered components, designed by the truss manufacturer for your house.

Truss drawings — sealed by an engineer

The truss drawings are designed and sealed by the manufacturer’s engineer, and the city will want them.

Install exactly as designed — no cutting

Install trusses exactly as designed. Never cut, notch, or alter a truss without an engineered repair.

Bracing — temporary and permanent

Install temporary bracing during erection, and permanent bracing as the truss drawings require. Many truss collapses happen during installation.

Girder trusses — and their connections

Girder trusses carry other trusses. Their hangers, plies, and connections are critical.

Connections to walls — for wind and seismic

Connect trusses to the walls as designed, with clips or straps, for wind uplift and seismic forces.

Crane day — setting trusses

Setting trusses is often done with a crane. Plan it carefully.

Crane location — firm ground, away from power lines

Choose the crane location on firm ground, away from overhead power lines, as we discussed in Chapter Twelve.

Street use permit — if the crane is on the street

Get a street use permit if the crane will be on the street, and plan traffic control.

Truss delivery — timed with the crane

Time the truss delivery with the crane, and stack them so they can be lifted in order.

Fall protection — in place before the lift

Have fall protection in place before the lift, and a plan for how workers will set and brace the trusses.

Weather — wind can stop the lift

Watch the weather. Wind can make lifting trusses dangerous. Have a backup day.

Roof framing details

The roof frame must support the roof and keep the attic healthy.

Roof sheathing — with clips or blocking at edges

Install roof sheathing with clips or blocking at the panel edges, as specified, and with gaps for expansion.

Overhangs and soffits — framed as designed

Frame overhangs and soffits as designed, including any fire protection near property lines.

Attic ventilation — intake and exhaust

Provide attic ventilation, with intake at the soffits and exhaust near the ridge, as the code and design require. Keep insulation from blocking the soffit vents.

Attic access — framed and sealed

Frame the attic access hatch, and plan to seal and insulate it.

Underlayment — as soon as possible

Install the roof underlayment as soon as possible, to protect the house from rain.

Stick-framed roofs and complex roofs

Not every roof uses trusses. Some are stick framed, with rafters, especially complex or vaulted roofs.

Rafters and ridge — sized and designed

Rafters, ridges, hips, and valleys must be sized by the code tables or designed by the engineer.

Ridge beams — for vaulted ceilings

Vaulted ceilings usually need a structural ridge beam, supported by posts down to the foundation.

Thrust — tied or designed for

If there are no ceiling joists tying the walls together, the design must deal with outward thrust on the walls.

Valleys and hips — carry extra loads

Valleys and hips carry extra loads and need proper support.

More skill — and more time

Stick framing takes more skill and time than trusses. Price and schedule it accordingly.

Skylights, dormers and roof openings

Roof openings add character to a house, but they also add structural and water risks.

Framed openings — headers and doubled members

Frame roof openings with proper headers and doubled members, as designed, especially when trusses are interrupted.

Never cut trusses to fit — without a design

Never cut trusses to fit a skylight or dormer. The truss supplier must design the opening.

Dormers — their own structure and flashing

Dormers have their own walls and roofs, and complex flashing where they meet the main roof.

Skylight curbs and flashing kits — as the manufacturer requires

Install skylight curbs and flashing kits exactly as the manufacturer requires.

Plan them early — not during framing

Plan them early, in the design and the truss order, not during framing. Adding a skylight after the trusses are set is costly and risky.

Engineered beams and lumber

Engineered beams, like L.V.L. and glulam, carry heavy loads over long spans.

Strong and straight — but strict rules

They are strong and straight, but they come with strict rules from the manufacturer.

Correct orientation — and correct ply connections

Install them in the correct orientation, and connect multiple plies exactly as specified.

No cutting or drilling — unless allowed

No cutting, notching, or drilling, unless the manufacturer allows it in writing.

Protect them from weather

Protect them from weather. Some engineered products can swell or delaminate if left wet.

Check sizes on delivery

Check sizes and grades on delivery against the drawings. Substitutions must be approved by the engineer.

Product documentation on site

Engineered products come with documentation that inspectors and engineers will want to see.

Truss drawings and layouts

Truss drawings, sealed by the manufacturer’s engineer, and the truss layout.

