A free course by Xerox Builders · Instructor: Mandeep Singh, Licensed Residential Builder · All 20 chapters
Opening
Welcome to Chapter Fifteen of Running a Residential Build in BC, Start to Finish. This chapter is about the Building Envelope, Energy Efficiency, and the Step Code. I am Mandeep Singh, a licensed residential builder in British Columbia. The building envelope keeps the weather out and the comfort in. In our wet coastal climate, it is also where many of the most expensive building failures have happened. This chapter gives practical, general information. Energy requirements are changing quickly, and they differ between cities. Always check the current BC Building Code, your city’s bylaws, and your energy advisor’s advice for your specific project.
Quick recap of Chapter 14
Let’s quickly recap Chapter Fourteen.
Respect the structure — load paths, shear walls, connections
We learned to respect the structure: load paths, shear walls, hold downs, and connections, exactly as designed.
Engineered products — never cut without a design
We followed the manufacturer’s rules for engineered products, and never cut trusses or joist flanges.
Manage moisture — and reach lockup
And we managed moisture, passed the framing inspection, and reached lockup. Now we wrap the house in its envelope.
By the end of this chapter you will be able to:
Here are the learning outcomes for this chapter.
Explain what the building envelope does
One. Explain what the building envelope does, and why it matters so much in British Columbia.
Manage water — rainscreen, flashings and windows
Two. Manage water, with rainscreen walls, flashings, and proper window installation.
Build a continuous air barrier — and pass the blower door test
Three. Build a continuous air barrier, and pass the blower door test.
Install insulation and vapour control correctly
Four. Install insulation and vapour control correctly.
Understand the BC Energy Step Code and Zero Carbon Step Code
Five. Understand the BC Energy Step Code, and the Zero Carbon Step Code, and how they affect your projects.
Work with the energy advisor from design to occupancy
And six. Work with the energy advisor, from design to occupancy.
Part 1 — What the envelope does
The building envelope — the house’s skin
The building envelope is everything that separates the inside of the house from the outside.
Roof, walls, windows, doors and foundation
It includes the roof, the walls, the windows and doors, and the foundation and slab.
Controls water — the most important job
Its most important job is to control water: rain, snow, and ground water.
Controls air — leaks waste energy and carry moisture
It controls air movement. Air leaks waste energy, cause drafts, and carry moisture into walls.
Controls heat — insulation
It controls heat flow, with insulation and good windows.
Controls vapour — moisture in the air
And it controls water vapour, the moisture in the air, so it does not condense inside walls and roofs.
BC’s different climates
British Columbia has many different climates, and the envelope must suit the climate where you build.
The coast — wet, mild winters and lots of rain
The coast, including the Lower Mainland and Vancouver Island, has mild, very wet winters. Water management is the biggest challenge here.
The interior — colder winters and hotter summers
The interior has colder winters and hotter, drier summers. Insulation, airtightness, and snow loads become more important.
The north — very cold
The north is very cold, with long heating seasons, and needs even higher insulation and airtightness.
Climate zones — in the code and the Step Code
The building code and the Step Code use climate zones, based on how cold a place is, and set different requirements for each.
Don’t copy details between climates
Do not copy envelope details from one climate to another without checking. A wall that works in Kamloops may not work in Surrey, and the reverse.
Why BC learned the hard way
British Columbia has a hard history with building envelopes.
The leaky condo crisis — in the 1980s and 1990s
In the nineteen eighties and nineteen nineties, many buildings on the coast suffered serious water damage, known as the leaky condo crisis.
Billions of dollars in repairs
Repairs cost billions of dollars, and many homeowners suffered severe financial and personal hardship.
Caused by water getting in — and not getting out
The main cause was water getting into walls, through poor details and face sealed designs, and not being able to drain or dry out.
It changed the rules — rainscreen, licensing and warranty
It changed the rules in British Columbia: rainscreen walls in much of the coast, builder licensing, and mandatory home warranty insurance, which we discussed in Chapter One.
The lesson — details matter
The lesson for every builder is that details matter. Most envelope failures start at small details, like a window corner or a deck connection.
The envelope and your home warranty
As we discussed in Chapter One, every new home in British Columbia needs home warranty insurance. The envelope is a big part of it.
Building envelope coverage — for several years
Home warranty insurance includes coverage for defects in the building envelope, including water penetration, for a period of years, typically five years.
Envelope claims are among the most expensive
Envelope claims are among the most expensive warranty claims, because finding and fixing a leak often means removing cladding and interior finishes.
Warranty providers watch builders’ records
Warranty providers watch builders’ claims records. Repeated envelope claims can affect your ability to get coverage.
Some providers require reviews — or specific details
Some providers require envelope reviews, or specific details, on certain projects.
Good details protect the homeowner — and your business
Good envelope details protect the homeowner, and they protect your business and your reputation.
The cost of getting it right — versus fixing it
Builders sometimes see envelope details as extra cost. Compare that to the cost of failure.
A few hundred dollars per window — for proper details
Proper window details, sill membranes, and flashings may add a few hundred dollars per window, in materials and labour.
Thousands — to repair one leaking window later
Repairing a single leaking window after occupancy can cost thousands: removing siding, replacing rotten sheathing, and repairing interior finishes.
Tens of thousands — for a failed wall
Repairing a whole failed wall can cost tens of thousands of dollars, plus the disruption to the family living there.
Your time, reputation and warranty record
And it costs your time, your reputation, and your warranty record.
The cheapest time to do it right — is the first time
The cheapest time to do it right is the first time. Price the details properly in your estimate, and do not let them be cut.
The four Ds of water management
Building scientists often describe water management with four Ds.
Deflection — keep most water off the wall
Deflection: keep most water off the wall in the first place, with roof overhangs, flashings, and cladding.
Drainage — let water that gets in drain out
Drainage: water that gets past the cladding must have a path to drain out, such as a rainscreen cavity.
Drying — let wet materials dry
Drying: materials that get wet must be able to dry, through ventilation and vapour permeable materials.
Durability — materials that tolerate some moisture
Durability: use materials that can tolerate some moisture without failing.
Deflection and drainage — do most of the work
Deflection and drainage do most of the work. Never rely on caulking alone to keep water out.
Sealants — useful, but not the plan
Caulking and sealants are useful, but they are not a water management strategy.
Sealants age — and fail
Sealants age, crack, and lose adhesion over time, especially in sun and rain.
They need maintenance
They need inspection and maintenance, which homeowners rarely do.
Use them as a second line — not the first
Use them as a secondary line of defence, behind flashings and drained details, not as the main barrier.
Right product — and right joint design
Use the right product for the materials, and the right joint design, with backer rod where needed.
Never seal drainage paths
And never seal the drainage paths that let water out, like weep holes, the bottom of the rainscreen cavity, or window drainage.
Who designs the envelope?
On a house, envelope design responsibility is often unclear. Make it clear.
The designer — walls, roofs and details on the drawings
The house designer or architect shows the wall and roof assemblies, and some details, on the drawings.
