Welcome to Chapter Fourteen of Running a Residential Build in BC, Start to Finish. This chapter is about Framing. I am Mandeep Singh, a licensed residential builder in British Columbia. Framing is the stage when the house finally appears. It moves fast, it involves big money, and it sets the quality for every trade that follows. This chapter gives practical, general information. The BC Building Code, your structural engineer’s drawings, and the manufacturers’ instructions always govern your specific project.
Quick recap of Chapter 13
Let’s quickly recap Chapter Thirteen.
Prepare before digging — and work with the geotechnical engineer
We learned to prepare carefully before digging, and to work closely with the geotechnical engineer.
Accurate, inspected footings and walls — with hold-downs in place
We built accurate, inspected footings and walls, with hold downs and anchor bolts exactly where the drawings show.
Drainage, damp-proofing, soil gas and grading
And we installed drainage, damp-proofing, and soil gas control, and graded water away from the house. Now, the house goes up.
By the end of this chapter you will be able to:
Here are the learning outcomes for this chapter.
Prepare for framing — drawings, materials and the framer
One. Prepare for framing: drawings, materials, and the framing contractor.
Understand the structural system — loads, beams, shear walls
Two. Understand the structural system: load paths, beams, and shear walls.
Manage engineered products — joists, trusses and beams
Three. Manage engineered products, like I-joists, trusses, and engineered beams.
Control moisture and protect the frame
Four. Control moisture, and protect the frame from our wet climate.
Check framing quality — and pass the framing inspection
Five. Check the framing quality, and pass the framing inspection.
Prepare the house for the trades that follow
And six. Prepare the house for the trades that follow.
Part 1 — Preparing for framing
Why framing matters so much
Let’s start with why framing deserves so much attention.
It carries the house — for its whole life
The frame carries the house for its whole life: its weight, the people and furniture, snow on the roof, wind, and earthquakes.
It sets the quality — for every trade after
It sets the quality for every trade that follows. Crooked walls mean bad drywall, bad cabinets, and bad tile.
It’s a big part of the budget — and the schedule
It is a big part of the budget, and of the schedule. A good framing stage keeps the whole project on track.
Mistakes get covered quickly
And mistakes get covered quickly, by sheathing, insulation, and drywall. They must be caught while the frame is open.
The framing sequence
Let’s look at the typical sequence of framing a house, from the foundation up.
Sill plates and the first floor system
First, the sill plates are installed on the foundation, with the sill gasket and anchor bolts, followed by the beams and the first floor system.
Walls — laid out, framed, sheathed and stood
Next, the walls are laid out on the floor, framed, often sheathed while flat, and then stood up, plumbed, and braced.
Upper floors — repeat
Upper floors repeat the process: floor system, then walls.
Roof — trusses or rafters, then sheathing
Then the roof: trusses or rafters, bracing, and roof sheathing, followed by the underlayment.
Windows, doors, stairs and details
Finally, windows and exterior doors, stairs, blocking, backframing, and details. On a typical house, this takes several weeks to a few months, depending on size and complexity.
Layout — the first day matters most
The framing layout on the first floor sets the accuracy of the whole house.
Check the foundation — before the sill plates
Check the foundation dimensions, square, and level before the sill plates go down. Deal with any errors now.
Snap lines — from the drawings, not the foundation edge
Snap wall lines from the drawings, measured from established reference lines, not just from the edge of the foundation.
Check diagonals — every floor
Check diagonals for square on every floor.
Mark plumbing and mechanical locations
Mark the locations of toilets, tubs, drains, and major ducts, so the framing leaves room for them.
A walk-through — before walls go up
Walk through the layout with the framer before the walls go up. Moving a wall line in chalk is free. Moving a standing wall is not.
Plate heights and floor elevations
Heights are as important as dimensions. Small errors add up over several floors.
Wall plate heights — as on the drawings
Build walls to the plate heights shown on the drawings. Pre-cut studs come in standard lengths, but your design may need something different.
Floor system depths — confirmed with the supplier
Confirm the actual depth of the floor system with the supplier. Engineered joists come in specific depths, and a change in depth changes everything above.
Building height — check it during framing
Check the building height during framing against the zoning limit, especially on houses that were designed close to the maximum.
Ceiling heights — for suites and finishes
Check finished ceiling heights, especially in basement suites, where minimum heights apply, and under ducts and beams.
Measure at every floor — not just the top
Measure at every floor, not just at the top. It is much easier to correct a small error on the first floor than to discover a large one at the roof.
Drawings the framer needs
Before framing starts, the framer needs a complete, current set of drawings.
Architectural drawings — layout, heights and openings
Architectural drawings, showing the layout, wall heights, window and door openings, and stairs.
Structural drawings — beams, posts, shear walls and connections
Structural drawings, showing beams, posts, shear walls, hold downs, and connections.
Engineered product layouts — joists and trusses
Layouts for engineered products from the suppliers, like floor joist layouts and roof truss drawings.
Window and door schedules — with rough opening sizes
Window and door schedules, with rough opening sizes confirmed with the supplier.
The latest revisions — and old ones removed
And the latest revisions, with old drawings removed from site. Framing from an old drawing is one of the most common and costly mistakes.
Questions to answer before framing
Before framing starts, resolve the questions that commonly cause delays.
Window and door sizes — confirmed and ordered
Are the windows and exterior doors confirmed, and ordered, with rough opening sizes?
Stairs — type, finish and dimensions
Are the stairs designed: the type, the finished floor heights, and the finish materials, which affect the rise?
Finished floor heights — for each room
Do you know the finished floor materials in each room? Tile and hardwood heights affect door clearances and stair rises.
Tubs, showers and special fixtures
Are the tubs, shower bases, and special fixtures selected? Some need specific framing or support.
Mechanical routes — ducts and drains
And are the mechanical routes planned? Each unanswered question becomes a delay, or a change, during framing.
A framing pre-start meeting
Hold a short pre-start meeting with the framer before work begins. It prevents many problems.
Walk through the drawings — page by page
Walk through the drawings together, page by page, especially the structural details, shear walls, and hold downs.
Confirm the schedule and crew
Confirm the schedule, the crew size, and the key dates, like truss delivery and crane day.
Safety — the fall protection plan for each stage
Review safety, especially the fall protection plan for each stage, guardrails, and floor openings.
Site rules — deliveries, waste, parking and neighbours
Review your site rules: deliveries, waste, parking, working hours, and how to treat the neighbours.
How changes and questions will be handled
And agree how questions and changes will be handled. Nobody changes anything without asking you first, and changes are in writing.
Choosing and contracting the framer
As we discussed in Chapter Eight, choose and contract your trades carefully. Framing is one of the most important.
Experience with your type of house
Choose a framer with experience in your type of house: size, complexity, and engineered systems.
Clear scope — what’s included and what isn’t
Agree on a clear scope: walls, floors, roof, sheathing, stairs, blocking, backframing, windows, and clean up. Who installs windows and exterior doors? Who does fire blocking?