Joist layouts and installation guides

Floor joist layouts, and the manufacturer’s installation guides, including hole charts.

Beam specifications

Beam specifications, and any engineer approved substitutions.

Connector schedules

Connector schedules, showing which hangers and straps go where.

Keep them on site — and in the project file

Keep them on site during framing, and in the project file afterward. Some go in the homeowner manual.

Scenario: the truss layout doesn’t match the walls

The situation: When the trusses arrive, the framer finds that the girder truss bears on a wall that was moved during design changes. The crane is booked for this afternoon.

Here is a costly situation. When the trusses arrive, the framer finds that the girder truss bears on a wall that was moved during design changes. The crane is booked for this afternoon. What do you do?

Don’t set the girder on the wrong support

First, do not set the girder truss on the wrong support, or on a temporary guess. Girder trusses carry large loads.

Call the truss supplier and engineer — immediately

Second, call the truss supplier and the structural engineer immediately. They may be able to provide a revised bearing detail, a post, or a revised truss.

Set what you safely can — or reschedule the crane

Third, set only what you safely can, with the engineer’s agreement, or reschedule the crane. A crane cancellation is cheaper than a structural failure.

Find out why the revision was missed

And fourth, find out why the revision was missed. The truss supplier must always receive the latest drawings. Add a step to your process to confirm this before every truss order.

Knowledge check

The electrician wants to cut a small notch in the top chord of a roof truss. What is the rule?

  • Small notches are fine
  • Never cut or alter a truss without an engineered repair
  • Only on weekends
  • Only if the framer agrees
Show the answer

The answer is: never cut, notch or alter a truss without an engineered repair from the truss manufacturer or engineer.

Part 4 — Moisture and weather

Wet lumber — a BC problem

In our climate, lumber gets wet during framing. Managing that moisture is essential.

Wet framing shrinks as it dries

Wet framing shrinks as it dries, causing nail pops, drywall cracks, squeaky floors, and gaps.

Mould can grow on wet wood

Mould can grow on wood that stays wet too long, especially once it is enclosed.

Never enclose wet framing

Never insulate and drywall over wet framing. Check the moisture content first.

Moisture meter — use it

Use a moisture meter. Check framing in several places before insulation, especially plates, beams, and the floor system.

Plan for drying time — in the schedule

Plan for drying time in the schedule. Get the roof on, and the house closed in, as early as possible.

Checking moisture before close-in

Here is a practical way to check that framing is dry enough before insulation and drywall.

Check several locations — on every floor

Check moisture content in several locations on every floor: plates, studs, joists, beams, and sheathing.

Focus on the wettest areas

Focus on the areas that got wettest: bottom plates, floor systems, and areas near openings.

Follow the target — from the code or the design

Follow the target moisture content from the code or the design. Many builders aim for well under twenty percent before close in.

Record the readings

Record the readings, with dates and locations.

Dry it first — don’t hope it dries later

If it is too wet, dry it first, with time, heat, and dehumidifiers. Do not hope it will dry after the drywall is on.

Framing in the wet season

Many houses in British Columbia are framed between October and April. Plan for it.

Schedule the roof — as early as possible

Schedule the roof as early as possible. Order trusses early, so they are not the delay.

Temporary covers — tarps and roof underlayment

Have temporary covers ready: tarps, and roof underlayment installed as soon as the sheathing is on.

Moisture-resistant materials — where it helps

Consider moisture resistant subfloor products, which tolerate wet weather better.

Drainage holes — in floors during construction

Some builders drill small drainage holes in subfloors during construction, so rain water drains instead of ponding. Check with the manufacturer first.

Drying time — built into the schedule

Build drying time into the schedule before insulation. In winter, it is not optional.

Mould on framing — what to do

Even with good practices, mould can appear on framing in our climate. Here is a practical approach.

Find the cause — and stop the water

First, find the cause, and stop the water. Mould needs moisture. Without fixing the moisture, cleaning does not last.

Light surface mould — clean and dry

Light surface mould on framing can often be cleaned and dried, following good practice and the product guidance.

Heavy growth or damaged material — replace it

Heavy growth, or material that has been damaged by water, may need to be replaced.