The energy advisor — performance targets
The energy advisor sets the performance targets for insulation, windows, and airtightness.
Manufacturers — installation instructions
Manufacturers provide installation instructions for windows, membranes, and cladding, which must be followed.
An envelope consultant — for complex projects
On complex or high value projects, a building envelope consultant may design the details and review the work.
The builder — puts it all together on site
And the builder puts it all together on site. Where the details are missing, ask before building, and get the answer in writing.
Reading wall and roof assemblies on the drawings
The drawings usually show wall and roof assemblies as a list of layers, from outside to inside. Learn to read them carefully.
Every layer — in order, from outside to inside
Each assembly lists every layer, in order, from the outside to the inside: cladding, cavity, weather barrier, sheathing, insulation, vapour control, and the interior finish.
Check each layer — against what was ordered
Check each layer against what was ordered and what the trades plan to install. Substitutions often happen without anyone noticing.
Look for the air barrier — is it identified?
Look for the air barrier. Is it clearly identified? If not, ask the designer which layer it is.
Fire ratings — near property lines and at suites
Look for fire ratings, especially on walls near property lines, and between suites and garages.
Questions — before ordering, not during installation
Ask your questions before ordering materials, not during installation. A wrong layer discovered after cladding is very expensive.
Knowledge check
What was the main cause of the leaky condo crisis?
- Too much insulation
- Water getting into walls through poor details and not being able to drain or dry
- Too many windows
- Earthquakes
Show the answer
The answer is: water getting into walls through poor details and face sealed designs, and not being able to drain or dry out.
Part 2 — Keeping water out
Rainscreen walls
In much of coastal British Columbia, the building code requires a rainscreen wall, or capillary break, behind the cladding.
A drained cavity — behind the cladding
A rainscreen wall has a drained air space, or cavity, behind the cladding, usually created with vertical strapping.
Water that gets past the cladding — drains out
Water that gets past the cladding drains down the cavity, and out at the bottom.
The cavity also helps drying
The cavity also allows air movement that helps the wall dry.
Open at the bottom — with insect screen
The cavity must be open at the bottom, with an insect screen, and must not be blocked by debris or mortar.
Flashings — at every interruption
Flashings at every interruption, like windows, doors, floor lines, and decks, direct water out of the cavity.
Cladding choices and their details
Each type of cladding has its own installation requirements and common problems.
Fibre cement — very common in BC
Fibre cement siding is very common in British Columbia. It needs proper clearances, sealed or painted cut edges, and joint flashings, following the manufacturer. Remember the silica controls when cutting, from Chapter Twelve.
Wood — beautiful but needs care
Wood siding is beautiful, but needs back priming or ventilation, proper fasteners, and maintenance.
Stucco — on a drained cavity
Stucco on the coast is usually installed over a drained cavity, with control joints and careful details at windows and the base of the wall.
Vinyl and metal — follow the system
Vinyl and metal sidings have their own trims and systems. Follow the manufacturer exactly.
Stone and brick veneer — weeps and ties
Stone and brick veneer need a drained cavity, weep holes, ties, and flashings at the base and above openings.
Clearances at the base of the wall
The base of the wall is where water collects. Clearances protect it.
Cladding above the ground — as required
Keep cladding the required distance above the finished ground, so it is not wet from splashing and soil.
Above roofs and decks — at wall junctions
Keep cladding the required distance above roofs and decks where walls meet them.
Base flashing — at the foundation
Install a base flashing where the wall meets the foundation, directing water out.
Keep the cavity open — insect screen, not mortar
Keep the bottom of the rainscreen cavity open, with insect screen, and free of mortar and debris.
Landscaping — must respect the clearances
Make sure landscapers respect the clearances. Many walls are damaged by soil and mulch piled against them after occupancy.
Flashings — the order matters
Flashings must be installed in the right order, so each layer laps over the one below it.
Think like a raindrop
Think like a raindrop. Follow the path water would take down the wall, and make sure every layer sheds water outward.
Sill first — then jambs — then head
At windows, the sill protection goes in first, then the jambs, then the head flashing, each lapping correctly.
Floor-line and transition flashings
At floor lines and changes in cladding, horizontal flashings direct water out of the cavity.
End dams — so water doesn’t run off the ends
Use end dams on flashings, so water does not run off the ends into the wall.
Sketch it — for complex details
For complex details, sketch the sequence before work starts, and show it to the trades.
Knowledge check
At a window, what is the usual order of flashing?
- Head, then jambs, then sill
- Sill protection first, then jambs, then head flashing — each lapping correctly
- Any order
- Only the head
Show the answer
The answer is: sill protection first, then the jambs, then the head flashing, each lapping correctly so water always sheds outward.
The weather barrier — the second line of defence
Behind the rainscreen cavity is the weather resistive barrier, often called house wrap or sheathing membrane.
Sheds water that gets past the cladding
It sheds the water that gets past the cladding, keeping it off the sheathing.
Lapped like shingles — upper over lower
It must be lapped like shingles, upper layers over lower layers, so water always runs out, never in.
Taped and sealed — as the system requires
Seams and penetrations are taped and sealed as the manufacturer’s system requires.
Integrated with windows and flashings
It must be integrated with window and door flashings, in the right order.
Protected from long UV exposure
Do not leave it exposed to sun for longer than the manufacturer allows before cladding is installed.
Windows — the most common leak point
Windows and doors are the most common source of leaks in walls.
Sill protection — a sloped, waterproof sill
Install sill protection, a waterproof, sloped membrane at the bottom of the opening, so water that gets in drains out.
Follow the manufacturer and the envelope details
Follow the window manufacturer’s instructions, and the envelope details for your project.
Flash the head — and lap correctly
Flash the head of the window, and lap the membranes in the right order.
Leave the bottom open to drain — where designed
Do not seal the bottom of the window flange or the sill if the design needs it to drain.
Water test — where possible
Some builders water test a sample window installation, to make sure the details work.
A window installation mock-up
A mock-up is a sample installation, done before the rest of the windows are installed.
Install one window — with every layer
Install one typical window with every layer: sill membrane, flashings, weather barrier, air seal, and trims.
Review it — with the trades and reviewers
Review it with the window installer, the siding installer, and any envelope consultant or reviewer.
Water test it — if practical
Water test it, if practical, before covering it.
Photograph each step
Photograph each step, and use the photos as the standard for every other window.
Everyone builds to the mock-up
Then everyone builds to the mock-up. It is one of the best ways to avoid window leaks.
Protecting windows and the envelope during construction
Once the windows and weather barrier are installed, protect them from damage during the rest of construction.
Protect window frames and glass
Protect window frames and glass from scratches, paint, stucco, and welding or grinding sparks, which can permanently damage glass.
Repair torn house wrap — promptly
Repair torn house wrap promptly, and before the cladding is installed.
Scaffolds and ladders — careful at the wall
Make sure scaffolds and ladders do not damage the weather barrier, flashings, or windows.