Price — per square foot, lump sum, or labour only
Agree on the price, whether per square foot, lump sum, or labour only, and what is extra.
Schedule and crew size
Agree on the schedule, and the crew size needed to meet it.
Safety — fall protection plan and documentation
And confirm safety: their fall protection plan, training, WorkSafe BC registration, and clearance letter, as we discussed in Chapter Twelve.
Paying the framer
Framing payments are large. Structure them clearly.
Progress payments — tied to stages
Tie progress payments to clear stages, like floor systems complete, walls complete, roof complete, and lockup.
Check the work — before each payment
Check the work before each payment, including quality and safety.
Holdback — as required by law
Keep the holdback required by the Builders Lien Act.
Deficiencies — fixed before final payment
Keep enough back to cover deficiencies, as your contract allows.
Clearance letter — before final payment
And get a current WorkSafe BC clearance letter before final payment, as we discussed in Chapter Eight.
Pricing framing in your estimate
As we discussed in Chapter Six, a good estimate starts with understanding what drives the cost. For framing, these are the main drivers.
Floor area — the starting point, not the whole story
Floor area is the usual starting point, and many framers quote per square foot. But the square footage alone does not tell the whole story, so read the quote carefully.
Complexity — corners, roof lines, vaults and heights
Complexity drives cost: the number of corners, complicated roof lines, vaulted ceilings, tall walls, and cantilevers all take more labour and more material.
Engineered products and steel
Engineered beams, engineered joists, and any steel add material cost, and sometimes crane time and special installation.
Shear walls and seismic hardware
Shear walls, hold downs, and straps add material and labour, especially on houses with many windows and few solid walls.
Site access and season
And site access and season matter. A tight lot with no room for material, or a winter build with rain delays, will cost more than a wide open lot in summer.
Labour-only or supply-and-install?
Framers can be hired in two main ways. Each has advantages and risks for the builder.
Labour-only — you supply the materials
With a labour only contract, the builder buys the lumber package and the framer supplies the labour. You control the material quality and price, but you also carry the risk of shortages, wrong deliveries, and waste.
Supply-and-install — the framer supplies everything
With a supply and install contract, the framer supplies both the materials and the labour. Your price is more certain, but you have less control over material choices, and you must check substitutions carefully.
Either way — engineered products must match the drawings
Either way, engineered products, beams, and connectors must match the drawings exactly, and substitutions need the engineer’s approval.
Define responsibility for waste, theft and shortages
Define in writing who is responsible for waste, theft, damage, and shortages.
Choose what fits your business
Choose the method that fits your business, your cash flow, and your ability to manage materials on site. Many builders use both, depending on the project.
Materials — ordering the package
The framing materials are usually ordered as a package from a lumber supplier.
A takeoff — from the drawings
The supplier or framer does a takeoff from the drawings, listing every piece needed.
Check the takeoff — against the drawings
Check the takeoff yourself, especially beams, posts, engineered products, and sheathing for shear walls.
Lead times — for trusses and engineered products
Know the lead times, especially for trusses, engineered joists, and large beams, which can take weeks.
Delivery — staged, not all at once
Plan deliveries in stages if the site is tight, so materials are not damaged or in the way.
Storage — off the ground and covered
Store materials off the ground, on supports, and covered from rain. Wet lumber causes problems later.
Scenario: the wrong beam was delivered
The situation: The lumber delivery includes an LVL beam one size smaller than the structural drawings show. The framer says: ‘It’s close enough — we’ll double it up with a 2×10.’
Here is a situation that happens on many sites. The lumber delivery includes an L.V.L. beam one size smaller than the structural drawings show. The framer says: it is close enough, we will double it up with a two by ten. What do you do?
Don’t install a substitute — without approval
First, do not install a substitute without approval. Close enough is not a structural calculation.
Call the supplier — get the correct beam
Second, call the supplier, and get the correct beam delivered.
If time is critical — ask the engineer about alternatives
Third, if time is critical, ask the structural engineer whether an alternative is acceptable. If they approve one, get it in writing.
Check every engineered product on delivery
And fourth, check every engineered product on delivery against the drawings, so mistakes are caught before they are installed.
Treated lumber and fasteners
Some framing materials need special care.
Treated lumber — where wood touches concrete or soil
Treated lumber is used where wood is in contact with concrete or near the ground, as the code requires.
Corrosion-resistant fasteners — with treated lumber
Treated lumber can corrode ordinary fasteners. Use hot dip galvanized or stainless fasteners and connectors, as the manufacturer requires.
Cut ends — treated as required
Cut ends of treated lumber may need field treatment.
The right nails — size and type as specified
Use the right nails: the size and type specified for shear walls, connectors, and sheathing. Not every nail in the gun is the right nail.
Connectors — the right model, every hole
Use the exact connector model specified, with every required hole filled with the right fastener.
Framing waste and site cleanliness
Framing creates a lot of waste. Managing it keeps the site safe and saves money.
Bins — sized and placed for framing
Order bins sized for the framing stage, placed where they can be filled and swapped easily.
Sort where you can — wood, metal and cardboard
Sort waste where you can. Clean wood, metal, and cardboard can often be recycled, which may reduce disposal costs and help meet city requirements.
Daily clean-up — in the contract
Make daily clean up part of the framer’s contract, especially cut-offs on floors and around edges, which cause trips and falls.
Re-use off-cuts — for blocking
Re-use off-cuts for blocking and backing, where suitable. It reduces waste and cost.
A clean house — for the next trades
And hand over a clean house to the next trades. A clean start makes the rough-in stage faster.
Knowledge check
What is one of the most common and costly framing mistakes?
- Using too many nails
- Framing from an old or superseded drawing
- Starting on a Monday
- Using a nail gun
Show the answer
The answer is: framing from an old or superseded drawing. Make sure the framer has the latest revisions, and remove old drawings from site.
Part 2 — The structural system
Load paths — how weight reaches the ground
Every house has load paths: the routes that weight follows down to the foundation.
Roof to walls to floors to foundation
Loads travel from the roof, through the walls and floors, down to the foundation and footings.
Point loads — must be carried all the way down
Point loads, like the end of a beam or a girder truss, must be carried all the way down, with posts and solid blocking, to the foundation.
Missing a load path — is a serious defect
A missing load path, like a post that lands on nothing, is a serious structural defect.
Follow the structural drawings — exactly
Follow the structural drawings exactly. Do not move posts, beams, or bearing walls without the engineer’s approval.
Check for squash blocks and blocking
Check for squash blocks and solid blocking under posts, where loads pass through floor systems.
Bearing walls — know which ones they are
Not every wall is the same. Some carry loads, and some do not.
Bearing walls — carry loads from above
Bearing walls carry loads from floors or the roof above.
Mark them — on the drawings and on site
Mark them on the drawings and on site, so every trade knows which walls are structural.
Don’t move or cut them — without the engineer
Do not move, cut, or remove them, or make large openings in them, without the engineer’s approval.
Openings — need headers sized for the load
Openings in bearing walls need headers sized for the load above.