Protect workers

Protect the workers doing the clean up, with the right respiratory protection and procedures.

Document it — and tell the client

Document what was found and what was done, with photos and moisture readings, and tell the client. Hiding mould is never the right answer.

Protecting the frame

There are practical ways to protect the frame during construction.

Store lumber covered — off the ground

Store lumber covered, and off the ground.

Drain water off floors — don’t let it pond

Drain or sweep water off floor systems quickly. Do not let it pond on the subfloor.

Roof on fast — and temporary protection

Get the roof sheathing and underlayment on as fast as possible, and use temporary covers where needed.

Close in — windows and doors early

Close in the house with windows and doors early.

Heat and dehumidify — when needed

Use heat and dehumidification to dry the house when needed, especially in winter.

Scenario: three weeks of rain on an open frame

The situation: The roof trusses are delayed. Your second floor has been open to three weeks of heavy rain. The subfloor edges are swollen and there are dark spots on some plates.

Here is a situation that is all too common in our winters. The roof trusses were delayed, and your second floor has been open to three weeks of heavy rain. The subfloor edges are swollen, and there are dark spots on some plates. What do you do?

Get the roof on — as fast as possible

First, get the roof on, and the house closed in, as fast as possible, with temporary protection until then.

Dry the house — heat, dehumidifiers, air movement

Second, dry the house, using heat, dehumidifiers, and air movement.

Check and treat — swollen subfloor and mould

Third, check the damage. Swollen subfloor edges may need to be sanded flat or replaced before flooring. Dark spots may be mould, which must be properly cleaned or the material replaced, following good practice.

Measure moisture — before close-in

And fourth, measure moisture before close in, and record it. It is better to lose a week now than to have mould and cracks in a finished house.

Part 5 — Quality and the framing inspection

Framing quality — what to check

Check framing quality as it goes up, not only at the end.

Walls plumb and straight

Walls plumb and straight, especially in kitchens, bathrooms, and where cabinets and tile will go.

Floors level and flat

Floors level and flat, with no humps at beams or bearing walls.

Openings — the right size and location

Window and door openings the right size, in the right place, and square.

Stairs — rise and run within code

Stairs with consistent rises and runs within the code limits, and proper headroom.

Dimensions — rooms, ceiling heights and layouts

Room dimensions, ceiling heights, and layouts matching the drawings. Small errors here become big problems for cabinets and finishes.

Kitchens and bathrooms — framing extra carefully

Kitchens and bathrooms need extra care during framing, because the finishes there are expensive and unforgiving.

Straight walls — for cabinets and tile

Walls must be straight and plumb for cabinets and tile. Crowned studs show up as gaps behind cabinets and lippage in tile.

Exact dimensions — for cabinets and appliances

Room dimensions must be exact for the cabinet layout and appliances.

Shower and tub framing — per the product

Frame showers and tubs as the product requires, including curb heights, niches, and benches.

Blocking — for everything that hangs

Install blocking for cabinets, shelves, grab bars, and accessories.

Floor support — for heavy tubs and stone

Support floors for heavy tubs, stone, and large islands, as designed.

Stairs, guards and handrails

Stairs are among the most inspected, and most dangerous, parts of a house.

Consistent rises and runs — within code

Rises and runs must be consistent, and within the code limits. Inconsistent steps cause falls.

Allow for finished floors — top and bottom

Allow for the finished floor materials at the top and bottom, so the first and last steps are not different.

Headroom — through the full stair

Provide the required headroom through the full length of the stair.

Guards and handrails — heights and openings

Guards and handrails must meet the code requirements for height, strength, and openings, so children cannot climb or slip through.

Temporary stairs and guards — during construction

And use temporary stairs and guards during construction, as we discussed in Chapter Twelve.

Straightening walls before drywall

Even good framing has some crooked studs. Fix them before drywall.

Check walls with a straight edge or string

Check walls with a long straight edge or string line, especially in kitchens, bathrooms, and long hallways.

Plane, shim or replace crowned studs

Plane down, shim, or replace badly crowned studs.

Check ceilings — for level and flatness

Check ceilings for level and flatness, especially where long lights or crown moulding will be installed.