Remove protective films — on time
Remove protective films from windows and trims on time. Some films become very hard to remove after long sun exposure.
Check before handover
And check every window and door for damage before handover. Replacing a scratched glass unit after the client moves in is slow and costly.
Roofs, decks and other critical details
Other critical water details on houses include these.
Roof-to-wall flashings — kick-out flashings
Roof to wall junctions, with step flashing and kick out flashings that direct water into the gutter, not into the wall.
Decks and balconies — membranes and thresholds
Decks and balconies over living space, with membranes and door thresholds, as we discussed in Chapter Fourteen.
Penetrations — vents, pipes and lights
Penetrations through the wall, like vents, pipes, lights, and hose bibs, with proper flashing or mounting blocks.
Base of wall — clearances and flashings
The base of the wall, with clearances to the ground, and flashings at the foundation.
Gutters and downspouts — working and connected
And gutters and downspouts, working, and connected, as we discussed in Chapter Thirteen.
Roofing — protecting the top of the house
The roof takes the most weather of any part of the house.
Underlayment — as the manufacturer and code require
Install the underlayment as the roofing manufacturer and code require, with extra protection at eaves, valleys, and penetrations, where needed.
Flashings — valleys, walls, chimneys and skylights
Flash valleys, wall junctions, chimneys, and skylights carefully.
Penetrations — with proper boots and flashings
Use proper boots and flashings for vents and pipes.
Ventilation — matched to the roof design
Make sure the roof ventilation matches the design, or the roof is designed as an unvented assembly.
Low-slope roofs — membranes and drainage
Low slope and flat roofs need membranes designed for them, with good drainage and no ponding.
Exterior doors and thresholds
Exterior doors have a weak point that windows do not: the threshold at the floor.
Sill pan — under the threshold
Install a sill pan, or waterproof membrane, under the door threshold, sloped to the outside.
Step down — to the deck or landing
Where possible, step down from the threshold to the outside surface, so water does not sit against the door.
Accessible thresholds — need extra care
Low or accessible thresholds need extra care with drainage and membranes.
Covered entries — help a lot
Covered entries and roof overhangs help a lot, by keeping rain off the door.
Follow the manufacturer — and test
Follow the door manufacturer’s instructions, and water test critical doors before finishing.
Scenario: stucco crew blocks the cavity
The situation: During stucco application, you notice mortar has fallen into the bottom of the rainscreen cavity on one wall, blocking the drainage. The crew says it will be fine because the wall is under an overhang.
Here is a detail that is easy to miss. During stucco application, you notice mortar has fallen into the bottom of the rainscreen cavity on one wall, blocking the drainage path. The crew says it will be fine, because the wall is under an overhang. What do you do?
Stop and clean it out — before it hardens
First, stop, and have the cavity cleaned out before the mortar hardens.
Explain why drainage matters — even under an overhang
Second, explain why drainage matters, even under an overhang. Wind driven rain, condensation, and small leaks can still put water in the cavity, and it must be able to get out.
Protect the base of the cavity — for the rest of the work
Third, protect the base of the cavity for the rest of the work, for example with a temporary cover or a special drainage product.
Inspect every wall — before final coats
And fourth, inspect the base of every wall before the final coats, and take photos.
Scenario: the siding crew wants to skip the strapping
The situation: Your siding crew says they can save two days by installing the siding directly on the house wrap, without strapping. The house is in a coastal city where a rainscreen is required.
Here is a situation you may face. Your siding crew says they can save two days by installing the siding directly on the house wrap, without the strapping. The house is in a coastal city where a rainscreen is required. What do you do?
Say no — it’s a code requirement here
First, say no. In much of coastal British Columbia, a rainscreen is a code requirement, and the city or the warranty provider may check it.
Explain why — drainage and drying
Second, explain why: the cavity lets water drain and the wall dry. Without it, water trapped behind siding can rot the wall.
Check their other details — flashings and windows
Third, check their other details too, like flashings at windows and floor lines. A crew that wants to skip the strapping may also skip other things.
Inspect before the siding covers anything
And fourth, inspect the wall before the siding covers anything. Take photos of the strapping, flashings, and window details.
Scenario: the leak after the first big storm
The situation: After the first big storm, the drywaller finds a wet stain below a second-floor window corner. The siding is already installed. The window installer says it must be the siding; the siding installer says it must be the window.
Here is a situation many builders face. After the first big storm, the drywaller finds a wet stain below a second floor window corner. The siding is already installed. The window installer says it must be the siding, and the siding installer says it must be the window. What do you do?
Stop the drywall in that area
First, stop the drywall in that area, so the wet framing is not covered.
Investigate — water test if needed, open up if needed
Second, investigate. Water test the window and the wall above it, in sections, starting low and moving up. Open up the siding if needed.
Find the real cause — not the cheapest blame
Third, find the real cause, not the cheapest blame. Often it is a missing sill membrane, a reversed lap, or a missing end dam.
Fix it properly — and check similar windows
And fourth, fix it properly, dry the framing, and check similar windows on the house. If one window has a detail error, others may too. Then decide responsibility based on the facts and your trade contracts.
Knowledge check
What is a window installation mock-up?
- A drawing
- A sample installation with every layer, reviewed and photographed as the standard for the rest
- A cheaper window
- A type of caulking
Show the answer
The answer is: a sample installation of one typical window, with every layer, reviewed, ideally water tested, and photographed as the standard for all the other windows.
Part 3 — Air barriers and airtightness
Why airtightness matters
Airtightness has become one of the most important parts of building a house in British Columbia.
Air leaks waste energy
Air leaks waste a large share of the heat in many houses.
Air carries moisture into walls
Air leaking out of the house carries moisture into walls and roofs, where it can condense and cause rot and mould.
Comfort — fewer drafts
A tight house is more comfortable, with fewer drafts and cold spots.
The Step Code tests it
Under the Step Code, airtightness is measured with a blower door test, and higher steps usually need tighter houses.
Build tight — ventilate right
The saying is: build tight, ventilate right. A tight house needs good mechanical ventilation, which we will discuss in Chapter Sixteen.
Air changes per hour — what the number means
Airtightness is often reported as air changes per hour at fifty pascals.
Measured at a test pressure — fifty pascals
The blower door creates a pressure difference of fifty pascals between inside and outside, similar to a strong wind on all sides.
Air changes per hour — how much air leaks
Air changes per hour at fifty pascals tells you how many times the air in the house would be replaced in an hour at that pressure.
Lower is tighter
A lower number means a tighter house. Older houses may test very high, while a well-built new house can test very low.
The Step Code may use other metrics too
The Step Code and energy advisors may also use other metrics, based on leakage per area of envelope. Your energy advisor will explain the target for your project.
Know your target — before you build
Know your airtightness target before you build, and share it with every trade.
Air barrier approaches — choosing one
There are a few common approaches to the air barrier on houses. Each has advantages.
