The order of work, permits, waterproofing and the decisions that keep a kitchen or bathroom renovation on budget

Kitchens and bathrooms are the most popular renovations, and the most likely to go over budget. The reason is simple: the expensive parts are hidden behind the walls. Plumbing, wiring, ventilation and waterproofing have to be right before the nice finishes go on.

In short: make every design and fixture decision before demolition, get the plumbing and electrical permits, and never skip proper waterproofing in a bathroom. Changes after the walls are closed cost the most.

The right order of work

1Design & permits2Demolition3Rough-in plumbing & electrical4Inspection5Insulation & drywall6Waterproofing (wet areas)7Tile, cabinets & counters8Fixtures & final
A typical sequence. The two gold steps, inspection and waterproofing, are the ones people are tempted to rush.

Permits you’ll likely need

  • Plumbing permit: in Vancouver, any change to the plumbing system needs one, including moving a sink, toilet or shower.
  • Electrical permit: new circuits for appliances, lighting and heated floors.
  • Building permit: if you move or remove walls, especially load-bearing ones.
  • Mechanical permit: if you change heating or add ventilation equipment.

Waterproofing: the step you can’t see

Wall Waterproof membrane Tile setting bed Tile Sloped, waterproofed shower floor to the drain
A shower wall in section: the waterproof membrane goes behind the tile, and the floor is sloped and waterproofed to the drain.

Grout and tile are not waterproof on their own. Showers and tub surrounds need a continuous waterproof membrane behind the tile and a properly sloped, waterproofed floor. Water damage from a poorly built shower is one of the most expensive repairs in a home, and it often isn’t found until it has spread.

Insulation board installed behind a shower base
Preparing the wall behind a shower base before the waterproofing and tile.

Decisions to make before demolition

  1. Layout: moving the sink, toilet or range adds plumbing, venting and electrical work.
  2. Appliances: sizes and power needs (induction ranges and ovens need their own circuits).
  3. Fixtures and tile: order early. Late deliveries stop the job.
  4. Ventilation: a properly ducted range hood and bathroom fan, vented outside.
  5. Lighting: pot lights and under-cabinet lighting are wired at rough-in, not later.

What drives the cost

The biggest cost drivers are moving plumbing, structural changes, cabinet quality, countertop material, tile area and appliance level. A clear, itemized quote lets you see each one and decide where to spend.

Related reading

Please note: This page is general information, not legal, financial or professional advice. The facts, figures, bylaws, fees and code requirements described here were accurate to the best of our knowledge when it was published or last updated. These rules change often and differ from city to city, so some details may have changed since. Before you make decisions, please confirm the current requirements with your city’s planning and building department and with qualified professionals. We’re always happy to help you check what applies to your property.

Planning a new kitchen or bathroom? Book a free site visit and get an itemized quote.

Call 604-786-7000Book a Free Site Visit

Sources

Rules and figures change over time. Confirm the current requirements for your property with your municipality and qualified professionals.

Mandeep Singh, Builder and Director at Xerox Builders
Written by
Mandeep Singh
Builder & Director, Xerox Builders Ltd. · BC Housing Licensed Residential Builder

Mandeep has been a licensed residential builder in BC for almost 10 years. He builds custom homes, laneway homes, duplexes and multiplexes in Vancouver, Burnaby, Surrey and Delta, and writes these guides so homeowners know what to expect before they build.