Check corners — for square

Check corners for square where tile, cabinets, or built-ins will go.

Agree who does it — in the framing contract

Agree in the framing contract who does this straightening, and when. Many builders do a separate pre-drywall framing check.

Common framing defects that inspectors find

Here are framing defects that inspectors commonly find on residential projects.

Missing fire blocking and unsealed penetrations

Missing fire blocking, and penetrations through fire separations that are not sealed.

Shear wall nailing — wrong spacing or over-driven nails

Shear wall nailing with the wrong spacing, or over-driven nails.

Missing or incomplete hangers and connectors

Missing hangers, or connectors with missing nails.

Cut or notched joists, studs and trusses

Joists, studs, and trusses cut or notched by trades.

Stair and guard problems

And stair and guard problems: inconsistent rises, missing handrails, and guards that are too low or have openings that are too wide. Check these yourself before every framing inspection.

Blocking and backing — before it’s too late

Blocking and backing are small pieces of wood that save a lot of trouble later.

Cabinets and shelving

Backing for upper and lower cabinets, and built in shelving.

Handrails, grab bars and towel bars

Backing for handrails, grab bars, and towel bars, where required or planned.

TV mounts and heavy fixtures

Backing for wall mounted TVs, and heavy light fixtures or fans.

Drywall edges — at corners and ceilings

Drywall backing at inside corners and ceiling edges, as the drywall installer needs.

Photograph it — for the homeowner

Photograph the blocking with measurements, for the homeowner manual. Adding it after drywall is expensive.

Fire blocking and fire separations

Fire safety is built into the frame.

Fire blocking — to stop fire spreading in concealed spaces

Fire blocking stops fire from spreading through concealed spaces, like between floors, at stair stringers, and in soffits.

Fire separations — between suites and garages

Fire separations are required between dwelling units, like a main house and a suite, and between the house and an attached garage.

Penetrations — sealed with approved products

Penetrations through fire separations must be sealed with approved fire stopping products.

Coordinate with the trades

Coordinate with plumbers, electricians, and HVAC installers, who make many of these penetrations.

Inspectors check it

Inspectors check fire blocking and separations. Missing them is a common reason for failed inspections.

Balconies and decks over living space

Balconies and decks over living space are a common source of leaks and rot.

Slope — water must drain away

The deck must slope so water drains away from the house.

A waterproof membrane — designed and detailed

A waterproof membrane, properly designed and detailed, is essential.

Door thresholds and wall connections — flashed

Door thresholds and wall connections must be flashed carefully. Many leaks start here.

Guards — attached without making holes in the membrane

Guard posts must be attached without creating holes in the membrane, or with approved details.

Coordinate framing with the membrane installer

Coordinate the framing with the membrane installer before you build it. The framing slope and blocking must suit their system.

Window openings and egress

Window openings must meet several code requirements, not just the window size.

Bedroom windows — for emergency exit

Bedrooms usually need a window large enough for emergency exit, unless there is another exit, as the code requires.

Sill heights — for safety

Windows with low sills on upper floors may need guards, or limited openings, to protect children from falling.

Spatial separation — near property lines

Windows near property lines may be limited in size, or need to be fire rated, as part of spatial separation requirements.

Safety glass — in certain locations

Some locations need safety glass, like near doors, in showers, and near floors.

Check the window schedule — against the openings

Check the window schedule against the framed openings before the windows arrive.

Exterior walls and energy details during framing

Some energy efficiency details are decided during framing, not later.

Insulated headers — where the design calls for them

Insulated headers, or smaller headers where structure allows, leave more room for insulation.

Corners and wall intersections — room for insulation

Framing corners and wall intersections so insulation can reach them, instead of solid blocks of wood that create cold spots.

Air barrier details — at floors and top plates

Air barrier details at the rim joists, top plates, and where interior walls meet exterior walls.

Service cavities — where specified

Service cavities, or strapping on the inside, where specified, so wiring and plumbing do not puncture the air barrier.

Talk to the energy advisor — before framing

Talk to the energy advisor before framing about these details. We will look at the Step Code in Chapter Fifteen.

The framing inspection

The framing inspection is one of the most important inspections on the project.