Exterior sheathing — taped seams
Using the exterior sheathing, with taped seams and sealed transitions, keeps the air barrier outside the wiring and plumbing, so fewer penetrations.
Exterior membrane — a self-adhered or mechanically fastened membrane
An exterior membrane can act as both the weather barrier and the air barrier.
Interior polyethylene — sealed carefully
Interior polyethylene, sealed carefully at every joint and penetration, is a traditional approach, but it is easily damaged by trades.
Airtight drywall — sealed to the framing
Airtight drywall, sealed to the framing with gaskets and sealants, is another approach.
Pick one primary system — and detail it fully
Pick one primary system, and detail it fully. Mixing approaches without clear details creates gaps.
Recessed lights, fans and attic penetrations
Penetrations into the attic are among the worst air leaks, because warm moist air rises into the cold attic.
Airtight-rated recessed lights — or surface lights
Use airtight rated recessed lights, or surface mounted lights, in ceilings below attics.
Bathroom fans — sealed and ducted outside
Seal bathroom fans to the ceiling, and duct them to the outside, never into the attic.
Plumbing stacks and wires — sealed at the top plate
Seal plumbing stacks and wires where they pass through the top plates into the attic.
Attic hatch — insulated and gasketed
Insulate and gasket the attic hatch. It is often the biggest single leak.
Attic moisture — a sign of air leaks
Frost or mould in an attic in winter is usually a sign of air leaks from the house below.
Knowledge check
Where should bathroom exhaust fans discharge?
- Into the attic
- To the outside, through a sealed duct
- Into the wall cavity
- Into the garage
Show the answer
The answer is: to the outside, through a sealed duct. Never into the attic, where the moist air can cause frost and mould.
A continuous air barrier
An air barrier only works if it is continuous, around the whole house.
Choose the air barrier system — and the location
Choose the air barrier system, and where it is in the wall: for example, the exterior sheathing with taped seams, a membrane, or the interior drywall or polyethylene.
Trace it on the drawings — with a pen
A good test is to trace the air barrier on the drawings with a pen, all around the house, without lifting the pen. Every gap is a problem to solve.
Connect at transitions — foundation, floors, roof
Connect it at the transitions: foundation to wall, at floor lines, wall to roof, and at windows and doors.
Seal penetrations — pipes, wires, ducts and boxes
Seal every penetration: pipes, wires, ducts, electrical boxes, and recessed lights.
One person responsible
Make one person responsible for the air barrier. When everyone is responsible, nobody is.
Where houses leak the most
Blower door tests show the same leak locations again and again.
Rim joists and floor lines
Rim joists and floor lines, where floors meet exterior walls.
Top plates and attic hatches
Top plates of walls, and attic access hatches.
Electrical boxes and recessed lights
Electrical boxes on exterior walls and ceilings, and recessed lights.
Plumbing and duct penetrations
Plumbing stacks, drain lines, and duct penetrations, especially into the attic.
Windows, doors and cantilevers
Around windows and doors, at cantilevers, and behind bathtubs on exterior walls. Focus your air sealing on these locations.
Air sealing materials
Choose air sealing materials that are durable and compatible.
Tapes — for sheathing seams and membranes
Tapes for sheathing seams and membranes, rated for the substrate and the conditions.
Gaskets — at sill plates and top plates
Gaskets at sill plates, top plates, and between assemblies.
Spray foam and sealants — for gaps and penetrations
Low expansion spray foam and sealants for gaps and penetrations, used as the manufacturer allows.
Airtight boxes and covers — for electrical
Airtight electrical boxes, or covers, for boxes on exterior walls and ceilings.
Compatibility — check before you use them
Check compatibility between products, for example tapes on a specific membrane. A tape that does not stick is not an air barrier.
The attached garage — air sealing for health
The wall and ceiling between an attached garage and the house need special attention.
Car exhaust and fumes — must stay out of the house
Car exhaust, fuel fumes, and chemicals stored in garages must stay out of the house. Carbon monoxide is deadly.
Airtight — as the code requires
The code requires the separation between the garage and the house to be airtight, as well as fire rated.
Door — self-closing and weather-stripped
The door between the garage and the house must be weather stripped and, where required, self closing.
Penetrations — sealed
Seal every penetration through the separation: pipes, ducts, and wires.
Carbon monoxide alarms — as required
Install carbon monoxide alarms, as required, when there is an attached garage or fuel burning appliance.
Air sealing at the rim joist and floor lines
Rim joists and floor lines are often the leakiest areas in a house. Here is how to get them right.
Seal the sill plate — gasket and sealant
Seal the sill plate to the foundation with a gasket, and seal the joint between the sill and the rim board.
Seal the rim board — to the subfloor and plates
Seal the rim board to the subfloor and to the wall plates above, where the design requires.
Insulate the rim — often with spray foam or rigid board
Insulate the rim joist, often with spray foam, or rigid board sealed at the edges.
Seal penetrations — through the rim
Seal every penetration through the rim: dryer vents, hose bibs, pipes, and wires.
Check with the mid-construction test
And check these areas carefully during the mid construction blower door test.
The blower door test
The blower door test measures how airtight the house is.
A fan in a door — pressurizes the house
A calibrated fan in an exterior door pressurizes or depressurizes the house, and measures the air leakage.
Done by the energy advisor
It is done by the energy advisor, as part of the Step Code compliance.
A mid-construction test — highly recommended
A mid construction test, after the air barrier is complete but before drywall, is highly recommended. You can still find and fix leaks.
The final test — for compliance
The final test, near completion, is used for compliance with the Step Code.
Find leaks — with smoke or thermal cameras
During the test, find leaks with smoke pencils, or thermal cameras, and seal them.
Scenario: the final blower door test fails
The situation: At the final test, the house misses its airtightness target. The house is painted and almost finished. There was no mid-construction test.
Here is a costly situation. At the final blower door test, the house misses its airtightness target. The house is painted, and almost finished. There was no mid construction test. What do you do?
Find the leaks — during the test
First, find the leaks during the test, with the energy advisor, using smoke or a thermal camera.
Seal what you can from the inside — and the attic
Second, seal what you can from the inside, and from the attic: electrical boxes, recessed lights, the attic hatch, plumbing penetrations, and baseboards.
Re-test — and work with the energy advisor
Third, re-test, and work with the energy advisor. If the target still cannot be met, they may be able to show compliance in other ways, by re-modelling with other improvements.
Next time — always test mid-construction
And fourth, change your process. Always do a mid construction test, before drywall. It is far cheaper to fix leaks when the walls are open.
Knowledge check
When is the best time for a mid-construction blower door test?
- Before the foundation
- After the air barrier is complete, before drywall
- After occupancy
- Never
Show the answer
The answer is: after the air barrier is complete, but before drywall, when leaks can still be found and fixed easily.
Part 4 — Insulation and vapour control
Insulation — doing it right
Insulation only performs as rated if it is installed properly.
