Demolition Before You Rebuild: Permits, Asbestos and Recycling Rules in Vancouver and Burnaby

If you’re replacing an older house with a new home, duplex or multiplex, the old house has to come down first. Most homeowners picture an excavator and a few dumpsters. In Vancouver and Burnaby, demolition is a permitted, inspected process with its own paperwork, deposits and safety rules, and getting it right early keeps the rest of your project on schedule. This guide walks through what happens between “we’re going to rebuild” and a clean, empty lot ready for the new foundation.

Step 1: Find out what’s hiding in the house

Before any demolition or major renovation, the house must be checked for hazardous materials. The biggest concern is asbestos. According to WorkSafeBC, if your home was built before 1990, it’s likely that at least some parts of it contain asbestos, in materials such as drywall, textured ceilings, insulation, vinyl flooring and window putty. The survey (often called a hazardous building materials assessment) is done by a qualified surveyor who takes samples, sends them to a lab and produces a report showing what was found and where. Surveys typically also look at other materials found in older homes, such as lead paint.
Licensing matters: since January 1, 2024, asbestos abatement contractors in B.C. must be licensed by WorkSafeBC, and the workers doing the removal must be trained and certified. WorkSafeBC is clear that anyone you hire to deal with asbestos in your home must be licensed for that work. Ask for the licence before you sign.

Step 2: Abatement, then clearance

If the survey finds asbestos or other hazardous materials, they’re removed by a licensed abatement contractor before the house is knocked down. Doing it in this order keeps fibres out of the air, off the neighbours’ properties and out of the recycling stream. In Vancouver, the City’s demolition process lists two reports: the Hazardous Building Materials Assessment Report and, where required, a Post-Abatement Clearance Report confirming the materials were removed. The original reports must be available on site before machine demolition begins. Abatement can take a meaningful share of the demolition budget and schedule in an older house, so it’s worth getting the survey done early. You’ll get a real scope to price, rather than a surprise after the permit is issued.

Step 3: Apply for the demolition permit

Both cities require a demolition permit, and both attach waste recycling rules to it. The details differ:
City of Vancouver City of Burnaby
Who the recycling rules apply to Houses built before 1950 (voluntary for newer houses) Residential demolitions under the Construction and Demolition Waste Diversion Bylaw
Minimum reuse or recycling 75% of materials by weight; 90% for pre-1950 character houses 70% of demolition waste diverted to an approved facility
Extra salvage rule Heritage-listed or pre-1910 houses: at least 3 tonnes of wood salvaged None listed on the City’s page
Deposit (refundable) Green Demolition deposit of $15,310 $2.25 per sq ft of building demolished, up to $50,000
Non-refundable fee Permit fees per the City’s fee schedule $250 Demolition Waste Permit Fee, plus permit fees
Proof at the end Recycling compliance report with receipts Compliance documents within 90 days of completing demolition
To put Burnaby’s deposit in context: on a 2,000 sq ft house, $2.25 per sq ft works out to a deposit of about $4,500. It’s refunded in full if at least 70% of the materials are diverted. Below that, the refund is reduced in proportion to how close you came to 70%. In Vancouver, you won’t be able to request building inspections for your new home until the recycling compliance report has been submitted, so the paperwork from the old house directly affects the timeline of the new one.

What else the application needs

  • In Burnaby: the residential demolition permit application, an Owner’s Undertaking signed by all owners, an agent authorization if someone applies on your behalf, and two copies of a tree/site plan. The application is reviewed by Engineering, the Tree Bylaw team and Climate Action. Engineering may also take a damage deposit, set after a pre-demolition inspection.
  • In Vancouver: a recycling and reuse plan, the hazardous materials reports, a character assessment where the zoning requires one, and a tree barrier and pre-demolition inspection before the permit is issued.
Trees come first: both cities check trees before demolition. Protected trees need protection barriers in place before machines arrive, and removing one needs its own permit. Damage done during demolition counts the same as damage done during construction.

Step 4: Disconnect the services

Every service to the old house has to be safely cut off before demolition starts. Burnaby’s guide puts this on the owner or contractor: locate and disconnect all services before work begins, and contact BC 1 Call to identify anything buried.
  • Electricity: request removal of the service from BC Hydro.
  • Natural gas: FortisBC handles removal of the gas line; requests can be submitted online.
  • Water and sewer: capping or disconnection at the property line is coordinated with the City.
  • Telecom: cable and phone lines should be removed by their providers.
Utilities book this work on their own schedules, so it’s one of the easiest places to lose weeks. Put the requests in as soon as you know your demolition date.

Step 5: Timing the demolition with your building permit

An empty lot still costs money in property tax, financing and insurance, so ideally the house comes down shortly before the new build can start. In Vancouver, demolition permits have generally been held until the new project reached a certain point in the permit process. The City approved changes in late 2025 that give staff discretion to release demolition permits earlier for some projects, including vacated houses in the R1-1 zone. Whether that applies to your lot is something to confirm with the City when you apply. In Burnaby, all existing structures that need to come down must be removed before construction of the new home starts.

If the house has tenants

If you’re renting out the existing house or a suite, B.C.’s Residential Tenancy Act sets the rules. To end a tenancy for demolition, a landlord must already have all the permits and approvals required by law, give four months’ notice on the official form, and pay the tenant compensation equal to one month’s rent. Tenants have 30 days to dispute the notice. In Vancouver, some redevelopment projects also come with City tenant relocation requirements. Plan this into your timeline early: you can’t serve the notice until the permits are in place.

A practical pre-demolition checklist

  • Order a hazardous materials survey early, especially for a house built before 1990.
  • Check whether any trees on or near the lot are protected.
  • Confirm your house’s age (before or after 1950 matters in Vancouver).
  • Budget for the refundable deposit and the cost of sorting and recycling materials.
  • Hire a licensed abatement contractor and keep every disposal receipt.
  • Book utility disconnections well ahead of the demolition date.
  • If the home is tenanted, line up permits before giving notice.
  • Salvage what’s worth keeping, such as fixtures, cabinets and lumber, before abatement begins.
Once the lot is clear, the new home can begin. On a straightforward lot, the build itself takes about 10 months from foundation to finish. Our guide on how long it takes to build a custom home explains that timeline stage by stage.

Related reading

Please note: This page is general information, not legal, financial or professional advice. The facts, figures, bylaws, fees and code requirements described here were accurate to the best of our knowledge when it was published or last updated. These rules change often and differ from city to city, so some details may have changed since. Before you make decisions, please confirm the current requirements with your city’s planning and building department and with qualified professionals. We’re always happy to help you check what applies to your property.
Replacing an older house in Vancouver or Burnaby and not sure where to start with demolition? Talk to Xerox Builders

Share This Story, Choose Your Platform!

2 Comments

  1. […] Demolition before you rebuild […]

  2. […] Planning Your BuildDemolition Before You Rebuild […]

Comments are closed.

Recent Works

Tags