Usually after rough-ins — before insulation

In most cities, the framing inspection happens after the plumbing, electrical, and mechanical rough ins, before insulation.

Structure, fire safety and code items

The inspector checks the structure, fire blocking and separations, stairs, guards, and other code items.

Engineer field reviews — first

Many cities want the structural engineer’s field review, and sometimes letters of assurance, before or at the framing inspection.

Truss drawings and product documents — on site

Have the truss drawings, joist layouts, and product documents on site.

A pre-inspection walk — by you

Walk the house yourself before the inspection, with a checklist. Fix what you find before the inspector does.

A pre-inspection checklist for framing

Here is an example of a framing pre-inspection checklist.

Structure — beams, posts, point loads, connectors

Structure: beams, posts, point loads carried down, hangers and connectors complete.

Shear walls — nailing, blocking, hold-downs and straps

Shear walls: nailing, edge blocking, hold downs, and straps.

Fire — blocking, separations and penetrations

Fire safety: fire blocking, fire separations, and sealed penetrations.

Stairs, guards, windows and egress

Stairs, guards, and bedroom windows for emergency exit.

Documents — truss drawings, layouts, engineer reviews

And documents: truss drawings, joist layouts, and engineer field reviews. Check every item, and fix what you find.

Knowledge check

Why are inconsistent stair rises dangerous?

  • They aren’t
  • People expect each step to be the same — inconsistent steps cause trips and falls
  • They look old-fashioned
  • They squeak
Show the answer

The answer is: people expect every step to be the same height. Inconsistent steps cause trips and falls, so rises and runs must be consistent and within the code limits.

Scenario: the framing inspection fails

The situation: The inspector fails the framing inspection: missing fire blocking at the stairs, and shear wall nailing doesn’t match the drawings in two places. The insulator is booked for tomorrow.

Here is a situation every builder faces at some point. The inspector fails the framing inspection. There is missing fire blocking at the stairs, and the shear wall nailing does not match the drawings in two places. The insulator is booked for tomorrow. What do you do?

Reschedule the insulator — immediately

First, reschedule the insulator immediately. Nothing can be covered until the inspection passes.

Fix the items properly — with the framer

Second, fix the items properly with the framer, as part of their scope.

Get the engineer’s input on the shear walls

Third, get the structural engineer’s input on the shear wall nailing. They may need to review the fix, or specify additional nailing.

Re-book — and learn from the list

And fourth, re-book the inspection, and learn from the list. Add these items to your pre-inspection checklist, so they are caught next time before the inspector arrives.

Engineer field reviews during framing

As we discussed in Chapter Four, when an engineer provides letters of assurance, they must review the work in the field.

Book them in advance

Book the structural engineer’s field reviews in advance, at the stages they require.

Before anything is covered

Make sure the reviews happen before the work is covered.

Fix their items promptly

Fix the items in their field review reports promptly, and let them know when done.

Keep the reports

Keep their reports in the project file.

No letters — no occupancy

Remember that the city may not grant occupancy without the final letters of assurance. Missed reviews can delay the end of the project.

Framing photos — what to keep

Like the foundation, framing is soon hidden. Photograph it before it is covered.

Shear walls — nailing and hold-downs

Shear walls, including nailing patterns, hold downs, and straps.

Beams, posts and connections

Beams, posts, and their connections.

Blocking — with measurements

Blocking for cabinets, grab bars, TVs, and other fixtures, with a tape measure visible.

Every wall — before insulation

Every wall, room by room, before insulation, so plumbing and wiring locations are recorded.

Organized — by floor and room

Organize them by floor and room. Homeowners and future trades will thank you.

Scenario: the inspector questions the stair

The situation: At the framing inspection, the inspector measures the stair and finds the bottom rise is 3 cm taller than the others. The finished floor in the basement will be thin vinyl, not the tile shown on the drawings.

Here is a common inspection finding. At the framing inspection, the inspector measures the stair, and finds the bottom rise is three centimetres taller than the others. The reason is that the basement finish was changed from tile to thin vinyl, which was never communicated to the framer. What do you do?

Accept the finding — and measure everything

First, accept the finding, and measure every rise and run yourself.