Fill the cavity completely — no gaps or compression
Fill the cavity completely, with no gaps, voids, or compression. Small gaps greatly reduce performance.
Cut around wires and boxes — don’t stuff
Cut insulation carefully around wires, pipes, and boxes. Do not just stuff it behind them.
Exterior insulation — reduces thermal bridging
Exterior insulation, outside the sheathing, reduces thermal bridging through the studs, and is common at higher Step Code levels.
Attic insulation — depth and baffles
Attic insulation must reach the required depth, with baffles to keep soffit vents open.
Inspected before drywall — in many cities
Many cities inspect insulation and vapour barrier before drywall. It is another hold point.
Insulation types
There are several common insulation types on residential projects. Each has its uses.
Batts — fibreglass or mineral wool
Batts, made of fibreglass or mineral wool, are common in walls and floors. Mineral wool is also fire and water resistant.
Blown-in — cellulose or loose fibre
Blown in insulation, like cellulose or loose fibreglass, is common in attics.
Spray foam — open or closed cell
Spray foam, open cell or closed cell, insulates and air seals in one step, and is used in rim joists, cathedral ceilings, and difficult areas.
Rigid boards — foam or mineral wool
Rigid boards, foam or mineral wool, are used under slabs, on foundations, and as exterior insulation.
Choose for the assembly — not just the R-value
Choose insulation for the whole assembly, considering moisture, fire, air sealing, and cost, not just the R value.
Spray foam — safety and quality
Spray foam is effective, but it needs care.
Installed by trained, certified installers
It must be installed by trained, certified installers, following the manufacturer’s requirements.
Keep other trades out — during and after spraying
Keep other workers out during spraying, and for the re-entry time the manufacturer requires, because of chemical exposure.
Thickness and layers — as specified
Apply it in the thicknesses and layers specified. Too thick in one pass can cause problems.
Fire protection — usually needs a covering
It usually needs a thermal barrier or covering for fire protection, like drywall, as the code requires.
Plan for future access
Remember that spray foam makes future changes to plumbing and wiring harder. Plan service locations carefully.
Cathedral ceilings and flat roofs
Cathedral ceilings and flat roofs are difficult to insulate and ventilate. They need careful design.
Vented or unvented — designed as one or the other
The roof must be designed as either vented, with a ventilation space above the insulation, or unvented, with the insulation and air sealing designed to prevent condensation.
Airtightness — even more critical
Airtightness is even more critical here, because there is no attic space to dry out moisture.
Spray foam or exterior insulation — common solutions
Spray foam, or insulation above the roof deck, are common solutions for unvented roofs.
Follow the designer’s assembly — exactly
Follow the designer’s assembly exactly. Do not substitute materials.
A common source of failures
These roofs are a common source of moisture failures when the details are wrong. Ask questions before you build.
Insulating basements and slabs
Basements and slabs are often forgotten parts of the insulation, but they matter for energy and comfort.
Foundation walls — inside, outside or both
Foundation walls can be insulated inside, outside, or both, as we discussed in Chapter Thirteen. Follow the design.
Moisture — basements need careful vapour control
Basement walls need careful moisture and vapour control, because the concrete can carry moisture from the soil.
Under-slab insulation — before the pour
Under slab insulation must be installed before the pour, and cannot be added later.
Slab edges — a common thermal bridge
Slab edges are a common thermal bridge. Insulate them as designed.
Comfortable basements — help suites and resale
A warm, dry, comfortable basement makes a better suite, and helps resale value.
Insulation and fire safety
Insulation choices also affect fire safety, and the code has rules about them.
Foam plastics — need a protective covering
Foam plastic insulations, including spray foam and rigid foam boards, generally need a protective covering on the interior, like drywall, so they are not exposed in living spaces, as the code requires.
Exposed foam — only where approved
Exposed foam is only allowed in certain locations, with approved products or coatings. Check the code and the product listing before leaving any foam exposed, for example in a crawlspace, garage, or attic.
Near property lines — limits on combustible materials
On walls near property lines, there may be limits on combustible insulation and cladding, as part of spatial separation requirements.
Mineral wool — non-combustible and useful
Mineral wool is non-combustible, and it is often used where fire performance matters, like between suites, at fire separations, and around chimneys.
Penetrations through rated assemblies — fire stopped
And remember that penetrations through fire rated assemblies must be fire stopped with approved products, not just foam. Inspectors check this carefully.
Vapour control
Vapour control manages moisture moving through materials by diffusion.
Usually on the warm side — in our climate
In our heating climate, the vapour barrier or retarder is usually on the warm side of the insulation, as the code requires.
Polyethylene or other approved materials
It may be polyethylene, a vapour retarder paint, or another approved material, depending on the wall design.
Avoid double vapour barriers
Avoid creating two vapour barriers, one on each side of the wall, which can trap moisture.
Exterior insulation — changes the analysis
When there is exterior insulation, the vapour control design may change. Follow the designer’s details.
Air barrier and vapour barrier — not the same thing
Remember that the air barrier and vapour barrier are different functions, even when one material does both.
Exterior insulation — new details to learn
Exterior insulation is becoming common at higher Step Code levels. It brings new details.
Cladding attachment — long screws or clips
The cladding must be attached through the insulation, with long screws through strapping, or special clips, designed for the weight of the cladding.
Window installation — in a thicker wall
Windows sit in a thicker wall, so the window position, flashing, and support details change.
Penetrations — longer and harder to seal
Penetrations through the wall are longer, and need careful sealing and flashing.
Fire — near property lines
Near property lines, the fire performance of the insulation and cladding may be limited by the code.
Get the details from the designer — before framing
Get these details from the designer before framing, and walk the trades through them.
Condensation on windows — homeowner calls
One of the most common calls in the first winter is about condensation on windows.
High indoor humidity — from new materials and living
New houses have high indoor humidity in the first year, from drying concrete, lumber, and finishes, plus cooking, showers, and breathing.
Cold surfaces — glass and frames
Moisture condenses on the coldest surfaces, usually window glass and frames.
Ventilation — run it properly
The solution is usually ventilation: run the ventilation system as designed, and use bathroom and kitchen fans.
Window coverings — can trap cold air
Heavy window coverings can trap cold air against the glass and make it worse.
Explain it — before the first winter
Explain this to homeowners before their first winter, in the homeowner manual and at handover.
Sound insulation — a bonus benefit
Insulation also helps with sound, which clients care about more than many builders realize.
Between suites — required separation
Between a main house and a secondary suite, the code requires sound separation, which affects insulation, framing, and drywall.
Bedrooms and bathrooms — interior walls
Insulating interior walls around bedrooms, bathrooms, and laundry rooms is a popular, inexpensive upgrade.
Floors — between storeys
Insulating floors between storeys reduces noise from footsteps and voices.
Plumbing drains — wrap or choose quieter pipe
Wrap plumbing drains, or use quieter pipe, where they pass near bedrooms and living rooms.
Offer it as an option — in your pricing
Offer sound insulation as an option in your pricing. Many clients choose it once they know about it.
