How Long Does It Take to Build a Custom Home in Vancouver or Burnaby?

“How long will it take?” is usually the second question homeowners ask, right after “how much will it cost?” On a straightforward lot, the answer is simpler than most people expect: building the home itself takes about 10 months, from the foundation to the finished house.

What the 10 months assumes: a relatively flat lot, no significant trees to work around, and no major slope. It counts the build itself, from foundation to completion. It does not include design and permitting beforehand, or elaborate landscaping afterwards. Those are covered separately below.

The 10-month build: time and money, stage by stage

Here’s roughly how those 10 months break down, and how the money is spent along the way. The example below is a 2,500 sq ft single-family home, priced across the mid range of about $250 to $350 per sq ft for construction.

About 10 months from foundation to finishExample: 2,500 sq ft home at a mid-range $300 per sq ft (approximate)StartM1M2M3M4M5M6M7M8M9M10Foundation and underground servicesFraming and roof structureClosing in: roofing, windows, doorsRough-ins: plumbing, electrical, HVACInsulation, air barrier, drywallInterior finishingExterior completion and final inspectionsMoney spent so far (cumulative)0% · $0k25% · $188k50% · $375k75% · $563k100% · $750kStartM1M2M3M4M5M6M7M8M9M1030% · $225k57% · $428k92% · $690k100% · $750kStages shown one after another for simplicity; on site some overlap. Excludes land, design, permits, landscaping and GST.

The schedule and budget at a glance

Stage When Share of build cost Approx. cost (2,500 sq ft) Spent by end of stage
Foundation and underground services Month 0 to 1.5 12% $75k to $105k 12%
Framing and roof structure Month 1.5 to 3.5 18% $113k to $158k 30%
Closing in: roofing, windows, doors Month 3.5 to 4.5 12% $75k to $105k 42%
Rough-ins: plumbing, electrical, HVAC Month 4.5 to 5.5 15% $94k to $131k 57%
Insulation, air barrier, drywall Month 5.5 to 7 10% $63k to $88k 67%
Interior finishing Month 7 to 9 25% $156k to $219k 92%
Exterior completion and final inspections Month 9 to 10 8% $50k to $70k 100%
Total About 10 months 100% $625k to $875k 100%
About the cost range: $250 to $350 per sq ft is the mid-range price. At the high end there’s no limit. Designer imported tile, custom millwork, premium fixtures and top-tier craftsmanship can take the cost as high as you want to go. Interior finishing is where most of that difference shows up, which is why it’s the biggest share of the budget.

Notice how spending follows the schedule: the structure (foundation and framing) uses about 30% of the budget in the first three and a half months, while interior finishing alone accounts for about a quarter. This is also why lenders release construction financing in stages, tied to progress on site.

Each stage has to pass inspection before the work is covered up and the next stage begins. The City of Burnaby’s inspection guide, for example, lists more than a dozen separate inspections for a new house, from foundation forms through framing, insulation and the final inspections.

What happens before construction starts

Before the first footing is poured, the home has to be designed and approved. This happens before the build and isn’t part of the 10 months, but it’s worth planning for:

  • Design and engineering: the survey, architectural drawings, structural engineering, an energy model for the Step Code and, where needed, geotechnical and arborist reports. How long this takes depends mostly on how quickly design decisions are made.
  • Building permit review: this is improving. The City of Vancouver reports that permit processing for single-detached homes dropped to about 160 days in 2025, down from 250 days in 2022, and laneway homes to about 100 days, down from 200. Burnaby has its own process, so timelines there should be confirmed with the City.
A good use of the permit wait: finalize your finishes, such as windows, cabinets, flooring and fixtures, while the permit is under review. Items with long lead times can then be ordered on time, and the build doesn’t stall waiting for decisions.

What can add time to the build

The 10-month figure is for a straightforward site. These are the most common reasons a build takes longer:

  • Sloped lots, which may need retaining walls, shoring or more complex foundations
  • Trees that need protection zones or change where and how the house can be built
  • Demolition of an existing house, including the hazardous materials survey that’s required before older homes come down
  • Complex or custom landscaping, such as extensive hardscaping, water features or large planting plans, which is usually scheduled separately
  • Design changes during construction or late finish selections
  • Site surprises, such as poor soil, groundwater or unexpected utility locations
  • Wet-season weather during foundation and roofing work

How to keep your build on schedule

  • Make the major design decisions before the permit application goes in.
  • Choose windows, cabinets and other long-lead items early, and order them on time.
  • Keep changes to a minimum once construction has started.
  • Ask your builder for a written schedule with milestones, and regular updates against it.

Related reading

Planning a new home in Vancouver or Burnaby and want a realistic timeline for your lot?

Talk to Xerox Builders

Share This Story, Choose Your Platform!

One Comment

  1. […] How long it takes to build a custom home in Vancouver or Burnaby […]

Comments are closed.

Recent Works

Tags

No tags to display. Try to select another taxonomy.