Calculate with the real finished floor materials

Second, recalculate the stair using the real finished floor materials at the top and the bottom.

Rebuild the stringers if needed — before finishes

Third, if needed, rebuild or adjust the stringers now, before finishes. It is much cheaper than after the treads and handrails are installed.

Confirm finished floor materials before stairs are framed

And fourth, change your process. Confirm finished floor materials before any stair is framed, and communicate client changes to every trade that is affected.

Knowledge check

When does the framing inspection usually happen?

  • Before the foundation
  • After rough-ins, before insulation
  • After drywall
  • At occupancy
Show the answer

The answer is: after the plumbing, electrical and mechanical rough ins, and before insulation, so the inspector can see the structure and fire safety details.

Part 6 — Preparing for the trades that follow

Planning service routes

The frame must leave room for plumbing, ducts, and wiring.

Plan ducts and drains — before framing

Plan duct runs and drain lines before framing, with the mechanical designer and plumber.

Chases and drops — framed in

Frame chases, bulkheads, and dropped ceilings where services will run.

Avoid structural conflicts

Avoid conflicts with beams, joists, and shear walls, so trades do not cut structure.

A rough-in walk-through — with each trade

Do a rough-in walk through with each trade before they start.

Engineered floors — help a lot

Open-web floor joists make service routing easier, and are worth considering in complex houses.

The rough-in stage — coordinating trades

After framing, the plumbing, electrical, and mechanical trades do their rough ins. This is a busy, crowded time.

Sequence them — or coordinate overlap

Sequence the trades, or coordinate how they overlap. Usually, the larger items go in first: ducts and drains, then water lines, then wiring.

Protect the structure — no cutting without approval

Remind every trade: no cutting structure without approval.

Fire stopping — who does it

Agree who does the fire stopping at penetrations.

Check before insulation

Check the rough ins before insulation, as we will discuss in Chapter Sixteen.

Clean up between trades

Keep the house clean between trades, so each one starts on a clear site.

Who cuts what — setting the rules

Most structural damage during rough-in is done by trades who did not know the rules.

A written rule — no cutting structure without approval

Put it in writing in every trade contract: no cutting, notching, or drilling structural members without approval.

Show them the hole charts

Show trades the manufacturer’s hole charts for engineered joists, and post them on site.

Mark no-cut zones

Mark no cut zones, like beams, trusses, and shear walls, on site.

Check after each trade

Check the structure after each trade finishes their rough in.

Back-charge damage — as the contract allows

Back charge the cost of repairs to the trade that caused the damage, as your contract allows. It changes behaviour quickly.

Handover from framing to rough-in — a checklist

Before the rough-in trades start, check that the house is ready for them. A clean handover avoids delays and arguments.

Framing complete — or the remaining items listed

Framing is complete, or the remaining framing items are clearly listed, with dates.

Roof on and house dry — or drying

The roof is on, the house is closed in, and it is dry or drying.

Chases, drops and blocking — in place for the trades

Chases, dropped ceilings, and blocking are in place for the trades’ routes and fixtures.

Stairs and guards — safe for the trades

Stairs and guards are safe for the trades to use, and floor openings are covered.

Fixture and layout information — confirmed

And the fixture and layout information is confirmed: plumbing fixtures, lighting plan, appliance specifications, and the mechanical design. Trades cannot rough in what has not been decided.

Scenario: the framer is behind schedule

The situation: The framer is two weeks behind. They have a smaller crew than promised because they’re working on another builder’s job. Your rough-in trades are booked next week.

Here is a situation many builders face. The framer is two weeks behind schedule. They have a smaller crew than promised, because they are also working on another builder’s job. Your rough-in trades are booked for next week. What do you do?

Talk directly — with the owner of the framing company

First, talk directly with the owner of the framing company, not just the crew.

Get a recovery plan — with crew size and dates

Second, ask for a written recovery plan, with crew size and dates. Remind them of the schedule in their contract.

Adjust the trades — before they arrive

Third, adjust the trades before they arrive. Rebook them, or have them start in areas that are ready.

Use your contract — and plan a backup

And fourth, use your contract if the framer does not recover, and plan a backup. Keep a relationship with a second framer for situations like this, as we discussed in Chapter Eight.