Thermal bridges
A thermal bridge is a path where heat escapes more easily, through materials that conduct heat.
Studs, plates and headers
Studs, plates, and headers are thermal bridges in every wood frame wall.
Slab edges and foundation walls
Slab edges and foundation walls, as we discussed in Chapter Thirteen.
Balconies, beams and steel
Balconies, beams, and steel connections that pass through the envelope.
Window frames and installation
Window frames, and how windows are installed in the wall.
They matter more — as walls get better
Thermal bridges matter more as the rest of the wall gets better. At higher Step Code levels, they must be designed for.
The insulation inspection — what to check first
Before the city insulation inspection, check these items yourself.
Every cavity filled — no gaps or compression
Every cavity is filled, with no gaps or compression, including small spaces around windows and corners.
Rim joists and cantilevers — insulated and sealed
Rim joists and cantilevers are insulated and sealed.
Vapour barrier — sealed at laps, edges and penetrations
The vapour barrier is continuous, sealed at laps, edges, and penetrations.
Attic baffles — and hatch insulation
Attic baffles are installed, and plans are in place to insulate and seal the attic hatch.
Photos — every wall
And take photos of every wall before drywall. They are useful for warranty questions, and future renovations.
Knowledge check
Why should other workers stay out while spray foam is applied?
- To save time
- Because of chemical exposure — they must wait for the manufacturer’s re-entry time
- Because it is noisy
- No reason
Show the answer
The answer is: because of chemical exposure. Workers must stay out during spraying and for the re-entry time the manufacturer requires.
Part 5 — The Step Code and Zero Carbon Step Code
The BC Energy Step Code
The BC Energy Step Code is part of the BC Building Code. It sets energy efficiency targets in steps.
Performance-based — measured, not prescribed
It is performance based. Instead of only prescribing materials, it sets targets that are measured, with an energy model and an airtightness test.
Steps 1 to 5 for houses
For houses, there are five steps. Step One is the base, and Step Five is close to net zero energy ready.
Step 3 — the provincial minimum since 2023
Since May twenty twenty three, new homes across the province must meet at least Step Three, which is about twenty percent more efficient than the older base code.
Cities can require higher steps
Local governments can require higher steps, and many do. Check your city’s requirements for every project.
Higher steps — over time
The province plans to require higher steps over time, with the goal of net zero energy ready buildings by twenty thirty two. Watch for code updates.
How the Step Code is measured for houses
The Step Code uses a few key measurements for houses. Your energy advisor will calculate them.
Energy use — compared with a reference house
The energy model compares the house with a reference house built to the base code, and shows how much better it performs.
Airtightness — from the blower door test
Airtightness, measured by the blower door test.
Envelope and equipment performance
The performance of the envelope, like insulation and windows, and the efficiency of the mechanical equipment.
Higher steps — tougher targets
Each higher step has tougher targets, usually needing better envelopes, tighter houses, and more efficient systems.
Reports — at permit and at occupancy
Reports are submitted at the building permit stage, and again at occupancy, based on the as built house and the final test.
Meeting higher steps — common strategies
Builders use several common strategies to reach higher Step Code levels.
Airtightness — often the cheapest improvement
Better airtightness is often the most cost effective improvement. It costs attention more than money.
Better windows — double to triple glazing
Better windows, sometimes triple glazing, especially on larger window areas.
More insulation — and exterior insulation
More insulation, including exterior insulation, under slab insulation, and attic insulation.
Efficient mechanical systems — heat pumps and heat recovery
Efficient mechanical systems, like heat pumps, and heat recovery ventilators.
Simpler forms — fewer corners and bump-outs
And simpler house forms, with fewer corners, bump outs, and complicated roofs. Simple shapes are easier to insulate and seal.
Pricing energy performance
Energy performance affects your estimate. Price it properly.
Energy advisor fees — modelling and testing
Include the energy advisor’s fees, for modelling, the mid construction test, and the final test.
Better materials — windows, insulation, membranes
Include better materials: windows, insulation, membranes, and tapes.
More labour — for air sealing and details
Include more labour for air sealing and careful details. It takes time to do well.
Mechanical systems — heat pumps and ventilation
Include the mechanical systems needed, like heat pumps and heat recovery ventilation.
Re-testing and fixes — an allowance
And include an allowance for re-testing and fixes, especially on your first projects at a higher step.
Rebates and incentives
There are sometimes rebates and incentives for energy efficient new homes and equipment.
Programs change — check what’s current
Programs change often. Check what is currently available, from the province, BC Hydro, Fortis BC, the federal government, and your city.
Heat pumps and equipment — often supported
Heat pumps and efficient equipment are often supported by rebates.
Higher performance — sometimes rewarded
Some programs reward higher Step Code levels or better performance.
Apply in time — some need pre-approval
Apply in time. Some programs need pre-approval, or an energy advisor’s involvement before construction.
A selling point — for your clients
Rebates are a selling point. Help clients find them, and include them in your proposals where they apply.
Common Step Code problems at occupancy
Some Step Code problems only appear at the end of the project. Here are the common ones.
Failing the final airtightness test
Failing the final airtightness test, because there was no mid construction test.
Equipment installed — different from the model
Mechanical equipment installed that is different from what was modelled, like a less efficient heat pump or ventilator.
Window or insulation substitutions — not re-modelled
Window or insulation substitutions that were never re-modelled.
Missing documentation — product data and commissioning
Missing documentation, like product data sheets, or ventilation commissioning reports.
Avoid them — by keeping the energy advisor informed
Avoid them by keeping the energy advisor informed throughout the project, and collecting documents as you go, not at the end.
The Zero Carbon Step Code
The Zero Carbon Step Code was introduced in twenty twenty three. It limits greenhouse gas emissions from new buildings.
Emission levels — EL-1 to EL-4
It has emission levels, from E L one to E L four. E L four is zero carbon performance.
Focuses on heating and hot water
It focuses on emissions from space heating, hot water, and some other equipment.
EL-1 — the provincial minimum
Since March twenty twenty five, E L one, which is measure and report, has been the provincial minimum.
Many cities require higher — often EL-4
Many cities require higher levels, often E L four, which in practice usually means electric heat pumps for heating and hot water, instead of gas.
Check before design — it affects the mechanical system
Check your city’s requirement before design, because it decides the mechanical system and gas service.
What EL-4 usually means on site
When a city requires the highest emission level, it changes several things on a house project.
Electric heat pumps — for space heating
Space heating is usually provided by electric heat pumps, instead of gas furnaces or boilers.
Electric hot water — often heat pump water heaters
Domestic hot water is usually electric, often with heat pump water heaters.
Gas service — may not be needed at all
Gas service may not be needed at all, which saves the gas connection cost. Some cities may allow certain gas appliances, like cooking or fireplaces, so check the local rules.
Electrical service — may need to be larger
The electrical service may need to be larger. Check early with the electrician and BC Hydro.