Client changes — check before agreeing
When a client asks to move a wall, check whether it is bearing before agreeing, and price the engineering as a change order.
Reading the structural drawings
Builders and site supervisors should be comfortable reading the structural drawings.
The general notes — read them first
Read the general notes first. They contain important requirements for materials, nailing, connections, and field reviews.
Framing plans — beams, posts and bearing walls
The framing plans show beams, headers, posts, and bearing walls on each floor.
Shear wall schedule — types and nailing
The shear wall schedule shows the type of each shear wall, its sheathing, and its nailing.
Details — connections and special conditions
The details show special connections and conditions, like beam pockets, cantilevers, and step downs.
Questions — ask the engineer early
If something is unclear, ask the engineer early, in writing. Do not let the framer guess.
When the drawings don’t work on site
Sometimes what is on the drawings cannot be built exactly as shown. Here is how to handle it properly.
Stop and confirm the conflict
First, stop, and confirm that the conflict is real. Measure, check the latest revisions, and compare the architectural and structural drawings.
Ask the right professional — in writing
Ask the right professional in writing: the designer for layout issues, and the engineer for anything structural. Send photos and a sketch.
Get the answer in writing — with a sketch or revision
Get the answer in writing, with a sketch, a revised detail, or a revised drawing.
Share it with the framer and the inspector
Share it with the framer, keep it on site, and make sure the inspector can see it if asked.
Track any cost or time — as a change if needed
And track any cost or time impact. If it was caused by a design error or a client change, handle it through your change order process.
Shear walls and seismic resistance
As we discussed in Chapter Thirteen, our coast is an earthquake zone. Shear walls keep the house standing.
Shear walls — sheathed walls with special nailing
Shear walls are walls sheathed with plywood or O.S.B., with special nailing patterns, that resist sideways forces.
Nailing — size, spacing and edge distance
The nailing must match the drawings: nail size, spacing at edges and in the field, and distance from the panel edges.
Blocking — at panel edges where required
Blocking at panel edges, where required, so every edge is nailed.
Hold-downs and straps — connected as designed
Hold downs and straps must be connected as designed, to the foundation and between floors.
Over-driven nails — reduce strength
Watch for over-driven nails, where the nail head breaks through the sheathing surface. They reduce the strength of the wall. Adjust the nail gun pressure.
Connections between floors
A house only resists earthquakes and wind if its parts are connected together.
Straps and hold-downs — between floors
Straps and hold downs connect the walls of one floor to the walls or foundation below.
Floor diaphragms — sheathing and nailing
Floors and roofs act as diaphragms, carrying sideways forces to the shear walls. Their sheathing and nailing matter too.
Blocking — to transfer forces
Blocking between joists transfers forces at shear walls and diaphragm edges, where required.
Shrinkage — affects connections
Wood shrinks as it dries, which can loosen connections. Some hold down systems include shrinkage compensation.
The engineer’s field review — catches problems
The structural engineer’s field review checks these connections. Book it before the framing is covered.
Knowledge check
A client asks to remove a wall to open up the kitchen. What should you check first?
- The paint colour
- Whether it is a bearing or shear wall — and get the engineer involved if it is
- Nothing — just remove it
- Only the electrical
Show the answer
The answer is: whether it is a bearing wall or a shear wall. If it is, the engineer must design the change, and it should be priced as a change order.
Beams, headers and posts
Beams and headers carry loads over openings and open spaces.
Sized by the code or the engineer
Beams and headers are sized according to the building code tables, or by the engineer.
Bearing — enough length at each end
Each end needs enough bearing length, as designed, on posts or walls.
Posts — built up or solid, as specified
Posts must be built up or solid, as specified, with the right number of plies and fastening.
No notching or drilling — without approval
Do not notch or drill beams without the engineer’s or manufacturer’s approval.
Hangers and connectors — correctly installed
Install hangers and connectors correctly: the right model, every nail hole filled with the right nail, as the manufacturer requires.
Tall walls, vaulted ceilings and open spaces
Modern house designs often have tall walls, vaulted ceilings, and large open spaces. They need special care.
Tall walls — may need engineered studs
Tall walls may need engineered studs or special design, to resist wind and to stay straight.
Vaulted ceilings — ridge beams and thrust
Vaulted ceilings may need structural ridge beams, and the design must deal with the outward thrust on the walls.
Large openings — big headers and posts
Large window walls and wide openings need big headers and posts, and sometimes steel.
Fewer walls — less bracing
Open spaces have fewer walls, so the remaining shear walls must work harder.
Follow the engineer’s details — exactly
Follow the engineer’s details exactly. These areas are where structural problems most often appear.
Cantilevers and overhangs
Cantilevers, where floors or walls extend past the support below, are common in modern designs.
Designed by the engineer
Cantilevers must be designed by the engineer or follow the code and manufacturer’s limits.
Back-span and connections
The joists must extend back far enough into the house, with the right connections, to hold the cantilever.
Insulation and air sealing — at the underside
The underside of a cantilever is exposed to the outside, so it must be insulated and air sealed carefully. It is a common cold spot.
Water — at the wall connection
Flash the connection between the cantilever and the wall below, so water does not get in.
Check for bounce and deflection
Check the finished cantilever for bounce and deflection, especially under heavy loads like bathtubs or kitchen islands.
Shrinkage in multi-storey wood houses
Wood shrinks across its grain as it dries. In a house with several floors, that shrinkage adds up.
Most shrinkage — in plates, rims and joists
Most shrinkage happens across the width of horizontal members, like plates, rim boards, and sawn joists, not along the length of studs.
It adds up — floor by floor
It adds up floor by floor. A three storey house can shrink noticeably between the foundation and the roof.
Effects — cracks, gaps and stressed pipes
It can cause drywall cracks, gaps at stairs and trim, stressed plumbing stacks, and problems where wood framing meets materials that do not shrink, like concrete, steel, or brick.
Reduce it — dry lumber and engineered products
Reduce it by using dry lumber, and engineered products for rims and joists, which shrink less.
Detail for it — where materials meet
And detail for it where different materials meet, as the designer and engineer specify.
Scenario: the plumber cut the joist
The situation: The plumber has cut a large notch through the bottom of a floor joist to run a drain line. The joist supports a bathroom with a heavy tub.
Here is a very common problem. The plumber has cut a large notch through the bottom of a floor joist to run a drain line. The joist supports a bathroom with a heavy tub. What do you do?
Stop — don’t let it be covered
First, stop, and do not let it be covered. Notches in the bottom of a joist can seriously weaken it.
Check the code or the manufacturer’s rules
Second, check the building code limits for sawn joists, or the manufacturer’s rules for engineered joists. Most do not allow cutting the flanges at all.
Get an engineered repair if needed
Third, if it is outside the rules, get an engineered repair from the engineer or manufacturer, and install it exactly.
Plan service routes before rough-in next time
And fourth, prevent it next time. Plan the drain routes with the plumber and designer before framing, and frame in drops or chases where needed.
