Ground preparation completed before concrete forming
Construction Insights

Topographic Surveys, Posting Plans and Form Surveys Explained for Vancouver and Burnaby Homeowners

Almost every new home in Vancouver and Burnaby starts with a land surveyor. Before an architect or designer can finalize a site plan, and before the City will accept a building permit application, someone has to measure exactly where your property lines are, how the ground slopes, which trees stand where and what sits under the street out front. Surveys come up again during construction, when the foundation forms are checked against the approved plans.

This guide explains the surveys a typical new house, duplex, laneway home or small multiplex needs, what the City of Vancouver and the City of Burnaby ask for, and how to keep surveys from holding up your project.

In short: both cities require a survey plan signed and sealed by a BC Land Surveyor (BCLS) with your building permit application. Vancouver’s checklist for a new one- or two-family home asks for a survey sealed less than 6 months before you apply; Burnaby’s checklist for new R1 homes accepts a topographical survey and posting plan up to 12 months old. In Burnaby, a posting survey and a foundation form survey must also be on site for the foundation formwork inspection. Check the current checklist for your project type before you order a survey.

Who does surveys in BC

Legal surveys in British Columbia are done by BC Land Surveyors, who are members of the Association of British Columbia Land Surveyors. Under the Land Surveyors Act, only a BCLS may establish or re-establish property boundaries. The Land Title and Survey Authority (LTSA), which runs the land title and survey system, refers homeowners who need a survey or have a boundary question directly to a BC Land Surveyor.

That matters because your lot’s legal boundaries are not always where the fence, hedge or old driveway suggests. Setbacks, height limits and floor area are all calculated from the true property lines, so the whole design depends on getting them right.

The surveys you’re likely to need

SurveyWhenWhat it does
Topographic (site) surveyBefore design is finalized and with the permit applicationShows property lines, existing grades and elevations, trees, structures, easements and street and lane features
Posting plan / posting surveyApplication and before foundationsConfirms that survey posts or pins mark each lot corner, so the house can be set out accurately
Engineering surveyFor the City’s engineering pre-application reviewGives the City detail on street, lane and utility features for servicing, driveways and grades
Foundation form surveyAfter foundation forms are built, before concrete is pouredConfirms the foundation is in the approved location, so setbacks are met before it’s too late to adjust

Your permit conditions, your lender or your warranty provider may ask for more, such as a survey confirming building height or final location. Ask early which surveys apply to your project.

What a topographic survey shows

The topographic survey is the base drawing for your whole project. The cities’ checklists ask it to show, among other things:

  • Legal information: the civic address, legal description and parcel identifier (PID), lot dimensions and area, and the survey posts or pins at the corners.
  • Registered charges: easements, rights-of-way, encroachments and any lane dedications that affect where you can build.
  • Existing grades: elevations at the lot corners and around the site, at retaining walls and a few metres onto neighbouring lots. Burnaby requires original grades, not grades altered by fill or excavation.
  • Street and lane features: curbs, gutters, sidewalks, catch basins, manholes, hydrants, poles and lane or street centreline elevations.
  • Trees: trees and stumps 20 cm (about 8 inches) in diameter or larger, including relevant trees on neighbouring lots and City land. Burnaby asks for numbered tree tags, species, drip line and base elevation for each tagged tree.
  • Neighbouring setbacks: where front yard averaging applies, the setbacks of adjacent houses, which can decide how far back your home must sit.

Your designer uses these grades to calculate building height, basement depth and floor area, and your arborist and geotechnical engineer rely on the same drawing.

Vancouver requirements

For an outright one- or two-family home, the City of Vancouver’s building permit checklist asks for:

  • A survey plan prepared by a BC Registered Land Surveyor, certified correct and signed and sealed less than 6 months before application. Vancouver’s legal survey checklist lists what it must show, including the ultimate property line, setbacks of the two adjacent sites on each side, grades and trees under the Protection of Trees By-law.
  • An updated posting plan for all new construction, in addition to the surveys.
  • A building grades plan if City staff decide one is needed, and an additional survey for the Engineering Department’s pre-application for engineering services.

Where the City sets building grades, it has its own survey standards, including tight accuracy requirements and coverage of the street and lane beyond your lot. The City notes that surveys certified by a BCLS are generally reviewed faster.

Burnaby requirements

Burnaby’s submission checklist for new single family and duplex homes under R1 zoning asks for a topographical survey and a posting or subdivision plan, each signed, sealed and not more than 12 months old, plus a current land title search for each parcel. Burnaby’s topographical survey requirements add some local specifics:

  • A BC Land Surveyor must seal, sign and date the plan, using the Burnaby Integrated Datum and a City survey monument as the elevation reference.
  • Street and lane infrastructure must be shown at least to the centreline and out to the farthest utility connection point.
  • Where front yard averaging applies, the surveyor calculates the average setback.

Burnaby also requires Engineering pre-application approval before a building application is submitted, and the topographical survey is part of that package. The City says complete submissions typically take about 15 business days to review (approximate). During construction, Burnaby’s inspection guide requires a posting survey and a foundation form survey, both by a BC Land Surveyor, to be on site for the foundation formwork inspection.

Watch the expiry date: because surveys must be recent (6 months in Vancouver, 12 months in Burnaby for these checklists), ordering one too early can mean paying for an update. Order it once you’re serious about the lot and ready to start design, and confirm the current age limit with the City first.

How surveys fit into your timeline

A sensible order for most projects:

  1. Pull the title. A land title search shows registered easements, covenants and rights-of-way. Existing survey plans for many lots can be found through the LTSA, and basic parcel information through ParcelMap BC.
  2. Order the topographic survey as one of the first steps of design, together with the arborist and geotechnical work.
  3. Design to the survey. Setbacks, height and floor area are worked out from it, so avoid designing from old plans or assumptions.
  4. Submit the survey and posting plan with your permit application while they are still within the City’s age limit.
  5. Book the form survey as soon as foundation forms are built, so the surveyor’s results are on site before the formwork inspection and the pour.

Design, survey and permit work is a separate stage before construction. Once construction starts on a straightforward lot (relatively flat, with no significant trees and little slope), building a custom home typically takes about 10 months from foundation to finish (approximate).

Common survey issues to plan for

  • Missing corner pins: if posts are gone, the surveyor may need to re-establish them and file a posting plan.
  • Encroachments: a neighbour’s fence, garage or retaining wall over the line can complicate demolition, excavation and design.
  • Protected trees: trees picked up on the survey feed directly into tree permits and arborist reports.
  • Steep or uneven grades: average grade calculations affect allowable height and basement depth, so accurate elevations matter.
  • Form survey surprises: a foundation that is slightly out of position is far easier to fix in formwork than after concrete is poured.

Related reading

Please note: This page is general information, not legal, financial or professional advice. The facts, figures, bylaws, fees and code requirements described here were accurate to the best of our knowledge when it was published or last updated. These rules change often and differ from city to city, so some details may have changed since. Before you make decisions, please confirm the current requirements with your city’s planning and building department and with qualified professionals. We’re always happy to help you check what applies to your property.

Not sure which surveys your lot needs before you apply for a permit?

Talk to Xerox Builders

Mandeep Singh, Builder and Director at Xerox Builders
Written by
Mandeep Singh
Builder & Director, Xerox Builders Ltd. · BC Housing Licensed Residential Builder

Mandeep has been a licensed residential builder in BC for almost 10 years. He builds custom homes, laneway homes, duplexes and multiplexes in Vancouver, Burnaby, Surrey and Delta, and writes these guides so homeowners know what to expect before they build.

Share This Story, Choose Your Platform!

Recent Works

Tags