Client expectations — explain early
Explain this to clients early, especially those who expect a gas range or gas fireplace.
Scenario: the client wants a gas fireplace
The situation: Your client wants a gas fireplace and gas range. The city requires the highest Zero Carbon Step Code level for new homes. The client says: ‘Just put it in — who will check?’
Here is a conversation many builders are having now. Your client wants a gas fireplace and a gas range. The city requires the highest Zero Carbon Step Code level for new homes. The client says: just put it in, who will check? What do you do?
Check the city’s actual rules — what’s allowed
First, check the city’s actual rules. Some cities may allow certain gas appliances under certain conditions. Know the facts before you answer.
Explain the options — honestly
Second, explain the options honestly, and what the rules allow.
Offer alternatives — electric fireplace, induction range
Third, offer alternatives that clients often love, like electric fireplaces, and induction ranges, which are fast and precise.
Never install something non-compliant
And fourth, never install something that does not comply. The city and the energy advisor will check, and it could delay occupancy. And your licence and reputation are worth more than one appliance.
Knowledge check
What does the highest Zero Carbon Step Code level usually mean for heating and hot water?
- Gas furnace and gas water heater
- Electric heat pumps for heating and electric — often heat pump — hot water
- Wood stoves
- No heating
Show the answer
The answer is: electric heat pumps for space heating, and electric, often heat pump, water heaters, with little or no gas used.
The energy advisor
The energy advisor is a key member of the project team under the Step Code.
Models the house — before the permit
They create an energy model of the house before the building permit, showing it meets the required step.
Recommends the envelope and systems
They recommend insulation levels, windows, airtightness targets, and mechanical systems to meet the target.
Tests the house — mid-construction and final
They do the blower door tests during and at the end of construction.
Confirms compliance — for occupancy
They prepare the final compliance report, which the city needs for occupancy.
Involve them early — and keep them informed
Involve them early, and tell them about any changes to windows, insulation, or systems. Changes can affect compliance.
Energy advisor milestones on your schedule
Put the energy advisor’s work on your schedule, just like inspections.
Design — the pre-construction model
During design, the pre-construction energy model, before the building permit application.
Changes — re-modelled before they’re approved
During construction, any changes to windows, insulation, or systems are reviewed before they are approved.
Mid-construction — the blower door test
At the mid construction stage, the blower door test, after the air barrier is complete, before drywall.
Final — test and documentation
Near completion, the final test, with documentation of the installed equipment and materials.
Occupancy — the compliance report
And at occupancy, the compliance report for the city, and often an EnerGuide label for the homeowner.
Selling energy performance to clients
Energy performance is a selling point, if you explain it well.
Comfort — no drafts, even temperatures
Comfort: no drafts, and even temperatures throughout the house.
Lower energy bills — for the life of the house
Lower energy bills, for the life of the house.
Health — fresh, filtered air
Health: fresh, filtered air from the ventilation system.
Quiet — from good windows and airtightness
Quiet: good windows and airtightness reduce outside noise.
Resale value — and the EnerGuide label
And resale value, supported by the EnerGuide label. Explain these benefits, not just the code requirements.
Scenario: the window substitution
The situation: The window supplier can’t deliver the specified triple-glazed windows on time, and offers double-glazed windows instead. The client is happy — they’re cheaper and faster.
Here is a common situation. The window supplier cannot deliver the specified triple glazed windows on time, and offers double glazed windows instead. The client is happy, because they are cheaper and faster. What do you do?
Don’t approve it — without the energy advisor
First, do not approve it without the energy advisor. The windows may be essential to meeting the required step.
Ask the energy advisor to re-model
Second, ask the energy advisor to re-model the house with the new windows.
Consider compensating changes — or wait
Third, if it no longer complies, consider compensating changes, like more insulation, or better airtightness, or wait for the right windows.
Document the decision — and the client’s approval
And fourth, document the decision, the cost and schedule impact, and the client’s approval in a change order. Failing the Step Code at the end can delay occupancy.
Knowledge check
What is the provincial minimum Energy Step Code level for new homes since May 2023?
- Step 1
- Step 3
- Step 5
- There is none
Show the answer
The answer is: Step Three. Many cities require higher steps, so always check the local requirements.
Part 6 — Managing the envelope on site
Who builds the envelope?
The envelope is built by many trades, which is why it often fails.
Framers — sheathing and sometimes windows
Framers install sheathing, and sometimes windows and the weather barrier.
Roofers — roofing and roof flashings
Roofers install the roofing and roof flashings.
Siding and window installers
Siding installers, and sometimes specialist window installers.
Insulators — insulation and vapour barrier
Insulators install insulation, and often the vapour barrier.
Plumbers, electricians and HVAC — make holes
And plumbers, electricians, and HVAC installers make holes in it. The builder must coordinate all of them, because each one can damage the work of the others.
Sequencing the envelope trades
The order of envelope work matters, and so does the timing between trades.
Roof first — to protect everything else
Get the roof on first, to protect everything else.
Windows and doors — integrated with the barrier
Install windows and doors, integrated with the weather barrier and flashings.
Penetrations — before cladding
Have the trades make their exterior penetrations, for vents, pipes, and wires, before the cladding, with mounting blocks and flashings.
Inspect — before the cladding covers it
Inspect the weather barrier, windows, and penetrations before the cladding covers them.
Then cladding — and final sealants
Then the cladding, trims, and final sealants. Late penetrations through finished cladding are a common source of leaks.
Teaching the trades about the air barrier
Most air barrier damage is done by trades who do not understand it.
Explain it — at the start of each trade
Explain the air barrier at the start of each trade’s work, as part of the orientation.
Show them where it is
Show them where it is, and how to seal their penetrations.
Give them the materials
Give them the right sealing materials, or make sure their contract includes them.
Check after each trade
Check after each trade, and fix damage quickly.
Share the test results
Share the blower door test results with the trades. When they see the numbers, they start to care.
Your first project at a higher step
If you are moving to a higher Step Code level for the first time, plan for a learning curve.
Train your team — before the project
Train your team before the project starts. Many industry groups and energy advisors offer training.
Choose experienced trades — where you can
Choose trades with experience at that level, where you can.
Build in extra time and money
Build in extra time and money for learning, testing, and fixing.
Test early — and often
Test early and often. A mid construction test is essential.
Record what you learn
Record what you learn, and update your details and checklists. The second project is always easier.
Envelope lessons — after every project
As with every stage of the build, learn from every envelope.
Test results — and where the leaks were
Record the blower door test results, and where the leaks were found.
Water problems — during construction and warranty
Record any water problems during construction and during the warranty period, and their causes.
Details that worked — and details that didn’t
Note which details worked well, and which were difficult to build or caused problems.
Trade performance — envelope quality
Note how each trade performed on envelope quality.
Update your standard details
And update your standard details and checklists. Over time, you will build a library of details that work for your company.
Bringing it all together — an envelope checklist
Here is a simple envelope checklist that brings this chapter together. Use it on every project.