Steel in residential framing
Some house designs include structural steel beams or posts.
Shop drawings and fabrication — lead time
Steel needs shop drawings and fabrication, which take time. Order early.
Lifting and placement — plan the crane
Plan how the steel will be lifted and placed, often with a crane, on the same day as other heavy lifts.
Connections — bolted or welded as designed
Connections must be bolted or welded exactly as designed, and sometimes inspected.
Wood-to-steel connections — nailer plates
Wood framing connects to steel with nailer plates or special connectors.
Fire protection and thermal bridging
Consider fire protection, and thermal bridging where steel passes through the building envelope.
Part 3 — Engineered products
I-joists and engineered floor systems
Most new homes in British Columbia use engineered floor joists, like I-joists or open-web joists.
Longer spans, straighter floors
They allow longer spans, and make straighter, quieter floors than sawn lumber.
A layout from the supplier — follow it
The supplier provides a layout. Follow it exactly: joist sizes, spacing, and blocking.
Holes — only where the manufacturer allows
Holes for services are only allowed in certain locations and sizes, as the manufacturer’s charts show. Never cut the flanges.
Rim board, web stiffeners and blocking
Install the rim board, web stiffeners, and blocking where required.
Floor sheathing — glued and fastened
Glue and fasten the floor sheathing as specified. It reduces squeaks, which are one of the most common homeowner complaints.
Floors that don’t squeak or bounce
Squeaky and bouncy floors are among the most common homeowner complaints. Most can be prevented during framing.
Dry, straight joists — installed level
Use dry, straight joists, installed level and at the correct spacing.
Glue and fasten the subfloor
Glue and fasten the subfloor as specified, with the right adhesive, applied before it skins over.
Blocking and bridging — as required
Install blocking and bridging as the layout requires.
Stiffer floors — for tile and long spans
Consider stiffer floors for tile, stone, and long spans, by closer spacing or deeper joists.
Keep the subfloor dry
Keep the subfloor dry, and sweep water off quickly. Wet subfloors swell at the edges, causing humps under flooring.
Knowledge check
What helps prevent squeaky floors during framing?
- Using wet joists
- Gluing and fastening the subfloor as specified, with dry, straight joists
- Leaving the subfloor wet
- Fewer nails
Show the answer
The answer is: dry, straight joists, installed level, and a subfloor glued and fastened as specified, with blocking where required.
Roof trusses
Roof trusses are engineered components, designed by the truss manufacturer for your house.
Truss drawings — sealed by an engineer
The truss drawings are designed and sealed by the manufacturer’s engineer, and the city will want them.
Install exactly as designed — no cutting
Install trusses exactly as designed. Never cut, notch, or alter a truss without an engineered repair.
Bracing — temporary and permanent
Install temporary bracing during erection, and permanent bracing as the truss drawings require. Many truss collapses happen during installation.
Girder trusses — and their connections
Girder trusses carry other trusses. Their hangers, plies, and connections are critical.
Connections to walls — for wind and seismic
Connect trusses to the walls as designed, with clips or straps, for wind uplift and seismic forces.
Crane day — setting trusses
Setting trusses is often done with a crane. Plan it carefully.
Crane location — firm ground, away from power lines
Choose the crane location on firm ground, away from overhead power lines, as we discussed in Chapter Twelve.
Street use permit — if the crane is on the street
Get a street use permit if the crane will be on the street, and plan traffic control.
Truss delivery — timed with the crane
Time the truss delivery with the crane, and stack them so they can be lifted in order.
Fall protection — in place before the lift
Have fall protection in place before the lift, and a plan for how workers will set and brace the trusses.
Weather — wind can stop the lift
Watch the weather. Wind can make lifting trusses dangerous. Have a backup day.
Roof framing details
The roof frame must support the roof and keep the attic healthy.
Roof sheathing — with clips or blocking at edges
Install roof sheathing with clips or blocking at the panel edges, as specified, and with gaps for expansion.
Overhangs and soffits — framed as designed
Frame overhangs and soffits as designed, including any fire protection near property lines.
Attic ventilation — intake and exhaust
Provide attic ventilation, with intake at the soffits and exhaust near the ridge, as the code and design require. Keep insulation from blocking the soffit vents.
Attic access — framed and sealed
Frame the attic access hatch, and plan to seal and insulate it.
Underlayment — as soon as possible
Install the roof underlayment as soon as possible, to protect the house from rain.
Stick-framed roofs and complex roofs
Not every roof uses trusses. Some are stick framed, with rafters, especially complex or vaulted roofs.
Rafters and ridge — sized and designed
Rafters, ridges, hips, and valleys must be sized by the code tables or designed by the engineer.
Ridge beams — for vaulted ceilings
Vaulted ceilings usually need a structural ridge beam, supported by posts down to the foundation.
Thrust — tied or designed for
If there are no ceiling joists tying the walls together, the design must deal with outward thrust on the walls.
Valleys and hips — carry extra loads
Valleys and hips carry extra loads and need proper support.
More skill — and more time
Stick framing takes more skill and time than trusses. Price and schedule it accordingly.
Skylights, dormers and roof openings
Roof openings add character to a house, but they also add structural and water risks.
Framed openings — headers and doubled members
Frame roof openings with proper headers and doubled members, as designed, especially when trusses are interrupted.
Never cut trusses to fit — without a design
Never cut trusses to fit a skylight or dormer. The truss supplier must design the opening.
Dormers — their own structure and flashing
Dormers have their own walls and roofs, and complex flashing where they meet the main roof.
Skylight curbs and flashing kits — as the manufacturer requires
Install skylight curbs and flashing kits exactly as the manufacturer requires.
Plan them early — not during framing
Plan them early, in the design and the truss order, not during framing. Adding a skylight after the trusses are set is costly and risky.
Engineered beams and lumber
Engineered beams, like L.V.L. and glulam, carry heavy loads over long spans.
Strong and straight — but strict rules
They are strong and straight, but they come with strict rules from the manufacturer.
Correct orientation — and correct ply connections
Install them in the correct orientation, and connect multiple plies exactly as specified.
No cutting or drilling — unless allowed
No cutting, notching, or drilling, unless the manufacturer allows it in writing.
Protect them from weather
Protect them from weather. Some engineered products can swell or delaminate if left wet.
Check sizes on delivery
Check sizes and grades on delivery against the drawings. Substitutions must be approved by the engineer.
Product documentation on site
Engineered products come with documentation that inspectors and engineers will want to see.
Truss drawings and layouts
Truss drawings, sealed by the manufacturer’s engineer, and the truss layout.
Joist layouts and installation guides
Floor joist layouts, and the manufacturer’s installation guides, including hole charts.
Beam specifications
Beam specifications, and any engineer approved substitutions.
Connector schedules
Connector schedules, showing which hangers and straps go where.
Keep them on site — and in the project file
Keep them on site during framing, and in the project file afterward. Some go in the homeowner manual.
Scenario: the truss layout doesn’t match the walls
The situation: When the trusses arrive, the framer finds that the girder truss bears on a wall that was moved during design changes. The crane is booked for this afternoon.
