The rough-in stage is the last chance to see everything inside the walls. After insulation and drywall, pipes, wires and ducts are hidden for the life of the house. A mistake found now costs minutes. The same mistake found after the walls are painted costs days and a lot of money.
These photos are from our current builds at 909 E 64th Ave and 7920 Windsor St in Vancouver. Here’s what we look at before we call for the framing and rough-in inspection.
1. Laundry rough-in
- A recessed laundry box with hot and cold shut-off valves and water hammer arrestors, so pipes don’t bang when the washer valves snap shut.
- The drain set at the right height, with a proper trap below.
- A dedicated dryer outlet on its own circuit.
- PEX water lines secured with clips at every stud, and protected where they pass through framing.
2. Dryer exhaust

The dryer duct is rigid metal, with every joint sealed and the run supported with strapping. We keep it as short and straight as we can. A long or crushed dryer duct collects lint, slows drying and is a fire risk.
3. Bathroom fans and the air barrier

Each bathroom fan housing is mounted solid, and its duct is connected and sealed. Just as important is how the fan meets the poly vapour barrier at the ceiling. The poly has to be cut neatly and taped to the housing. Every hole in the ceiling is a path for warm, moist air to leak into the attic, and those small leaks add up on a blower door test.
4. Plumbing vents and chases


Plumbing vent stacks and ducts run up through framed chases. We check that pipes are strapped and supported, that nothing is pinched or crushed, and that the chase is properly sealed where it passes into the attic.
5. Floor topping over radiant heat

These homes have in-floor radiant heating. Once the heating lines are in, a self-levelling floor topping is poured over them. It gives a flat, solid floor for the finish flooring and spreads the heat evenly across the room. Before the pour we make sure the heating loops are tested and protected, because once the topping sets they can’t be reached.
6. Then the inspections
When the rough-ins are complete, the City and the home warranty provider inspect the framing and rough-ins before any insulation goes in. We walk the whole house ourselves first, room by room, so the inspector finds a clean job.
For the full build sequence, see our step-by-step guide to building a house in Vancouver.