Design — assemblies, air barrier, and energy targets clear
At design: the wall and roof assemblies are clear, the air barrier is identified, the energy targets are known, and the Step Code and Zero Carbon requirements for your city are confirmed.
Before close-in — water details inspected and photographed
Before the cladding: the weather barrier, flashings, windows, doors, and penetrations are inspected and photographed, and the rainscreen cavity is open at the bottom.
Before drywall — air barrier tested, insulation and vapour control inspected
Before drywall: the mid construction blower door test is done and leaks are fixed, the insulation and vapour control pass inspection, and every wall is photographed.
Before occupancy — final test and documents
Before occupancy: the final test is passed, and the energy advisor has the documents for the compliance report.
At handover — maintenance explained
And at handover: the homeowner understands how to maintain the envelope and run the ventilation. Follow this checklist, and your envelope warranty calls will be few.
Knowledge check
When moving to a higher Step Code level for the first time, what is a wise approach?
- Do everything the same as before
- Train the team, build in extra time and money, and test early and often
- Skip the mid-construction test
- Use the cheapest trades
Show the answer
The answer is: train your team, choose experienced trades where you can, build in extra time and money, and test early and often.
Envelope inspections and reviews
Several people may review the envelope on your project.
The city — insulation and vapour barrier inspection
The city usually inspects insulation and vapour barrier before drywall.
The warranty provider — on some projects
Your home warranty provider may require envelope reviews on some projects.
A building envelope professional — on complex projects
On complex projects, a building envelope professional may design and review the envelope.
The energy advisor — tests and documentation
The energy advisor tests airtightness and confirms the energy details.
Your own checks — before covering
And your own checks, with photos, before every part of the envelope is covered.
Envelope photos and documentation
Envelope work is hidden quickly. Record it.
Weather barrier and flashings — every elevation
The weather barrier and flashings on every elevation of the house, before cladding.
Windows — sill, jambs and head
Window installations: sill, jambs, and head, at least for each type of window.
Rainscreen — strapping and the base of the wall
The rainscreen strapping, and the base of the wall with the insect screen.
Air barrier details — transitions and penetrations
Air barrier details at transitions and penetrations.
Product data and warranties — for the homeowner manual
And the product data sheets and warranties for the windows, roofing, membranes, and cladding, for the homeowner manual, which we will discuss in Chapter Nineteen.
Envelope maintenance — tell the homeowner
Even a perfect envelope needs maintenance. Tell the homeowner what to do.
Clean gutters and downspouts — every year
Clean gutters and downspouts every year, especially in the fall.
Check sealants — and repaint as needed
Check sealants around windows and penetrations, and repaint wood and other finishes as needed.
Keep soil and plants back from the walls
Keep soil, mulch, and plants back from the walls, and keep the base of the rainscreen open.
Check the roof and flashings
Check the roof and flashings, especially after storms.
Maintenance is part of the warranty
Explain that some warranty coverage depends on reasonable maintenance. Put the schedule in the homeowner manual.
Scenario: the electrician adds an outdoor light after the siding
The situation: After the siding is finished, the client asks for an extra outdoor light. The electrician drills through the siding and house wrap and caulks around the box. It’s on the rainy side of the house.
Here is a very common source of leaks. After the siding is finished, the client asks for an extra outdoor light. The electrician drills through the siding and house wrap, and caulks around the box. It is on the rainy side of the house. What do you do?
Don’t accept caulking as the fix
First, do not accept caulking as the fix. As we discussed, sealants are not a water management strategy.
Install a proper mounting block and flashing
Second, have a proper mounting block installed, with flashing above it, as the siding manufacturer requires.
Repair the weather barrier behind it — properly
Third, repair the weather barrier behind it properly, which may mean removing some siding to lap the membrane correctly.
Price late changes to include envelope work
And fourth, when pricing late changes, include the envelope work, not just the electrical work. Every late penetration through finished cladding needs envelope care.
Chapter 15 — key takeaways
Let’s review the key takeaways from this chapter.
The envelope controls water, air, heat and vapour
One. The envelope controls water, air, heat, and vapour. Water is the most important.
Deflect, drain, dry — rainscreen, flashings and windows
Two. Deflect and drain water, with rainscreen walls, flashings, and properly installed windows. Never rely on caulking alone.
A continuous air barrier — tested mid-construction
Three. Build a continuous air barrier, and test it mid construction.
Insulate properly — and control vapour
Four. Install insulation properly, control vapour, and reduce thermal bridges.
Know the Step Code and Zero Carbon Step Code — and involve the energy advisor
And five. Know the Step Code and Zero Carbon Step Code requirements for your city, and involve the energy advisor from the start.
Coming up in Chapter 16
In Chapter Sixteen, we look inside the walls.
Mechanical, electrical and plumbing
We will look at mechanical, electrical and plumbing,
Ventilation, heat pumps and hot water
ventilation, heat pumps, and hot water,
Coordinating the rough-ins
and coordinating the rough ins. But first, the quiz.
Chapter 15 Quiz
1. What is the most important job of the building envelope?
- Looks
- Controlling water
- Holding up the roof
- Sound
Show the answer
Answer: B — Controlling water.
2. A rainscreen wall has:
- No cladding
- A drained cavity behind the cladding
- Only caulking
- Two vapour barriers
Show the answer
Answer: B — A drained, ventilated cavity behind the cladding.
3. The weather barrier must be lapped:
- Lower over upper
- Upper over lower, like shingles
- In any direction
- Not at all
Show the answer
Answer: B — Upper over lower, like shingles.
4. What is the most common leak point in walls?
- Studs
- Windows and doors
- Insulation
- Drywall
Show the answer
Answer: B — Windows and doors.
5. Kick-out flashings direct water:
- Into the wall
- Into the gutter, away from the wall
- Into the attic
- Onto the deck
Show the answer
Answer: B — Into the gutter, away from the wall.
6. A good way to check the air barrier design is to:
- Guess
- Trace it on the drawings around the house without lifting the pen
- Ask the client
- Paint it
Show the answer
Answer: B — Trace it continuously on the drawings.
7. Who performs the blower door test for Step Code compliance?
- The plumber
- The energy advisor
- The client
- The city clerk
Show the answer
Answer: B — The energy advisor.
8. In our climate, the vapour retarder is usually:
- On the cold side
- On the warm side of the insulation
- On both sides
- Not needed
Show the answer
Answer: B — On the warm side, as the code requires.
9. The Zero Carbon Step Code focuses on:
- Paint colours
- Emissions from heating, hot water and some equipment
- Window sizes
- Roof shape
Show the answer
Answer: B — Emissions from heating, hot water and some equipment.
10. Before approving a window substitution, you should:
- Approve it immediately
- Have the energy advisor re-model the house
- Ask the framer
- Nothing
Show the answer
Answer: B — Have the energy advisor check compliance.
Rules and figures change. Confirm current BC Housing, municipal, WorkSafeBC and warranty provider requirements before publishing.