Here is a costly situation. When the trusses arrive, the framer finds that the girder truss bears on a wall that was moved during design changes. The crane is booked for this afternoon. What do you do?
Don’t set the girder on the wrong support
First, do not set the girder truss on the wrong support, or on a temporary guess. Girder trusses carry large loads.
Call the truss supplier and engineer — immediately
Second, call the truss supplier and the structural engineer immediately. They may be able to provide a revised bearing detail, a post, or a revised truss.
Set what you safely can — or reschedule the crane
Third, set only what you safely can, with the engineer’s agreement, or reschedule the crane. A crane cancellation is cheaper than a structural failure.
Find out why the revision was missed
And fourth, find out why the revision was missed. The truss supplier must always receive the latest drawings. Add a step to your process to confirm this before every truss order.
Knowledge check
The electrician wants to cut a small notch in the top chord of a roof truss. What is the rule?
- Small notches are fine
- Never cut or alter a truss without an engineered repair
- Only on weekends
- Only if the framer agrees
Show the answer
The answer is: never cut, notch or alter a truss without an engineered repair from the truss manufacturer or engineer.
Part 4 — Moisture and weather
Wet lumber — a BC problem
In our climate, lumber gets wet during framing. Managing that moisture is essential.
Wet framing shrinks as it dries
Wet framing shrinks as it dries, causing nail pops, drywall cracks, squeaky floors, and gaps.
Mould can grow on wet wood
Mould can grow on wood that stays wet too long, especially once it is enclosed.
Never enclose wet framing
Never insulate and drywall over wet framing. Check the moisture content first.
Moisture meter — use it
Use a moisture meter. Check framing in several places before insulation, especially plates, beams, and the floor system.
Plan for drying time — in the schedule
Plan for drying time in the schedule. Get the roof on, and the house closed in, as early as possible.
Checking moisture before close-in
Here is a practical way to check that framing is dry enough before insulation and drywall.
Check several locations — on every floor
Check moisture content in several locations on every floor: plates, studs, joists, beams, and sheathing.
Focus on the wettest areas
Focus on the areas that got wettest: bottom plates, floor systems, and areas near openings.
Follow the target — from the code or the design
Follow the target moisture content from the code or the design. Many builders aim for well under twenty percent before close in.
Record the readings
Record the readings, with dates and locations.
Dry it first — don’t hope it dries later
If it is too wet, dry it first, with time, heat, and dehumidifiers. Do not hope it will dry after the drywall is on.
Framing in the wet season
Many houses in British Columbia are framed between October and April. Plan for it.
Schedule the roof — as early as possible
Schedule the roof as early as possible. Order trusses early, so they are not the delay.
Temporary covers — tarps and roof underlayment
Have temporary covers ready: tarps, and roof underlayment installed as soon as the sheathing is on.
Moisture-resistant materials — where it helps
Consider moisture resistant subfloor products, which tolerate wet weather better.
Drainage holes — in floors during construction
Some builders drill small drainage holes in subfloors during construction, so rain water drains instead of ponding. Check with the manufacturer first.
Drying time — built into the schedule
Build drying time into the schedule before insulation. In winter, it is not optional.
Mould on framing — what to do
Even with good practices, mould can appear on framing in our climate. Here is a practical approach.
Find the cause — and stop the water
First, find the cause, and stop the water. Mould needs moisture. Without fixing the moisture, cleaning does not last.
Light surface mould — clean and dry
Light surface mould on framing can often be cleaned and dried, following good practice and the product guidance.
Heavy growth or damaged material — replace it
Heavy growth, or material that has been damaged by water, may need to be replaced.
Protect workers
Protect the workers doing the clean up, with the right respiratory protection and procedures.
Document it — and tell the client
Document what was found and what was done, with photos and moisture readings, and tell the client. Hiding mould is never the right answer.
Protecting the frame
There are practical ways to protect the frame during construction.
Store lumber covered — off the ground
Store lumber covered, and off the ground.
Drain water off floors — don’t let it pond
Drain or sweep water off floor systems quickly. Do not let it pond on the subfloor.
Roof on fast — and temporary protection
Get the roof sheathing and underlayment on as fast as possible, and use temporary covers where needed.
Close in — windows and doors early
Close in the house with windows and doors early.
Heat and dehumidify — when needed
Use heat and dehumidification to dry the house when needed, especially in winter.
Scenario: three weeks of rain on an open frame
The situation: The roof trusses are delayed. Your second floor has been open to three weeks of heavy rain. The subfloor edges are swollen and there are dark spots on some plates.
Here is a situation that is all too common in our winters. The roof trusses were delayed, and your second floor has been open to three weeks of heavy rain. The subfloor edges are swollen, and there are dark spots on some plates. What do you do?
Get the roof on — as fast as possible
First, get the roof on, and the house closed in, as fast as possible, with temporary protection until then.
Dry the house — heat, dehumidifiers, air movement
Second, dry the house, using heat, dehumidifiers, and air movement.
Check and treat — swollen subfloor and mould
Third, check the damage. Swollen subfloor edges may need to be sanded flat or replaced before flooring. Dark spots may be mould, which must be properly cleaned or the material replaced, following good practice.
Measure moisture — before close-in
And fourth, measure moisture before close in, and record it. It is better to lose a week now than to have mould and cracks in a finished house.
Part 5 — Quality and the framing inspection
Framing quality — what to check
Check framing quality as it goes up, not only at the end.
Walls plumb and straight
Walls plumb and straight, especially in kitchens, bathrooms, and where cabinets and tile will go.
Floors level and flat
Floors level and flat, with no humps at beams or bearing walls.
Openings — the right size and location
Window and door openings the right size, in the right place, and square.
Stairs — rise and run within code
Stairs with consistent rises and runs within the code limits, and proper headroom.
Dimensions — rooms, ceiling heights and layouts
Room dimensions, ceiling heights, and layouts matching the drawings. Small errors here become big problems for cabinets and finishes.
Kitchens and bathrooms — framing extra carefully
Kitchens and bathrooms need extra care during framing, because the finishes there are expensive and unforgiving.
Straight walls — for cabinets and tile
Walls must be straight and plumb for cabinets and tile. Crowned studs show up as gaps behind cabinets and lippage in tile.
Exact dimensions — for cabinets and appliances
Room dimensions must be exact for the cabinet layout and appliances.
Shower and tub framing — per the product
Frame showers and tubs as the product requires, including curb heights, niches, and benches.
Blocking — for everything that hangs
Install blocking for cabinets, shelves, grab bars, and accessories.
Floor support — for heavy tubs and stone
Support floors for heavy tubs, stone, and large islands, as designed.
Stairs, guards and handrails
Stairs are among the most inspected, and most dangerous, parts of a house.
Consistent rises and runs — within code
Rises and runs must be consistent, and within the code limits. Inconsistent steps cause falls.
Allow for finished floors — top and bottom
Allow for the finished floor materials at the top and bottom, so the first and last steps are not different.