Windows and exterior doors

Windows and doors are usually installed near the end of framing, and they are critical for keeping water out.

Rough openings — the right size

Check rough openings are the right size for the windows ordered.

Sill protection and flashing — as designed

Install sill protection and flashing as designed, so water that gets in can drain out.

Follow the manufacturer’s installation instructions

Follow the manufacturer’s installation instructions, and the building envelope details, which we will discuss in Chapter Fifteen.

Air seal around the frames

Air seal around the window and door frames, with approved products.

Protect them — during construction

Protect windows and doors during construction from scratches, paint, and damage.

Scenario: the client wants to move a window

The situation: During framing, the client visits and asks to move a window 60 cm to the left and make it larger. The windows are already ordered.

Here is a common request during framing. The client visits, and asks to move a window sixty centimetres to the left, and make it larger. The windows are already ordered. What do you do?

Don’t agree on the spot

First, do not agree on the spot. Moving and enlarging a window affects many things.

Check structure, code and energy impacts

Second, check the impacts: the header and structure, shear walls, code requirements like spatial separation near property lines, and the energy model.

Price it — including the window order

Third, price it, including changes to the window order, framing, engineering, and any delay.

Change order in writing — before the work

And fourth, prepare a written change order, as we discussed in Chapter Ten, and get it signed before doing the work.

Framing deficiencies and handover

Before the framer leaves, close out their work properly.

A deficiency list — walked together

Walk the house together and make a written deficiency list.

Fixed before final payment

Agree that deficiencies are fixed before final payment, as your contract allows.

Clean up — and remove waste

Make sure the framer cleans up and removes waste as agreed.

Return trips — for later items

Plan return trips for items needed later, like fixing damage, or framing items after mechanical rough-in.

Holdbacks — as the Builders Lien Act requires

And remember the holdback requirements under the Builders Lien Act, which we discussed in Chapter Nine.

Framing a garage, suite or laneway home

Many BC projects include an attached garage, a secondary suite, or a laneway home. Each has special framing details.

Garages — fire separation and the door header

Attached garages need a fire separation from the house, and a large header over the garage door.

Suites — fire separation and sound

Secondary suites need fire separations, and sound control between units, which affect wall and floor framing.

Laneway homes — spatial separation near property lines

Laneway homes are often close to property lines, which limits window sizes and requires fire rated walls.

Separate drawings — check them carefully

These often have their own drawings, or special details. Check them carefully with the framer.

Inspections — may have extra items

Inspections may include extra items, like fire separation details. Prepare for them.

Knowledge check

A client asks to move and enlarge a window during framing. What should you do?

  • Agree on the spot
  • Check structure, code and energy impacts, price it, and use a written change order
  • Refuse
  • Ask the framer to just do it
Show the answer

The answer is: check the impacts on structure, code and energy, price it, and prepare a written, signed change order before doing the work.

Exterior sheathing and the weather barrier

Before the house is clad, the exterior sheathing and weather barrier must be complete.

Sheathing — fully nailed and gapped

Exterior sheathing fully nailed, with the right gaps between panels.

Weather barrier — lapped like shingles

The weather barrier, or house wrap, lapped like shingles, so water runs down and out.

Windows and doors — integrated with the barrier

Windows and doors integrated with the weather barrier and flashings.

Penetrations — sealed

Penetrations for vents, pipes and wires sealed.

Next chapter — the full envelope

We will look at the full building envelope, including rainscreen, air barriers, and insulation, in Chapter Fifteen.

Lockup — a major milestone

Lockup, when the house is closed in with roof, windows, and doors, is a major milestone.

Roof on — with underlayment or roofing

The roof is on, with underlayment or finished roofing.

Windows and exterior doors installed

Windows and exterior doors are installed and secured.

The house can be locked

The house can be locked, protecting materials and work inside.

Often a payment milestone — for lenders

It is often a payment milestone for lenders and in the client contract, as we discussed in Chapter Nine.

Celebrate it — and update the client

Celebrate it with the client, and update the schedule. From here, the work moves inside.

Learning from every framing stage

As with the foundation, capture what you learned from each framing stage.

Actual cost versus estimate

Compare the actual framing cost to your estimate, including materials, labour, cranes, and extras.

