The air barrier is the first envelope decision on a high-performance home, and it has to be made before framing starts. This Detail shows how to choose the airtight layer, how to check the plan on paper with the pencil test, and how to make sure one person owns it on site.

Why it comes first

  • Air leaks drive heat loss and draughts.
  • Leaking air carries moisture into walls and roofs, where it can condense.
  • Ventilation systems and heat pumps are designed for a tight house, so they only perform as intended when it is tight.
  • Once drywall is up, most of the air barrier is hidden.

The choice changes the sheathing, the way windows are installed, the order of the trades and the testing plan.

The pencil test

Take a section through the house and trace the air barrier all the way around in one colour without lifting your pencil: from the base of the wall, up the wall, across the ceiling and back down. Every place you have to lift the pencil is a detail you must solve. Typical ones are the base of the wall, the rim joist, the top plate under the attic and every window. Do it for the plans, the sections and every penetration.

Four ways to build the airtight layer

Approach How it works
Sealed interior poly Polyethylene behind the drywall, with every lap and edge sealed with acoustical sealant
Airtight drywall The drywall itself, sealed to the framing with gaskets and sealant
Exterior sheathing membrane A taped, airtight membrane over the sheathing, often also the water-resistive barrier
Sealed sheathing Plywood or OSB with every joint taped or sealed

Whichever you choose, the materials must be airtight. The BC Building Code limit for air barrier materials is 0.02 L/(s·m²) at 75 Pa.

Interior or exterior?

Interior Exterior
Floor lines and interior walls Must be sealed at each one Passes by unbroken
Penetrations Many (boxes, pipes, ducts) Few
When you can test it Poly: before drywall. Airtight drywall: only after Before insulation
Weather exposure Protected Needs care while the building is open

BC Housing’s airtightness guide reports that exterior approaches consistently do better, especially on larger buildings.

Primary outside, backup inside

Many high-performance builders use both: a primary air barrier outside (membrane or taped sheathing) and careful sealing inside, which often doubles as the vapour control layer. Two lines of defence make a low blower door result much easier to reach.

Check the vapour profile: if the outside layer has low vapour permeance, the wall needs enough exterior insulation to keep that layer warm, or moisture can collect behind it. Your designer or envelope consultant should confirm the wall assembly.

Make one person own it

  1. Mark the air barrier on every drawing in one colour.
  2. Name one owner, usually the site supervisor.
  3. Brief every trade at the pre-construction meeting.
  4. Protect it, and repair any damage the same day.
  5. Test it with a blower door before insulation and drywall.

What good looks like

Benchmark ACH50
Typical new home (rough) about 3 to 4
Vancouver houses, building by-law maximum 2.5
High-performance home (rough) about 1.0
Passive House limit 0.6

ACH50 is air changes per hour at 50 Pa. Targets change over time and differ between cities, so confirm the current requirement with your city and energy advisor.

Site checklist

  • Air barrier approach chosen and agreed before framing
  • Air barrier drawn in one colour on every plan and section
  • Pencil test done; every break has a drawn detail
  • One owner named on site
  • All trades briefed at the pre-construction meeting
  • Damage repaired the same day
  • Blower door test booked before insulation and drywall

Test yourself

Try to answer each question, then click it to check.

What is the pencil test?

Tracing the air barrier around every section without lifting your pencil. Every place you lift it is a detail you must solve.

Name one advantage of an exterior air barrier.

It passes floor lines and interior walls unbroken, has few penetrations, and can be tested before insulation and drywall.

Who should own the air barrier on site?

One named person, usually the site supervisor, who briefs the trades, protects it and arranges the test.

Next: Detail 02, Air Barrier Materials & Compatibility. New to the physics? Start with our Building Science Deep Dive, lesson 1.3.

Please note: This page is general information, not legal, financial or professional advice. The facts, figures, bylaws, fees and code requirements described here were accurate to the best of our knowledge when it was published or last updated. These rules change often and differ from city to city, so some details may have changed since. Before you make decisions, please confirm the current requirements with your city’s planning and building department and with qualified professionals. We’re always happy to help you check what applies to your property.