Headroom — through the full stair
Provide the required headroom through the full length of the stair.
Guards and handrails — heights and openings
Guards and handrails must meet the code requirements for height, strength, and openings, so children cannot climb or slip through.
Temporary stairs and guards — during construction
And use temporary stairs and guards during construction, as we discussed in Chapter Twelve.
Straightening walls before drywall
Even good framing has some crooked studs. Fix them before drywall.
Check walls with a straight edge or string
Check walls with a long straight edge or string line, especially in kitchens, bathrooms, and long hallways.
Plane, shim or replace crowned studs
Plane down, shim, or replace badly crowned studs.
Check ceilings — for level and flatness
Check ceilings for level and flatness, especially where long lights or crown moulding will be installed.
Check corners — for square
Check corners for square where tile, cabinets, or built-ins will go.
Agree who does it — in the framing contract
Agree in the framing contract who does this straightening, and when. Many builders do a separate pre-drywall framing check.
Common framing defects that inspectors find
Here are framing defects that inspectors commonly find on residential projects.
Missing fire blocking and unsealed penetrations
Missing fire blocking, and penetrations through fire separations that are not sealed.
Shear wall nailing — wrong spacing or over-driven nails
Shear wall nailing with the wrong spacing, or over-driven nails.
Missing or incomplete hangers and connectors
Missing hangers, or connectors with missing nails.
Cut or notched joists, studs and trusses
Joists, studs, and trusses cut or notched by trades.
Stair and guard problems
And stair and guard problems: inconsistent rises, missing handrails, and guards that are too low or have openings that are too wide. Check these yourself before every framing inspection.
Blocking and backing — before it’s too late
Blocking and backing are small pieces of wood that save a lot of trouble later.
Cabinets and shelving
Backing for upper and lower cabinets, and built in shelving.
Handrails, grab bars and towel bars
Backing for handrails, grab bars, and towel bars, where required or planned.
TV mounts and heavy fixtures
Backing for wall mounted TVs, and heavy light fixtures or fans.
Drywall edges — at corners and ceilings
Drywall backing at inside corners and ceiling edges, as the drywall installer needs.
Photograph it — for the homeowner
Photograph the blocking with measurements, for the homeowner manual. Adding it after drywall is expensive.
Fire blocking and fire separations
Fire safety is built into the frame.
Fire blocking — to stop fire spreading in concealed spaces
Fire blocking stops fire from spreading through concealed spaces, like between floors, at stair stringers, and in soffits.
Fire separations — between suites and garages
Fire separations are required between dwelling units, like a main house and a suite, and between the house and an attached garage.
Penetrations — sealed with approved products
Penetrations through fire separations must be sealed with approved fire stopping products.
Coordinate with the trades
Coordinate with plumbers, electricians, and HVAC installers, who make many of these penetrations.
Inspectors check it
Inspectors check fire blocking and separations. Missing them is a common reason for failed inspections.
Balconies and decks over living space
Balconies and decks over living space are a common source of leaks and rot.
Slope — water must drain away
The deck must slope so water drains away from the house.
A waterproof membrane — designed and detailed
A waterproof membrane, properly designed and detailed, is essential.
Door thresholds and wall connections — flashed
Door thresholds and wall connections must be flashed carefully. Many leaks start here.
Guards — attached without making holes in the membrane
Guard posts must be attached without creating holes in the membrane, or with approved details.
Coordinate framing with the membrane installer
Coordinate the framing with the membrane installer before you build it. The framing slope and blocking must suit their system.
Window openings and egress
Window openings must meet several code requirements, not just the window size.
Bedroom windows — for emergency exit
Bedrooms usually need a window large enough for emergency exit, unless there is another exit, as the code requires.
Sill heights — for safety
Windows with low sills on upper floors may need guards, or limited openings, to protect children from falling.
Spatial separation — near property lines
Windows near property lines may be limited in size, or need to be fire rated, as part of spatial separation requirements.
Safety glass — in certain locations
Some locations need safety glass, like near doors, in showers, and near floors.
Check the window schedule — against the openings
Check the window schedule against the framed openings before the windows arrive.
Exterior walls and energy details during framing
Some energy efficiency details are decided during framing, not later.
Insulated headers — where the design calls for them
Insulated headers, or smaller headers where structure allows, leave more room for insulation.
Corners and wall intersections — room for insulation
Framing corners and wall intersections so insulation can reach them, instead of solid blocks of wood that create cold spots.
Air barrier details — at floors and top plates
Air barrier details at the rim joists, top plates, and where interior walls meet exterior walls.
Service cavities — where specified
Service cavities, or strapping on the inside, where specified, so wiring and plumbing do not puncture the air barrier.
Talk to the energy advisor — before framing
Talk to the energy advisor before framing about these details. We will look at the Step Code in Chapter Fifteen.
The framing inspection
The framing inspection is one of the most important inspections on the project.
Usually after rough-ins — before insulation
In most cities, the framing inspection happens after the plumbing, electrical, and mechanical rough ins, before insulation.
Structure, fire safety and code items
The inspector checks the structure, fire blocking and separations, stairs, guards, and other code items.
Engineer field reviews — first
Many cities want the structural engineer’s field review, and sometimes letters of assurance, before or at the framing inspection.
Truss drawings and product documents — on site
Have the truss drawings, joist layouts, and product documents on site.
A pre-inspection walk — by you
Walk the house yourself before the inspection, with a checklist. Fix what you find before the inspector does.
A pre-inspection checklist for framing
Here is an example of a framing pre-inspection checklist.
Structure — beams, posts, point loads, connectors
Structure: beams, posts, point loads carried down, hangers and connectors complete.
Shear walls — nailing, blocking, hold-downs and straps
Shear walls: nailing, edge blocking, hold downs, and straps.
Fire — blocking, separations and penetrations
Fire safety: fire blocking, fire separations, and sealed penetrations.
Stairs, guards, windows and egress
Stairs, guards, and bedroom windows for emergency exit.
Documents — truss drawings, layouts, engineer reviews
And documents: truss drawings, joist layouts, and engineer field reviews. Check every item, and fix what you find.
Knowledge check
Why are inconsistent stair rises dangerous?
- They aren’t
- People expect each step to be the same — inconsistent steps cause trips and falls
- They look old-fashioned
- They squeak
Show the answer
The answer is: people expect every step to be the same height. Inconsistent steps cause trips and falls, so rises and runs must be consistent and within the code limits.
Scenario: the framing inspection fails
The situation: The inspector fails the framing inspection: missing fire blocking at the stairs, and shear wall nailing doesn’t match the drawings in two places. The insulator is booked for tomorrow.
Here is a situation every builder faces at some point. The inspector fails the framing inspection. There is missing fire blocking at the stairs, and the shear wall nailing does not match the drawings in two places. The insulator is booked for tomorrow. What do you do?
Reschedule the insulator — immediately
First, reschedule the insulator immediately. Nothing can be covered until the inspection passes.
Fix the items properly — with the framer
Second, fix the items properly with the framer, as part of their scope.
