When you build a new home, duplex, laneway home or multiplex, the City collects a set of one-time charges before it issues your building permit. They pay for the roads, water and sewer mains, parks and community facilities that growth needs. Homeowners often call them all “DCCs,” but in practice they are several separate charges set by different bodies, and together they can add tens of thousands of dollars per home to a project.

This guide explains what each charge is, how Vancouver and Burnaby apply them in 2026, roughly what they cost and how to plan for them.

In short: development charges are paid once, as a condition of building permit issuance (or subdivision approval), at the rate in effect on that day. In Burnaby, the City’s own DCC and ACC for a low-density home were listed at about $81,833 per primary unit, before regional, TransLink and school charges. In Vancouver, the City charges per square foot of floor area, plus Metro Vancouver’s regional charge per unit. All figures here are approximate; ask the City for an estimate for your project.

The charges that make up the total

For a typical residential project in Vancouver or Burnaby, the bill can include:

ChargeSet byWhat it pays for
City Development Cost Charges (DCCs) — called Development Cost Levies (DCLs) in VancouverThe CityRoads, water, sewer, drainage and park land needed for growth
Amenity Cost Charges (ACCs)The CityCommunity amenities such as community centres, libraries and child care
Regional DCCsMetro Vancouver (collected by the City)Regional water, liquid waste (sewer) and park land
Regional Transportation DCCTransLink (collected by the City)Transit projects in TransLink’s investment plan
School Site Acquisition ChargeSchool district (collected by the City)Land for new schools

These are separate from building permit fees, plan review fees and the water and sewer connection fees covered in our servicing guide. Amenity Cost Charges are newer: the Province allowed municipalities to adopt them in 2023, Burnaby brought them in on July 1, 2024 and Vancouver’s took effect on September 30, 2026.

How it works in Burnaby

Burnaby charges its DCCs and ACCs per unit, by density category. The City’s development funding page lists these rates (effective July 1, 2024):

CategoryCity DCCCity ACCTotal
Low density residential (per primary unit or lot, includes single-family)about $54,870about $26,963about $81,833
Medium density residential (per unit, includes townhouses)about $37,423about $18,874about $56,297
High density residential (per apartment unit)about $25,360about $13,481about $38,841

A few points to know:

  • Small-scale multiplexes and laneway homes have their own guidance from the City, and the category that applies depends on the project. Our earlier Burnaby articles used the medium-density rate for laneway homes; confirm with the City’s fee estimator for your design.
  • Burnaby amended its ACC bylaw effective July 28, 2026, so check that the rates you’re quoted are current.
  • Credit for a demolished home is generally given, so replacing one house with one house costs less than adding new units; ask the City how credits apply to your lot.
  • Regional, TransLink and School District 41 charges are added on top. Burnaby lots fall in Metro Vancouver’s Vancouver or Fraser sewerage area depending on location, which changes the regional rate slightly.
  • Installment payments may be available in some circumstances, under a provincial regulation that was amended for charges imposed from January 1, 2026.

How it works in Vancouver

Vancouver charges its Development Cost Levies by floor area rather than per unit. For residential projects at or below 1.2 FSR, which covers most houses, duplexes, multiplexes and laneway homes, the City’s DCL bulletin lists a combined city-wide and utilities levy of $8.92 per square foot (rates approved for September 30, 2024). In December 2025, Council approved a temporary 20% reduction to the city-wide, utilities and area-specific DCLs, and kept it in its July 2026 financing growth update, so the rate you pay today should be lower. Confirm the current figure in the bulletin.

On top of that, Vancouver’s new Amenity Cost Charge applies to applications submitted on or after September 30, 2026:

Residential densityACC from Sept 30, 2026Sept 30, 2027
At or below 1.2 FSR and laneway houses$2.32 / sq ft$2.39 / sq ft
Above 1.2 to 1.5 FSR$5.00 / sq ft$5.15 / sq ft
Above 1.5 FSR$5.00 / sq ft$10.30 / sq ft

Vancouver exempts alterations that add no floor area, small residential units of 320 sq ft or less from DCLs, and additions under 500 sq ft to existing buildings with fewer than four units. For the ACC, a new building whose floor area does not exceed the building it replaces is exempt. Applications already in stream before a rate change are generally protected if the building permit is issued within 12 months.

Rough example (illustrative only): a new 2,500 sq ft home on a Vancouver lot at the bulletin’s $8.92 DCL rate would be about $22,300 in City DCLs before the temporary 20% reduction (about $17,800 after it), plus about $5,800 in ACC if the application was made after September 30, 2026, plus Metro Vancouver and TransLink charges per unit. Your actual figure depends on floor area, credits and the rates on the day your permit is issued.

Regional and transit charges

Metro Vancouver collects regional water, liquid waste and park land DCCs through each city. On July 24, 2026, its board rolled back the 2026 increases to 2025 levels. For a single-family lot in the Vancouver Sewerage Area, the regional total dropped from about $29,196 to about $21,941 per unit for permits issued from that date, with about $19,874 per townhouse and $13,392 per apartment. Rates are scheduled to rise again on January 1, 2027 (to about $28,322 for a single-family lot), so permit timing matters.

TransLink‘s regional transportation DCC for 2026 is about $3,416 per single-family dwelling and $2,837 per duplex or townhouse unit. It doesn’t apply to units of 29 m² or less or to permits for work valued at $50,000 or less.

What the provincial rules allow

Under BC’s Local Government Act, developments with fewer than four self-contained homes are exempt from DCCs unless the city’s bylaw says otherwise, and many Metro Vancouver bylaws now charge them. Cities can also waive or reduce charges for not-for-profit and certain affordable rental housing. In June 2026, the federal and provincial governments announced funding intended to cut development charges on multi-unit housing by up to 50% in “priority communities,” but as of Burnaby’s June 2026 statement, which communities qualify and when it starts were not yet known.

What this means for your project

  • Budget for charges as their own line. They are separate from construction cost, which typically runs about $250 to $350 per square foot for a mid-range new home in Vancouver or Burnaby (approximate, with no upper limit for premium finishes).
  • Plan for cash at permit issuance. Charges are due before the permit is issued, so check early with your lender how they will be funded.
  • Watch the dates. Rates change on set dates, and in-stream protection usually depends on when you apply and when the permit is issued.
  • Ask about credits and waivers. Demolition credits, small-unit exemptions and affordable housing waivers can change the total significantly.
  • Get a written estimate. Both cities can estimate charges for a specific design; ask early, before the unit mix is final.

Related reading

Please note: This page is general information, not legal, financial or professional advice. The facts, figures, bylaws, fees and code requirements described here were accurate to the best of our knowledge when it was published or last updated. These rules change often and differ from city to city, so some details may have changed since. Before you make decisions, please confirm the current requirements with your city’s planning and building department and with qualified professionals. We’re always happy to help you check what applies to your property.

Wondering how development charges will affect the budget for your lot and unit mix?

Talk to Xerox Builders

Mandeep Singh, Builder and Director at Xerox Builders
Written by
Mandeep Singh
Builder & Director, Xerox Builders Ltd. · BC Housing Licensed Residential Builder

Mandeep has been a licensed residential builder in BC for almost 10 years. He builds custom homes, laneway homes, duplexes and multiplexes in Vancouver, Burnaby, Surrey and Delta, and writes these guides so homeowners know what to expect before they build.

Share This Story, Choose Your Platform!

2 Comments

  1. […] Permits and City charges: permit fees and one-time development charges, paid before the building permit is issued. See development cost charges explained. […]

  2. […] Development cost charges explained […]

Comments are closed.

Recent Works

Tags