How Long Does It Take to Build a Custom Home in Vancouver or Burnaby?

“How long will it take?” is usually the second question homeowners ask, right after “how much will it cost?” On a straightforward lot, the answer is simpler than most people expect: building the home itself takes about 10 months, from the foundation to the finished house.

What the 10 months assumes: a relatively flat lot, no significant trees to work around, and no major slope. It counts the build itself, from foundation to completion. It does not include design and permitting beforehand, or elaborate landscaping afterwards. Those are covered separately below.

The 10-month build: time and money, stage by stage

Here’s roughly how those 10 months break down, and how the money is spent along the way. The example below is a 2,500 sq ft single-family home, priced across the mid range of about $250 to $350 per sq ft for construction.

About 10 months from foundation to finishExample: 2,500 sq ft home at a mid-range $300 per sq ft (approximate)StartM1M2M3M4M5M6M7M8M9M10Foundation and underground servicesFraming and roof structureClosing in: roofing, windows, doorsRough-ins: plumbing, electrical, HVACInsulation, air barrier, drywallInterior finishingExterior completion and final inspectionsMoney spent so far (cumulative)0% · $0k25% · $188k50% · $375k75% · $563k100% · $750kStartM1M2M3M4M5M6M7M8M9M1030% · $225k57% · $428k92% · $690k100% · $750kStages shown one after another for simplicity; on site some overlap. Excludes land, design, permits, landscaping and GST.

The schedule and budget at a glance

StageWhenShare of build costApprox. cost (2,500 sq ft)Spent by end of stage
Foundation and underground servicesMonth 0 to 1.512%$75k to $105k12%
Framing and roof structureMonth 1.5 to 3.518%$113k to $158k30%
Closing in: roofing, windows, doorsMonth 3.5 to 4.512%$75k to $105k42%
Rough-ins: plumbing, electrical, HVACMonth 4.5 to 5.515%$94k to $131k57%
Insulation, air barrier, drywallMonth 5.5 to 710%$63k to $88k67%
Interior finishingMonth 7 to 925%$156k to $219k92%
Exterior completion and final inspectionsMonth 9 to 108%$50k to $70k100%
TotalAbout 10 months100%$625k to $875k100%
About the cost range: $250 to $350 per sq ft is the mid-range price. At the high end there’s no limit. Designer imported tile, custom millwork, premium fixtures and top-tier craftsmanship can take the cost as high as you want to go. Interior finishing is where most of that difference shows up, which is why it’s the biggest share of the budget.

Notice how spending follows the schedule: the structure (foundation and framing) uses about 30% of the budget in the first three and a half months, while interior finishing alone accounts for about a quarter. This is also why lenders release construction financing in stages, tied to progress on site.

Each stage has to pass inspection before the work is covered up and the next stage begins. The City of Burnaby’s inspection guide, for example, lists more than a dozen separate inspections for a new house, from foundation forms through framing, insulation and the final inspections.

What happens before construction starts

Before the first footing is poured, the home has to be designed and approved. This happens before the build and isn’t part of the 10 months, but it’s worth planning for:

  • Design and engineering: the survey, architectural drawings, structural engineering, an energy model for the Step Code and, where needed, geotechnical and arborist reports. How long this takes depends mostly on how quickly design decisions are made.
  • Building permit review: this is improving. The City of Vancouver reports that permit processing for single-detached homes dropped to about 160 days in 2025, down from 250 days in 2022, and laneway homes to about 100 days, down from 200. Burnaby has its own process, so timelines there should be confirmed with the City.
A good use of the permit wait: finalize your finishes, such as windows, cabinets, flooring and fixtures, while the permit is under review. Items with long lead times can then be ordered on time, and the build doesn’t stall waiting for decisions.

What can add time to the build

The 10-month figure is for a straightforward site. These are the most common reasons a build takes longer:

  • Sloped lots, which may need retaining walls, shoring or more complex foundations
  • Trees that need protection zones or change where and how the house can be built
  • Demolition of an existing house, including the hazardous materials survey that’s required before older homes come down
  • Complex or custom landscaping, such as extensive hardscaping, water features or large planting plans, which is usually scheduled separately
  • Design changes during construction or late finish selections
  • Site surprises, such as poor soil, groundwater or unexpected utility locations
  • Wet-season weather during foundation and roofing work

How to keep your build on schedule

  • Make the major design decisions before the permit application goes in.
  • Choose windows, cabinets and other long-lead items early, and order them on time.
  • Keep changes to a minimum once construction has started.
  • Ask your builder for a written schedule with milestones, and regular updates against it.

Related reading

Please note: This page is general information, not legal, financial or professional advice. The facts, figures, bylaws, fees and code requirements described here were accurate to the best of our knowledge when it was published or last updated. These rules change often and differ from city to city, so some details may have changed since. Before you make decisions, please confirm the current requirements with your city’s planning and building department and with qualified professionals. We’re always happy to help you check what applies to your property.

Planning a new home in Vancouver or Burnaby and want a realistic timeline for your lot?

Talk to Xerox Builders

Mandeep Singh, Builder and Director at Xerox Builders
Written by
Mandeep Singh
Builder & Director, Xerox Builders Ltd. · BC Housing Licensed Residential Builder

Mandeep has been a licensed residential builder in BC for almost 10 years. He builds custom homes, laneway homes, duplexes and multiplexes in Vancouver, Burnaby, Surrey and Delta, and writes these guides so homeowners know what to expect before they build.

Share This Story, Choose Your Platform!

13 Comments

  1. […] How long it takes to build a custom home in Vancouver or Burnaby […]

  2. […] How long it takes to build a custom home in Vancouver or Burnaby […]

  3. […] How long it takes to build a custom home in Vancouver or Burnaby […]

  4. […] to finish (design and permits come before that, as a separate stage). Using the same example as our build timeline article, a 2,500 sq ft home at a mid-range $300 per sq ft costs about $750,000 to build. A draw schedule […]

  5. […] How long it takes to build a custom home, with a cost breakdown […]

  6. […] straightforward lot, the build itself takes about 10 months from foundation to finish. Our guide on how long it takes to build a custom home explains that timeline stage by […]

  7. […] How long it takes to build a custom home in Vancouver or Burnaby […]

  8. […] How long does it take to build a custom home? […]

  9. […] How long it takes to build a custom home in Vancouver or Burnaby […]

  10. […] Planning Your BuildHow Long Does It Take to Build a Custom Home? […]

  11. […] are part of the roughly 10-month build on a straightforward lot that we describe in our guide to how long it takes to build a custom home. When they’re planned well, they fit into that schedule rather than adding to […]

  12. […] How long does it take to build a custom home? […]

  13. […] How long does it take to build a custom home? […]

Comments are closed.