Get the engineer’s input on the shear walls
Third, get the structural engineer’s input on the shear wall nailing. They may need to review the fix, or specify additional nailing.
Re-book — and learn from the list
And fourth, re-book the inspection, and learn from the list. Add these items to your pre-inspection checklist, so they are caught next time before the inspector arrives.
Engineer field reviews during framing
As we discussed in Chapter Four, when an engineer provides letters of assurance, they must review the work in the field.
Book them in advance
Book the structural engineer’s field reviews in advance, at the stages they require.
Before anything is covered
Make sure the reviews happen before the work is covered.
Fix their items promptly
Fix the items in their field review reports promptly, and let them know when done.
Keep the reports
Keep their reports in the project file.
No letters — no occupancy
Remember that the city may not grant occupancy without the final letters of assurance. Missed reviews can delay the end of the project.
Framing photos — what to keep
Like the foundation, framing is soon hidden. Photograph it before it is covered.
Shear walls — nailing and hold-downs
Shear walls, including nailing patterns, hold downs, and straps.
Beams, posts and connections
Beams, posts, and their connections.
Blocking — with measurements
Blocking for cabinets, grab bars, TVs, and other fixtures, with a tape measure visible.
Every wall — before insulation
Every wall, room by room, before insulation, so plumbing and wiring locations are recorded.
Organized — by floor and room
Organize them by floor and room. Homeowners and future trades will thank you.
Scenario: the inspector questions the stair
The situation: At the framing inspection, the inspector measures the stair and finds the bottom rise is 3 cm taller than the others. The finished floor in the basement will be thin vinyl, not the tile shown on the drawings.
Here is a common inspection finding. At the framing inspection, the inspector measures the stair, and finds the bottom rise is three centimetres taller than the others. The reason is that the basement finish was changed from tile to thin vinyl, which was never communicated to the framer. What do you do?
Accept the finding — and measure everything
First, accept the finding, and measure every rise and run yourself.
Calculate with the real finished floor materials
Second, recalculate the stair using the real finished floor materials at the top and the bottom.
Rebuild the stringers if needed — before finishes
Third, if needed, rebuild or adjust the stringers now, before finishes. It is much cheaper than after the treads and handrails are installed.
Confirm finished floor materials before stairs are framed
And fourth, change your process. Confirm finished floor materials before any stair is framed, and communicate client changes to every trade that is affected.
Knowledge check
When does the framing inspection usually happen?
- Before the foundation
- After rough-ins, before insulation
- After drywall
- At occupancy
Show the answer
The answer is: after the plumbing, electrical and mechanical rough ins, and before insulation, so the inspector can see the structure and fire safety details.
Part 6 — Preparing for the trades that follow
Planning service routes
The frame must leave room for plumbing, ducts, and wiring.
Plan ducts and drains — before framing
Plan duct runs and drain lines before framing, with the mechanical designer and plumber.
Chases and drops — framed in
Frame chases, bulkheads, and dropped ceilings where services will run.
Avoid structural conflicts
Avoid conflicts with beams, joists, and shear walls, so trades do not cut structure.
A rough-in walk-through — with each trade
Do a rough-in walk through with each trade before they start.
Engineered floors — help a lot
Open-web floor joists make service routing easier, and are worth considering in complex houses.
The rough-in stage — coordinating trades
After framing, the plumbing, electrical, and mechanical trades do their rough ins. This is a busy, crowded time.
Sequence them — or coordinate overlap
Sequence the trades, or coordinate how they overlap. Usually, the larger items go in first: ducts and drains, then water lines, then wiring.
Protect the structure — no cutting without approval
Remind every trade: no cutting structure without approval.
Fire stopping — who does it
Agree who does the fire stopping at penetrations.
Check before insulation
Check the rough ins before insulation, as we will discuss in Chapter Sixteen.
Clean up between trades
Keep the house clean between trades, so each one starts on a clear site.
Who cuts what — setting the rules
Most structural damage during rough-in is done by trades who did not know the rules.
A written rule — no cutting structure without approval
Put it in writing in every trade contract: no cutting, notching, or drilling structural members without approval.
Show them the hole charts
Show trades the manufacturer’s hole charts for engineered joists, and post them on site.
Mark no-cut zones
Mark no cut zones, like beams, trusses, and shear walls, on site.
Check after each trade
Check the structure after each trade finishes their rough in.
Back-charge damage — as the contract allows
Back charge the cost of repairs to the trade that caused the damage, as your contract allows. It changes behaviour quickly.
Handover from framing to rough-in — a checklist
Before the rough-in trades start, check that the house is ready for them. A clean handover avoids delays and arguments.
Framing complete — or the remaining items listed
Framing is complete, or the remaining framing items are clearly listed, with dates.
Roof on and house dry — or drying
The roof is on, the house is closed in, and it is dry or drying.
Chases, drops and blocking — in place for the trades
Chases, dropped ceilings, and blocking are in place for the trades’ routes and fixtures.
Stairs and guards — safe for the trades
Stairs and guards are safe for the trades to use, and floor openings are covered.
Fixture and layout information — confirmed
And the fixture and layout information is confirmed: plumbing fixtures, lighting plan, appliance specifications, and the mechanical design. Trades cannot rough in what has not been decided.
Scenario: the framer is behind schedule
The situation: The framer is two weeks behind. They have a smaller crew than promised because they’re working on another builder’s job. Your rough-in trades are booked next week.
Here is a situation many builders face. The framer is two weeks behind schedule. They have a smaller crew than promised, because they are also working on another builder’s job. Your rough-in trades are booked for next week. What do you do?
Talk directly — with the owner of the framing company
First, talk directly with the owner of the framing company, not just the crew.
Get a recovery plan — with crew size and dates
Second, ask for a written recovery plan, with crew size and dates. Remind them of the schedule in their contract.
Adjust the trades — before they arrive
Third, adjust the trades before they arrive. Rebook them, or have them start in areas that are ready.
Use your contract — and plan a backup
And fourth, use your contract if the framer does not recover, and plan a backup. Keep a relationship with a second framer for situations like this, as we discussed in Chapter Eight.
Windows and exterior doors
Windows and doors are usually installed near the end of framing, and they are critical for keeping water out.
Rough openings — the right size
Check rough openings are the right size for the windows ordered.
Sill protection and flashing — as designed
Install sill protection and flashing as designed, so water that gets in can drain out.
Follow the manufacturer’s installation instructions
Follow the manufacturer’s installation instructions, and the building envelope details, which we will discuss in Chapter Fifteen.
Air seal around the frames
Air seal around the window and door frames, with approved products.
Protect them — during construction
Protect windows and doors during construction from scratches, paint, and damage.
Scenario: the client wants to move a window
The situation: During framing, the client visits and asks to move a window 60 cm to the left and make it larger. The windows are already ordered.
Here is a common request during framing. The client visits, and asks to move a window sixty centimetres to the left, and make it larger. The windows are already ordered. What do you do?