Actual duration versus schedule

Compare the actual duration to your schedule, and note what caused delays.

Inspection and engineer findings

Record the inspection and engineer findings, and add them to your checklists.

Trade performance — quality, safety and reliability

Note the framer’s performance: quality, safety, reliability, and how they handled problems.

Update your templates — for the next house

And update your templates, checklists, and estimating data for the next house. Each house should be a little better than the last.

Chapter 14 — key takeaways

Let’s review the key takeaways from this chapter.

Prepare — latest drawings, clear scope, right materials

One. Prepare well: latest drawings, a clear scope with the framer, and the right materials, stored dry.

Respect the structure — load paths, shear walls, connections

Two. Respect the structure: load paths, shear walls, hold downs, and connections, exactly as designed.

Engineered products — follow the manufacturer, never cut

Three. Follow the manufacturer’s rules for engineered products. Never cut trusses or joist flanges.

Manage moisture — never enclose wet framing

Four. Manage moisture, and never enclose wet framing.

Check quality early — and pass the framing inspection

And five. Check quality as it goes up, prepare for the trades, and pass the framing inspection the first time.

Coming up in Chapter 15

In Chapter Fifteen, we look at the building envelope.

Keeping water out — and heat in

We will look at keeping water out, and heat in,

Air barriers, insulation and windows

air barriers, insulation and windows,

The BC Energy Step Code

and the BC Energy Step Code. But first, the quiz.

Chapter 14 Quiz

1. What should be done with superseded drawings on site?

  • Keep them in the truck
  • Remove them — framing must follow the latest revisions
  • Give them to the client
  • Use them for estimates
Show the answer

Answer: B — Remove them, so nobody frames from an old drawing.

2. A point load from a beam must be:

  • Ignored
  • Carried all the way to the foundation with posts and blocking
  • Supported by drywall
  • Moved by the framer
Show the answer

Answer: B — Carried all the way down to the foundation.

3. What resists the sideways forces of an earthquake in a wood-frame house?

  • Drywall only
  • Shear walls with specified nailing, hold-downs and connections
  • Windows
  • Paint
Show the answer

Answer: B — Shear walls with specified nailing, hold-downs and connections.

4. Over-driven nails in shear wall sheathing:

  • Make it stronger
  • Reduce the strength of the wall
  • Have no effect
  • Are required
Show the answer

Answer: B — They reduce the wall’s strength.

5. Holes in I-joists are allowed:

  • Anywhere
  • Only where and as large as the manufacturer allows — never through flanges
  • Only in flanges
  • Never
Show the answer

Answer: B — Only as the manufacturer’s charts allow, never through flanges.

6. Roof trusses may be cut or altered:

  • If small
  • Only with an engineered repair
  • Whenever needed
  • By any trade
Show the answer

Answer: B — Only with an engineered repair.

7. Why should wet framing never be enclosed?

  • It’s heavier
  • It shrinks and can grow mould, causing cracks, pops and moisture problems
  • It looks bad
  • It’s cheaper
Show the answer

Answer: B — It shrinks and can grow mould.

8. Blocking for cabinets, grab bars and TV mounts should be installed:

  • After drywall
  • During framing, and photographed
  • Never
  • By the homeowner
Show the answer

Answer: B — During framing, with photos for the homeowner.

9. What does fire blocking do?

  • Holds up the roof
  • Stops fire spreading through concealed spaces
  • Keeps water out
  • Reduces noise only
Show the answer

Answer: B — Stops fire spreading through concealed spaces.

10. Before the framing inspection, you should:

  • Insulate
  • Walk the house yourself with a checklist and fix issues first
  • Drywall the garage
  • Do nothing
Show the answer

Answer: B — Do your own pre-inspection walk with a checklist.

Rules and figures change. Confirm current BC Housing, municipal, WorkSafeBC and warranty provider requirements before publishing.

Please note: This course is general information from our own experience as builders, not legal, financial or professional advice. Laws, codes, bylaws, fees and requirements change often and differ from city to city, so some details may have changed since this was published. Always confirm current requirements with BC Housing, your city, WorkSafeBC, your warranty provider and qualified professionals.