Don’t agree on the spot
First, do not agree on the spot. Moving and enlarging a window affects many things.
Check structure, code and energy impacts
Second, check the impacts: the header and structure, shear walls, code requirements like spatial separation near property lines, and the energy model.
Price it — including the window order
Third, price it, including changes to the window order, framing, engineering, and any delay.
Change order in writing — before the work
And fourth, prepare a written change order, as we discussed in Chapter Ten, and get it signed before doing the work.
Framing deficiencies and handover
Before the framer leaves, close out their work properly.
A deficiency list — walked together
Walk the house together and make a written deficiency list.
Fixed before final payment
Agree that deficiencies are fixed before final payment, as your contract allows.
Clean up — and remove waste
Make sure the framer cleans up and removes waste as agreed.
Return trips — for later items
Plan return trips for items needed later, like fixing damage, or framing items after mechanical rough-in.
Holdbacks — as the Builders Lien Act requires
And remember the holdback requirements under the Builders Lien Act, which we discussed in Chapter Nine.
Framing a garage, suite or laneway home
Many BC projects include an attached garage, a secondary suite, or a laneway home. Each has special framing details.
Garages — fire separation and the door header
Attached garages need a fire separation from the house, and a large header over the garage door.
Suites — fire separation and sound
Secondary suites need fire separations, and sound control between units, which affect wall and floor framing.
Laneway homes — spatial separation near property lines
Laneway homes are often close to property lines, which limits window sizes and requires fire rated walls.
Separate drawings — check them carefully
These often have their own drawings, or special details. Check them carefully with the framer.
Inspections — may have extra items
Inspections may include extra items, like fire separation details. Prepare for them.
Knowledge check
A client asks to move and enlarge a window during framing. What should you do?
- Agree on the spot
- Check structure, code and energy impacts, price it, and use a written change order
- Refuse
- Ask the framer to just do it
Show the answer
The answer is: check the impacts on structure, code and energy, price it, and prepare a written, signed change order before doing the work.
Exterior sheathing and the weather barrier
Before the house is clad, the exterior sheathing and weather barrier must be complete.
Sheathing — fully nailed and gapped
Exterior sheathing fully nailed, with the right gaps between panels.
Weather barrier — lapped like shingles
The weather barrier, or house wrap, lapped like shingles, so water runs down and out.
Windows and doors — integrated with the barrier
Windows and doors integrated with the weather barrier and flashings.
Penetrations — sealed
Penetrations for vents, pipes and wires sealed.
Next chapter — the full envelope
We will look at the full building envelope, including rainscreen, air barriers, and insulation, in Chapter Fifteen.
Lockup — a major milestone
Lockup, when the house is closed in with roof, windows, and doors, is a major milestone.
Roof on — with underlayment or roofing
The roof is on, with underlayment or finished roofing.
Windows and exterior doors installed
Windows and exterior doors are installed and secured.
The house can be locked
The house can be locked, protecting materials and work inside.
Often a payment milestone — for lenders
It is often a payment milestone for lenders and in the client contract, as we discussed in Chapter Nine.
Celebrate it — and update the client
Celebrate it with the client, and update the schedule. From here, the work moves inside.
Learning from every framing stage
As with the foundation, capture what you learned from each framing stage.
Actual cost versus estimate
Compare the actual framing cost to your estimate, including materials, labour, cranes, and extras.
Actual duration versus schedule
Compare the actual duration to your schedule, and note what caused delays.
Inspection and engineer findings
Record the inspection and engineer findings, and add them to your checklists.
Trade performance — quality, safety and reliability
Note the framer’s performance: quality, safety, reliability, and how they handled problems.
Update your templates — for the next house
And update your templates, checklists, and estimating data for the next house. Each house should be a little better than the last.
Chapter 14 — key takeaways
Let’s review the key takeaways from this chapter.
Prepare — latest drawings, clear scope, right materials
One. Prepare well: latest drawings, a clear scope with the framer, and the right materials, stored dry.
Respect the structure — load paths, shear walls, connections
Two. Respect the structure: load paths, shear walls, hold downs, and connections, exactly as designed.
Engineered products — follow the manufacturer, never cut
Three. Follow the manufacturer’s rules for engineered products. Never cut trusses or joist flanges.
Manage moisture — never enclose wet framing
Four. Manage moisture, and never enclose wet framing.
Check quality early — and pass the framing inspection
And five. Check quality as it goes up, prepare for the trades, and pass the framing inspection the first time.
Coming up in Chapter 15
In Chapter Fifteen, we look at the building envelope.
Keeping water out — and heat in
We will look at keeping water out, and heat in,
Air barriers, insulation and windows
air barriers, insulation and windows,
The BC Energy Step Code
and the BC Energy Step Code. But first, the quiz.
Chapter 14 Quiz
1. What should be done with superseded drawings on site?
- Keep them in the truck
- Remove them — framing must follow the latest revisions
- Give them to the client
- Use them for estimates
Show the answer
Answer: B — Remove them, so nobody frames from an old drawing.
2. A point load from a beam must be:
- Ignored
- Carried all the way to the foundation with posts and blocking
- Supported by drywall
- Moved by the framer
Show the answer
Answer: B — Carried all the way down to the foundation.
3. What resists the sideways forces of an earthquake in a wood-frame house?
- Drywall only
- Shear walls with specified nailing, hold-downs and connections
- Windows
- Paint
Show the answer
Answer: B — Shear walls with specified nailing, hold-downs and connections.
4. Over-driven nails in shear wall sheathing:
- Make it stronger
- Reduce the strength of the wall
- Have no effect
- Are required
Show the answer
Answer: B — They reduce the wall’s strength.
5. Holes in I-joists are allowed:
- Anywhere
- Only where and as large as the manufacturer allows — never through flanges
- Only in flanges
- Never
Show the answer
Answer: B — Only as the manufacturer’s charts allow, never through flanges.
6. Roof trusses may be cut or altered:
- If small
- Only with an engineered repair
- Whenever needed
- By any trade
Show the answer
Answer: B — Only with an engineered repair.
7. Why should wet framing never be enclosed?
- It’s heavier
- It shrinks and can grow mould, causing cracks, pops and moisture problems
- It looks bad
- It’s cheaper
Show the answer
Answer: B — It shrinks and can grow mould.
8. Blocking for cabinets, grab bars and TV mounts should be installed:
- After drywall
- During framing, and photographed
- Never
- By the homeowner
Show the answer
Answer: B — During framing, with photos for the homeowner.
9. What does fire blocking do?
- Holds up the roof
- Stops fire spreading through concealed spaces
- Keeps water out
- Reduces noise only
Show the answer
Answer: B — Stops fire spreading through concealed spaces.
10. Before the framing inspection, you should:
- Insulate
- Walk the house yourself with a checklist and fix issues first
- Drywall the garage
- Do nothing
Show the answer
Answer: B — Do your own pre-inspection walk with a checklist.
Rules and figures change. Confirm current BC Housing, municipal, WorkSafeBC and warranty provider requirements before publishing.